Message ID: 0000000000000000000000158_003


ID259
Market Participant NameEnergie Wasser Bern
Market Participant Typeace
Market Participant IDA00017933.DE
Message ID0000000000000000000000158_003
Event StatusActive
Type of EventProduction unavailability
Event Start2025-08-01 07:00:00
Event Stop2025-09-30 17:00:00
Type of UnavailabilityPlanned
Publication date/time2024-10-15 10:13:38
Unit of MeasurementMW
Unavailable Capacity43.50000
Available Capacity0.00000
Installed Capacity43.50000
Reason of the UnavailabilityRevision (Umbau LRV)
Remarks
Fuel TypeFossil Gas
Bidding Zone10YCH-SWISSGRIDZ
Affected Asset NameGUD Energiezentrale Forsthaus
Affected Asset EIC12W-0000001596-S
StatusSaved and Published
Created at15.10.2024 10:13:38
Updated at15.10.2024 10:13:38
Showing 1-3 of 3 items.
IDMessage IDStatusMarket Participant NameEvent StatusType of EventEvent StartEvent StopType of UnavailabilityPublication date/timeUnit of MeasurementUnavailable CapacityAvailable CapacityInstalled CapacityFuel TypeBidding ZoneAffected Asset Name
 
 
 
 
 
×
×
 
×
 
 
2590000000000000000000000158_003PublishedEnergie Wasser BernActiveProduction unavailability2025-08-01 07:00:002025-09-30 17:00:00Planned2024-10-15 10:13:38MW43.500000.0000043.50000Fossil Gas10YCH-SWISSGRIDZGUD Energiezentrale Forsthaus
2580000000000000000000000158_002PublishedEnergie Wasser BernDismissedProduction unavailability2025-08-10 07:00:002025-09-18 17:00:00Planned2024-10-15 10:12:08MW43.500000.0000043.50000Fossil Gas10YCH-SWISSGRIDZGUD Energiezentrale Forsthaus
1580000000000000000000000158_001PublishedEnergie Wasser BernDismissedProduction unavailability2025-08-10 07:00:002025-09-18 17:00:00Planned2023-06-19 05:53:02MW43.500000.0000043.50000Fossil Gas10YCH-SWISSGRIDZGUD Energiezentrale Forsthaus