 IDMessage IDMarket Participant NameEvent StatusType of EventEvent StartEvent StopType of UnavailabilityPublication date/timeUnit of MeasurementUnavailable CapacityAvailable CapacityTechnical CapacityBalancing Zone 1Affected Asset Name
 
 
 
×
×
 
×
 
 
340000000000000000000000034_001MET Speicher GmbHInactiveWithdrawal unavailability2022-01-17 08:00:002022-03-25 16:00:00Planned2022-01-03 16:52:47kWh/h631950.000001283050.000001915000.0000037Y005053MH0000RUGS Etzel-ESE MET
710000000000000000000000058_002MET Speicher GmbHInactiveInjection unavailability2022-10-10 08:00:002022-12-16 16:00:00Planned2022-09-23 09:17:44kWh/h752000.000001505000.000002257000.0000037Y005053MH0000RUGS Etzel-ESE MET
320000000000000000000000032_001MET Speicher GmbHInactiveInjection unavailability2022-01-03 08:00:002022-01-16 16:00:00Planned2022-01-03 16:51:54kWh/h750750.000001524250.000002275000.0000037Y005053MH0000RUGS Etzel-ESE MET
330000000000000000000000033_001MET Speicher GmbHInactiveInjection unavailability2022-01-17 08:00:002022-03-25 16:00:00Planned2022-01-03 16:52:30kWh/h750750.000001524250.000002275000.0000037Y005053MH0000RUGS Etzel-ESE MET
770000000000000000000000077_001MET Speicher GmbHDismissedWithdrawal unavailability2023-03-15 08:00:002023-04-04 16:00:00Planned2022-11-11 15:55:50kWh/h155500.000001759500.000001915000.0000037Y005053MH0000RUGS Etzel-ESE MET
830000000000000000000000077_002MET Speicher GmbHInactiveWithdrawal unavailability2023-03-17 08:00:002023-04-04 16:00:00Planned2022-11-16 16:40:32kWh/h155500.000001759500.000001915000.0000037Y005053MH0000RUGS Etzel-ESE MET
360000000000000000000000036_001MET Speicher GmbHDismissedWithdrawal unavailability2022-03-17 18:00:002022-05-13 16:00:00Planned2022-01-03 16:53:15kWh/h95750.000001819250.000001915000.0000037Y005053MH0000RUGS Etzel-ESE MET
500000000000000000000000036_002MET Speicher GmbHInactiveWithdrawal unavailability2022-03-17 18:00:002022-05-20 16:00:00Planned2022-04-28 13:07:34kWh/h95750.000001819250.000001915000.0000037Y005053MH0000RUGS Etzel-ESE MET
750000000000000000000000075_001MET Speicher GmbHDismissedWithdrawal unavailability2023-02-10 08:00:002023-03-15 08:00:00Planned2022-11-11 15:55:15kWh/h85500.000001829500.000001915000.0000037Y005053MH0000RUGS Etzel-ESE MET
810000000000000000000000075_002MET Speicher GmbHInactiveWithdrawal unavailability2023-02-10 08:00:002023-03-17 08:00:00Planned2022-11-16 16:37:23kWh/h85500.000001829500.000001915000.0000037Y005053MH0000RUGS Etzel-ESE MET
790000000000000000000000079_001MET Speicher GmbHDismissedWithdrawal unavailability2023-04-04 16:00:002023-05-24 16:00:00Planned2022-11-11 15:56:21kWh/h70000.000001845000.000001915000.0000037Y005053MH0000RUGS Etzel-ESE MET
850000000000000000000000079_002MET Speicher GmbHInactiveWithdrawal unavailability2023-04-04 16:00:002023-05-09 16:00:00Planned2022-11-16 16:41:38kWh/h70000.000001845000.000001915000.0000037Y005053MH0000RUGS Etzel-ESE MET
230000000000000000000000023_001astora GmbH and Co. KGInactiveInjection unavailability2021-10-19 16:00:002021-10-26 16:00:00Planned2021-05-28 08:11:06KWh/h2066166.000002066166.000004132332.0000037Y701133MH0000PUGS Haidach - Astora - Injection
240000000000000000000000022_002astora GmbH and Co. KGInactiveInjection unavailability2021-10-26 16:00:002021-11-17 22:00:00Planned2021-05-28 08:18:49KWh/h1033083.000003099249.000004132332.0000037Y701133MH0000PUGS Haidach - Astora - Injection
Showing 141-145 of 145 items.
 IDMessage IDMarket Participant NameEvent StatusType of EventEvent StartEvent StopType of UnavailabilityPublication date/timeUnit of MeasurementUnavailable CapacityAvailable CapacityInstalled CapacityFuel TypeBidding ZoneAffected Asset Name
 
