ID | Message ID | Market Participant Name | Event Status | Type of Event | Event Start | Event Stop | Type of Unavailability | Publication date/time | Unit of Measurement | Unavailable Capacity | Available Capacity | Technical Capacity | Balancing Zone 1 | Affected Asset Name | |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
×
|
×
|
×
| |||||||||||||
65 | 0000000000000000000000059_002 | MET Speicher GmbH | Dismissed | Withdrawal unavailability | 2022-09-27 06:00:00 | 2022-10-18 14:00:00 | Planned | 2022-05-19 14:04:13 | kWh/h | 209488.00000 | 209489.00000 | 418977.00000 | 21YNL----TTF---1 | UGS Etzel-ESE MET | |
66 | 0000000000000000000000060_002 | MET Speicher GmbH | Dismissed | Injection unavailability | 2022-09-27 06:00:00 | 2022-10-18 14:00:00 | Planned | 2022-05-19 14:04:59 | kWh/h | 127737.00000 | 127737.00000 | 255474.00000 | 21YNL----TTF---1 | UGS Etzel-ESE MET | |
69 | 0000000000000000000000038_003 | MET Speicher GmbH | Dismissed | Storage unavailability | 2022-10-09 06:00:00 | 2022-10-17 18:00:00 | Planned | 2022-05-27 07:27:36 | GWh | 1485.00000 | 0.00000 | 1485.00000 | 37Y005053MH0000R | UGS Etzel-ESE MET | |
72 | 0000000000000000000000048_002 | MET Speicher GmbH | Dismissed | Storage unavailability | 2022-10-18 06:00:00 | 2022-11-11 16:00:00 | Planned | 2022-10-13 06:22:49 | GWh | 1461.00000 | 0.00000 | 1461.00000 | 37Y005053MH0000R | UGS Reckrod | |
75 | 0000000000000000000000075_001 | MET Speicher GmbH | Dismissed | Withdrawal unavailability | 2023-02-10 08:00:00 | 2023-03-15 08:00:00 | Planned | 2022-11-11 15:55:15 | kWh/h | 85500.00000 | 1829500.00000 | 1915000.00000 | 37Y005053MH0000R | UGS Etzel-ESE MET | |
76 | 0000000000000000000000076_001 | MET Speicher GmbH | Dismissed | Storage unavailability | 2023-02-10 08:00:00 | 2023-03-15 08:00:00 | Planned | 2022-11-11 15:55:29 | GWh | 17.00000 | 1425.00000 | 1442.00000 | 37Y005053MH0000R | UGS Etzel-ESE MET | |
77 | 0000000000000000000000077_001 | MET Speicher GmbH | Dismissed | Withdrawal unavailability | 2023-03-15 08:00:00 | 2023-04-04 16:00:00 | Planned | 2022-11-11 15:55:50 | kWh/h | 155500.00000 | 1759500.00000 | 1915000.00000 | 37Y005053MH0000R | UGS Etzel-ESE MET | |
78 | 0000000000000000000000078_001 | MET Speicher GmbH | Dismissed | Storage unavailability | 2023-03-15 08:00:00 | 2023-04-04 16:00:00 | Planned | 2022-11-11 15:56:03 | GWh | 32.00000 | 1410.00000 | 1442.00000 | 37Y005053MH0000R | UGS Etzel-ESE MET | |
79 | 0000000000000000000000079_001 | MET Speicher GmbH | Dismissed | Withdrawal unavailability | 2023-04-04 16:00:00 | 2023-05-24 16:00:00 | Planned | 2022-11-11 15:56:21 | kWh/h | 70000.00000 | 1845000.00000 | 1915000.00000 | 37Y005053MH0000R | UGS Etzel-ESE MET | |
80 | 0000000000000000000000080_001 | MET Speicher GmbH | Dismissed | Storage unavailability | 2023-04-04 16:00:00 | 2023-05-24 16:00:00 | Planned | 2022-11-11 15:56:34 | GWh | 15.00000 | 1427.00000 | 1442.00000 | 37Y005053MH0000R | UGS Etzel-ESE MET | |
