Showing 21-40 of 74 items.
 IDMessage IDMarket Participant NameEvent StatusType of EventEvent StartEvent StopType of UnavailabilityPublication date/timeUnit of MeasurementUnavailable CapacityAvailable CapacityTechnical CapacityBalancing Zone 1Affected Asset Name
 
 
 
×
×
 
×
 
 
690000000000000000000000038_003MET Speicher GmbHDismissedStorage unavailability2022-10-09 06:00:002022-10-17 18:00:00Planned2022-05-27 07:27:36GWh1485.000000.000001485.0000037Y005053MH0000RUGS Etzel-ESE MET
680000000000000000000000068_001MET Speicher GmbHInactiveInjection unavailability2022-05-23 06:00:002022-05-24 06:00:00Planned2022-05-20 07:18:54kWh/h639.00000333.00000972.0000037Y005053MH0000RUGS Reckrod
670000000000000000000000064_002MET Speicher GmbHInactiveInjection unavailability2022-05-19 06:00:002022-05-21 06:00:00Planned2022-05-19 14:09:03kWh/h491000.00000483000.00000974000.0000037Y005053MH0000RUGS Reckrod
660000000000000000000000060_002MET Speicher GmbHDismissedInjection unavailability2022-09-27 06:00:002022-10-18 14:00:00Planned2022-05-19 14:04:59kWh/h127737.00000127737.00000255474.0000021YNL----TTF---1UGS Etzel-ESE MET
650000000000000000000000059_002MET Speicher GmbHDismissedWithdrawal unavailability2022-09-27 06:00:002022-10-18 14:00:00Planned2022-05-19 14:04:13kWh/h209488.00000209489.00000418977.0000021YNL----TTF---1UGS Etzel-ESE MET
640000000000000000000000064_001MET Speicher GmbHDismissedInjection unavailability2022-05-19 06:00:002022-05-20 06:00:00Planned2022-05-18 13:23:03kWh/h491000.00000483000.00000974000.0000037Y005053MH0000RUGS Reckrod
630000000000000000000000063_001MET Speicher GmbHInactiveInjection unavailability2022-05-18 14:00:002022-05-19 06:00:00Planned2022-05-17 14:15:59kWh/h479000.00000500000.00000979000.0000037Y005053MH0000RUGS Reckrod
620000000000000000000000062_001MET Speicher GmbHInactiveInjection unavailability2022-05-18 06:00:002022-05-18 14:00:00Planned2022-05-17 14:14:20kWh/h979000.000000.00000979000.0000037Y005053MH0000RUGS Reckrod
610000000000000000000000057_002MET Speicher GmbHInactiveInjection unavailability2022-05-17 00:00:002022-05-18 06:00:00Planned2022-05-17 14:12:06kWh/h754000.00000225000.00000979000.0000037Y005053MH0000RUGS Reckrod
600000000000000000000000060_001MET Speicher GmbHDismissedInjection unavailability2022-09-27 06:00:002022-10-18 14:00:00Planned2022-05-16 15:32:43kWh/h127737.00000127737.00000255474.0000021YNL----TTF---1UGS Etzel-ESE MET
590000000000000000000000059_001MET Speicher GmbHDismissedWithdrawal unavailability2022-09-27 06:00:002022-10-18 14:00:00Planned2022-05-16 15:30:18kWh/h209488.00000209489.00000418977.0000021YNL----TTF---1UGS Etzel-ESE MET
580000000000000000000000058_001MET Speicher GmbHDismissedInjection unavailability2022-10-10 08:00:002022-12-16 16:00:00Planned2022-05-16 15:08:19kWh/h640000.000001275000.000001915000.0000037Y005053MH0000RUGS Etzel-ESE MET
570000000000000000000000057_001MET Speicher GmbHDismissedInjection unavailability2022-05-17 00:00:002022-05-18 00:00:00Planned2022-05-16 10:15:11kWh/h754000.00000225000.00000979000.0000037Y005053MH0000RUGS Reckrod
560000000000000000000000038_002MET Speicher GmbHDismissedStorage unavailability2022-10-07 06:00:002022-10-15 18:00:00Planned2022-05-16 07:16:06GWh1485.000000.000001485.0000037Y005053MH0000RUGS Etzel-ESE MET
550000000000000000000000055_001MET Speicher GmbHInactiveInjection unavailability2022-05-16 00:00:002022-05-17 00:00:00Planned2022-05-13 12:49:10kWh/h679000.00000300000.00000979000.0000037Y005053MH0000RUGS Reckrod
540000000000000000000000051_004MET Speicher GmbHInactiveInjection unavailability2022-05-13 00:00:002022-05-16 00:00:00Planned2022-05-13 12:45:08kWh/h529000.00000450000.00000979000.0000037Y005053MH0000RUGS Reckrod
530000000000000000000000051_003MET Speicher GmbHDismissedInjection unavailability2022-05-13 00:00:002022-05-14 00:00:00Planned2022-05-12 13:09:45kWh/h529000.00000450000.00000979000.0000037Y005053MH0000RUGS Reckrod
520000000000000000000000051_002MET Speicher GmbHDismissedInjection unavailability2022-05-13 08:00:002022-05-13 16:00:00Planned2022-05-12 13:07:50kWh/h979000.000000.00000979000.0000037Y005053MH0000RUGS Reckrod
510000000000000000000000051_001MET Speicher GmbHDismissedInjection unavailability2022-05-13 08:00:002022-05-13 16:00:00Planned2022-05-12 13:04:05kWh/h979000.000000.00000979000.0000037Y005053MH0000RUGS Reckrod
500000000000000000000000036_002MET Speicher GmbHInactiveWithdrawal unavailability2022-03-17 18:00:002022-05-20 16:00:00Planned2022-04-28 13:07:34kWh/h95750.000001819250.000001915000.0000037Y005053MH0000RUGS Etzel-ESE MET
Showing 1-20 of 201 items.
 IDMessage IDMarket Participant NameEvent StatusType of EventEvent StartEvent StopType of UnavailabilityPublication date/timeUnit of MeasurementUnavailable CapacityAvailable CapacityInstalled CapacityFuel TypeBidding ZoneAffected Asset Name
 
