| ID | 438 |
|---|---|
| Market Participant Name | Zonnestroom Project 3 B.V. |
| Market Participant Type | ace |
| Market Participant ID | A0025868Y.NL |
| Message ID | 0000000000000000000000431_002 |
| Event Status | Active |
| Type of Event | Production unavailability |
| Event Start | 2026-03-05 09:00:00 |
| Event Stop | 2026-03-30 09:00:00 |
| Type of Unavailability | Planned |
| Publication date/time | 2026-03-25 14:41:31 |
| Unit of Measurement | MW |
| Unavailable Capacity | 11.00000 |
| Available Capacity | 14.00000 |
| Installed Capacity | 25.00000 |
| Reason of the Unavailability | Turning on the Solar Ground Park in Test Phase |
| Remarks | Turning on 32 inverters (Field 1 & 2) - 55% of total production (10,5 MWA) |
| Fuel Type | Solar |
| Bidding Zone | 10YNL----------L |
| Affected Asset Name | Heldair2_PV |
| Affected Asset EIC | 49W0000000002108 |
| Status | Saved and Published |
| Created at | 25.03.2026 14:41:31 |
| Updated at | 25.03.2026 14:41:31 |