17 | 0000000000000000000000016_002 | astora GmbH and Co. KG | Inactive | Injection unavailability | 2020-11-02 08:00:00 | 2020-12-11 18:00:00 | Planned | 2020-06-10 09:41:22 | KWh/h | 14365000.00000 | 0.00000 | 14365000.00000 | 37Z0000000052293 | Rehden natural gas storage facility | |
20 | 0000000000000000000000020_001 | astora GmbH and Co. KG | Inactive | Injection unavailability | 2021-10-04 06:00:00 | 2021-10-15 18:00:00 | Planned | 2021-05-25 12:09:00 | KWh/h | 14365000.00000 | 0.00000 | 14365000.00000 | 37Z0000000052293 | Rehden natural gas storage facility | |
21 | 0000000000000000000000021_001 | astora GmbH and Co. KG | Inactive | Withdrawal unavailability | 2021-10-04 06:00:00 | 2021-10-15 18:00:00 | Planned | 2021-05-26 19:21:51 | KWh/h | 22100000.00000 | 0.00000 | 22100000.00000 | 37Z0000000052293 | Rehden natural gas storage facility | |
23 | 0000000000000000000000023_001 | astora GmbH and Co. KG | Inactive | Injection unavailability | 2021-10-19 16:00:00 | 2021-10-26 16:00:00 | Planned | 2021-05-28 08:11:06 | KWh/h | 2066166.00000 | 2066166.00000 | 4132332.00000 | 37Y701133MH0000P | UGS Haidach - Astora - Injection | |
24 | 0000000000000000000000022_002 | astora GmbH and Co. KG | Inactive | Injection unavailability | 2021-10-26 16:00:00 | 2021-11-17 22:00:00 | Planned | 2021-05-28 08:18:49 | KWh/h | 1033083.00000 | 3099249.00000 | 4132332.00000 | 37Y701133MH0000P | UGS Haidach - Astora - Injection | |
26 | 0000000000000000000000025_002 | astora GmbH and Co. KG | Inactive | Injection unavailability | 2021-10-04 07:00:00 | 2021-10-19 16:00:00 | Planned | 2021-05-30 15:14:10 | KWh/h | 4132332.00000 | 0.00000 | 4132332.00000 | 37Y701133MH0000P | UGS Haidach - Astora - Injection | |
29 | 0000000000000000000000027_003 | astora GmbH and Co. KG | Inactive | Withdrawal unavailability | 2021-10-04 07:00:00 | 2021-10-19 16:00:00 | Planned | 2021-06-04 12:43:09 | kWh/h | 4357733.00000 | 0.00000 | 4357733.00000 | 37Y701133MH0000P | UGS Haidach - Astora - Withdrawal | |
30 | 0000000000000000000000030_001 | astora GmbH and Co. KG | Inactive | Injection unavailability | 2021-06-07 07:00:00 | 2021-06-09 16:00:00 | Planned | 2021-06-04 12:48:20 | kWh/h | 4132332.00000 | 0.00000 | 4132332.00000 | 37Y701133MH0000P | UGS Haidach - Astora - Injection | |
31 | 0000000000000000000000031_001 | astora GmbH and Co. KG | Inactive | Withdrawal unavailability | 2021-06-07 07:00:00 | 2021-06-09 16:00:00 | Planned | 2021-06-07 22:59:18 | kWh/h | 4357733.00000 | 0.00000 | 4357733.00000 | 37Y701133MH0000P | UGS Haidach - Astora - Withdrawal | |
32 | 0000000000000000000000032_001 | MET Speicher GmbH | Inactive | Injection unavailability | 2022-01-03 08:00:00 | 2022-01-16 16:00:00 | Planned | 2022-01-03 16:51:54 | kWh/h | 750750.00000 | 1524250.00000 | 2275000.00000 | 37Y005053MH0000R | UGS Etzel-ESE MET |
