ID | 13 |
---|---|
Market Participant Name | Swissgrid AG |
Market Participant Type | eic |
Market Participant ID | 10XCH-SWISSGRIDC |
Message ID | 0000000000000000000000013_001 |
Event Status | Inactive |
Event Start | 2024-02-20 04:00:00 |
Event Stop | 2024-02-21 19:00:00 |
Publication date/time | 2024-02-14 17:27:59 |
Remarks | UPDATE (reduced amount of energy) Information: At the request of the Swiss supervisory authority ElCom, Swissgrid (Swiss TSO) will coordinate an energy reserve test with hydroelectric reserve, thermal reserve power plant and emergency power groups between 20/02/2024 04:00 and 21/02/2024 19:00. During this period, an excess of approx. 966.5 MWh will be fed into the grid, which may have an impact on prices. |
Status | Saved and Published |
Created at | 14.02.2024 17:27:59 |
Updated at | 21.02.2024 19:00:01 |