 
 
×
×
 
×
 
 
 
2810000000000000000000000275_003Ineos oxide utilities NVActiveProduction unavailability2024-11-08 12:00:002024-11-27 00:00:00Planned2024-11-18 12:09:25MW71.5000067.50000139.00000Fossil Gas10X1001A1001A094INESCO WKK
2800000000000000000000000276_003Ineos oxide utilities NVInactiveProduction unavailability2024-11-08 18:00:002024-11-15 18:50:00Planned2024-11-15 17:45:13MW92.5000046.50000139.00000Fossil Gas10X1001A1001A094INESCO WKK
2790000000000000000000000276_002Ineos oxide utilities NVDismissedProduction unavailability2024-11-08 18:00:002024-11-16 00:00:00Planned2024-11-06 09:12:17MW92.5000046.50000139.00000Fossil Gas10X1001A1001A094INESCO WKK
2780000000000000000000000275_002Ineos oxide utilities NVDismissedProduction unavailability2024-11-08 12:00:002024-11-23 00:00:00Planned2024-11-05 14:58:29MW71.5000067.50000139.00000Fossil Gas10X1001A1001A094INESCO WKK
2770000000000000000000000277_001Ineos oxide utilities NVActiveProduction unavailability2024-11-29 00:00:002024-12-13 00:00:00Planned2024-11-05 14:58:06MW71.5000067.50000139.00000Fossil Gas10X1001A1001A094INESCO WKK
2760000000000000000000000276_001Ineos oxide utilities NVDismissedProduction unavailability2024-11-09 00:00:002024-11-16 00:00:00Planned2024-11-05 14:56:15MW92.5000046.50000139.00000Fossil Gas10X1001A1001A094INESCO WKK
2750000000000000000000000275_001Ineos oxide utilities NVDismissedProduction unavailability2024-11-08 12:00:002024-11-23 00:00:00Planned2024-11-05 14:54:41MW71.5000071.50000139.00000Fossil Gas10X1001A1001A094INESCO WKK
2740000000000000000000000270_003Ineos oxide utilities NVInactiveProduction unavailability2024-10-31 21:00:002024-11-05 12:00:00Unplanned2024-11-04 16:02:21MW76.0000063.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
2730000000000000000000000270_002Ineos oxide utilities NVDismissedProduction unavailability2024-10-31 21:00:002024-11-05 00:00:00Unplanned2024-11-04 15:10:07MW76.0000063.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
2720000000000000000000000263_007Ineos oxide utilities NVDismissedProduction unavailability2024-10-18 21:20:002024-10-30 10:30:00Unplanned2024-10-30 09:36:10MW76.0000063.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
2710000000000000000000000263_006Ineos oxide utilities NVDismissedProduction unavailability2024-10-18 21:20:002024-10-30 10:30:00Unplanned2024-10-30 09:09:18MW76.0000063.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
2700000000000000000000000270_001Ineos oxide utilities NVDismissedProduction unavailability2024-10-31 21:00:002024-11-04 00:00:00Unplanned2024-10-30 09:08:02MW76.0000063.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
2690000000000000000000000269_001Ineos oxide utilities NVInactiveProduction unavailability2024-10-30 10:30:002024-10-31 21:00:00Unplanned2024-10-30 09:03:28MW139.000000.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
2680000000000000000000000263_005Ineos oxide utilities NVDismissedProduction unavailability2024-10-18 21:20:002024-11-04 00:00:00Unplanned2024-10-22 09:13:21MW76.0000063.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
2670000000000000000000000263_004Ineos oxide utilities NVDismissedProduction unavailability2024-10-18 21:20:002024-10-25 00:00:00Unplanned2024-10-22 07:53:36MW76.0000063.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
2660000000000000000000000263_003Ineos oxide utilities NVDismissedProduction unavailability2024-10-18 21:20:002024-10-24 00:00:00Unplanned2024-10-21 09:57:59MW76.0000063.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
2650000000000000000000000262_002Ineos oxide utilities NVDismissedProduction unavailability2024-10-18 21:20:002024-10-22 23:55:00Unplanned2024-10-19 11:10:38MW96.0000043.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
2640000000000000000000000263_002Ineos oxide utilities NVDismissedProduction unavailability2024-10-18 21:20:002024-10-22 23:55:00Unplanned2024-10-19 05:32:26MW76.0000063.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
2630000000000000000000000263_001Ineos oxide utilities NVDismissedProduction unavailability2024-10-18 21:20:002024-10-22 23:55:00Unplanned2024-10-18 19:23:35MW96.0000043.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
2620000000000000000000000262_001Ineos oxide utilities NVDismissedProduction unavailability2024-10-18 21:20:002024-10-22 23:55:00Unplanned2024-10-18 19:23:34MW96.0000043.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
Showing 1-5 of 5 items.
 IDMessage IDMarket Participant NameEvent StatusEvent StartEvent StopPublication date/timeRemarks
 