 
 
×
×
 
×
 
 
 
1070000000000000000000000106_002Ineos oxide utilities NVDismissedProduction unavailability2023-02-12 22:35:002023-02-13 23:55:00Unplanned2023-02-13 08:26:34MW9.00000130.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
1340000000000000000000000134_001Ineos oxide utilities NVDismissedProduction unavailability2023-05-04 20:10:002023-05-05 13:00:00Unplanned2023-05-04 18:28:46MW4.50000134.50000139.00000Fossil Gas10X1001A1001A094INESCO WKK
1350000000000000000000000134_002Ineos oxide utilities NVDismissedProduction unavailability2023-05-04 20:10:002023-05-15 00:00:00Unplanned2023-05-05 08:01:17MW4.50000134.50000139.00000Fossil Gas10X1001A1001A094INESCO WKK
1360000000000000000000000134_003Ineos oxide utilities NVInactiveProduction unavailability2023-05-04 20:10:002023-05-20 00:00:00Unplanned2023-05-12 08:58:37MW4.50000134.50000139.00000Fossil Gas10X1001A1001A094INESCO WKK
1050000000000000000000000105_001Ineos oxide utilities NVInactiveProduction unavailability2023-02-05 12:15:002023-02-07 00:00:00Unplanned2023-02-05 11:21:51MW0.00000139.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
Showing 1-5 of 5 items.
 IDMessage IDMarket Participant NameEvent StatusEvent StartEvent StopPublication date/timeRemarks
 
 
×
×
×
140000000000000000000000012_002Swissgrid AGDismissed2024-02-20 04:00:002024-02-21 19:00:002024-02-14 17:40:34Information: At the request of the Swiss supervisory authority ElCom, Swissgrid (Swiss TSO) will coordinate an energy reserve test with hydroelectric reserve, thermal reserve power plant and emergency power groups between 20/02/2024 04:00 and 21/02/2024 19:00. During this period, an excess of approx. 1’452.80 MWh will be fed into the grid, which may have an impact on prices.
130000000000000000000000013_001Swissgrid AGInactive2024-02-20 04:00:002024-02-21 19:00:002024-02-14 17:27:59UPDATE (reduced amount of energy)
Information: At the request of the Swiss supervisory authority ElCom, Swissgrid (Swiss TSO) will coordinate an energy reserve test with hydroelectric reserve, thermal reserve power plant and emergency power groups between 20/02/2024 04:00 and 21/02/2024 19:00. During this period, an excess of approx. 966.5 MWh will be fed into the grid, which may have an impact on prices.
120000000000000000000000012_001Swissgrid AGDismissed2024-02-20 04:00:002024-02-21 19:00:002024-02-13 15:04:43Information: At the request of the Swiss supervisory authority ElCom, Swissgrid (Swiss TSO) will coordinate an energy reserve test with hydroelectric reserve, thermal reserve power plant and emergency power groups between 20/02/2024 04:00 and 21/02/2024 19:00. During this period, an excess of approx. 1’452.80 MWh will be fed into the grid, which may have an impact on prices.
110000000000000000000000011_001Swissgrid AGInactive2022-12-01 00:00:002023-05-15 23:55:002022-10-25 13:42:46Information about the Swiss hydropower reserve administrated by Swissgrid according to the Swiss Ordinance on the establishment of a hydropower reserve is available on our website. Today Swissgrid procured a total energy volume of 400 GWh for the coming winter period (01 December 2022 until 15 May 2023). See https://www.swissgrid.ch/en/home/newsroom/newsfeed/20221025-01.html
100000000000000000000000010_001Swissgrid AGInactive2020-12-21 00:00:002022-01-05 00:00:002021-12-23 09:12:31A temporary price Cap and Floor was introduced for Swiss offers in TERRE. From delivery period of 21.12.2020 00:00 onwards the offers prices in TERRE from Switzerland have been limited to +/- 999 EUR/MWh.