 
×
×
×
140000000000000000000000012_002Swissgrid AGDismissed2024-02-20 04:00:002024-02-21 19:00:002024-02-14 17:40:34Information: At the request of the Swiss supervisory authority ElCom, Swissgrid (Swiss TSO) will coordinate an energy reserve test with hydroelectric reserve, thermal reserve power plant and emergency power groups between 20/02/2024 04:00 and 21/02/2024 19:00. During this period, an excess of approx. 1’452.80 MWh will be fed into the grid, which may have an impact on prices.
130000000000000000000000013_001Swissgrid AGInactive2024-02-20 04:00:002024-02-21 19:00:002024-02-14 17:27:59UPDATE (reduced amount of energy)
Information: At the request of the Swiss supervisory authority ElCom, Swissgrid (Swiss TSO) will coordinate an energy reserve test with hydroelectric reserve, thermal reserve power plant and emergency power groups between 20/02/2024 04:00 and 21/02/2024 19:00. During this period, an excess of approx. 966.5 MWh will be fed into the grid, which may have an impact on prices.
120000000000000000000000012_001Swissgrid AGDismissed2024-02-20 04:00:002024-02-21 19:00:002024-02-13 15:04:43Information: At the request of the Swiss supervisory authority ElCom, Swissgrid (Swiss TSO) will coordinate an energy reserve test with hydroelectric reserve, thermal reserve power plant and emergency power groups between 20/02/2024 04:00 and 21/02/2024 19:00. During this period, an excess of approx. 1’452.80 MWh will be fed into the grid, which may have an impact on prices.
110000000000000000000000011_001Swissgrid AGInactive2022-12-01 00:00:002023-05-15 23:55:002022-10-25 13:42:46Information about the Swiss hydropower reserve administrated by Swissgrid according to the Swiss Ordinance on the establishment of a hydropower reserve is available on our website. Today Swissgrid procured a total energy volume of 400 GWh for the coming winter period (01 December 2022 until 15 May 2023). See https://www.swissgrid.ch/en/home/newsroom/newsfeed/20221025-01.html
100000000000000000000000010_001Swissgrid AGInactive2020-12-21 00:00:002022-01-05 00:00:002021-12-23 09:12:31A temporary price Cap and Floor was introduced for Swiss offers in TERRE. From delivery period of 21.12.2020 00:00 onwards the offers prices in TERRE from Switzerland have been limited to +/- 999 EUR/MWh.

The temporary price Cap and Floor will be removed as of 05.01.2022. For delivery periods from 05.01.2022 00:00 onwards, the relevant price Cap and Floor will be +/- 9’999 EUR/MWh.