ID | Message ID | Market Participant Name | Event Status | Type of Event | Event Start | Event Stop | Type of Unavailability | Publication date/time | Unit of Measurement | Unavailable Capacity | Available Capacity | Installed Capacity | Fuel Type | Bidding Zone | Affected Asset Name | |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
×
|
×
|
×
| ||||||||||||||
181 | 0000000000000000000000180_002 | Ineos oxide utilities NV | Dismissed | Production unavailability | 2023-11-11 16:00:00 | 2023-11-16 00:00:00 | Unplanned | 2023-11-14 10:13:01 | MW | 117.00000 | 22.00000 | 139.00000 | Fossil Gas | 10X1001A1001A094 | INESCO WKK | |
182 | 0000000000000000000000180_003 | Ineos oxide utilities NV | Dismissed | Production unavailability | 2023-11-11 16:00:00 | 2023-11-18 00:00:00 | Unplanned | 2023-11-15 09:51:17 | MW | 117.00000 | 22.00000 | 139.00000 | Fossil Gas | 10X1001A1001A094 | INESCO WKK | |
183 | 0000000000000000000000180_004 | Ineos oxide utilities NV | Dismissed | Production unavailability | 2023-11-11 16:00:00 | 2023-11-22 00:00:00 | Unplanned | 2023-11-16 12:19:25 | MW | 117.00000 | 22.00000 | 139.00000 | Fossil Gas | 10X1001A1001A094 | INESCO WKK | |
184 | 0000000000000000000000164_004 | Ineos oxide utilities NV | Dismissed | Production unavailability | 2023-11-15 00:00:00 | 2023-12-11 00:00:00 | Planned | 2023-11-17 12:24:05 | MW | 98.00000 | 41.00000 | 139.00000 | Fossil Gas | 10X1001A1001A094 | INESCO WKK | |
185 | 0000000000000000000000180_005 | Ineos oxide utilities NV | Dismissed | Production unavailability | 2023-11-11 16:00:00 | 2023-11-21 14:00:00 | Unplanned | 2023-11-17 12:26:36 | MW | 117.00000 | 22.00000 | 139.00000 | Fossil Gas | 10X1001A1001A094 | INESCO WKK | |
186 | 0000000000000000000000186_001 | Ineos oxide utilities NV | Dismissed | Production unavailability | 2023-11-21 14:00:00 | 2023-11-22 14:00:00 | Planned | 2023-11-17 12:29:05 | MW | 101.00000 | 38.00000 | 139.00000 | Fossil Gas | 10X1001A1001A094 | INESCO WKK | |
187 | 0000000000000000000000187_001 | Ineos oxide utilities NV | Dismissed | Production unavailability | 2023-11-22 14:00:00 | 2023-11-29 00:00:00 | Planned | 2023-11-17 12:32:09 | MW | 93.00000 | 46.00000 | 139.00000 | Fossil Gas | 10X1001A1001A094 | INESCO WKK | |
194 | 0000000000000000000000164_005 | Ineos oxide utilities NV | Dismissed | Production unavailability | 2023-11-15 00:00:00 | 2024-01-01 00:00:00 | Planned | 2023-12-07 12:45:25 | MW | 98.00000 | 41.00000 | 139.00000 | Fossil Gas | 10X1001A1001A094 | INESCO WKK | |
196 | 0000000000000000000000196_001 | Ineos oxide utilities NV | Dismissed | Production unavailability | 2023-12-09 00:00:00 | 2024-01-01 00:00:00 | Planned | 2023-12-09 09:47:45 | MW | 46.00000 | 93.00000 | 139.00000 | Fossil Gas | 10X1001A1001A094 | INESCO WKK | |
199 | 0000000000000000000000199_001 | Ineos oxide utilities NV | Dismissed | Production unavailability | 2023-12-23 10:00:00 | 2023-12-27 00:00:00 | Unplanned | 2023-12-23 08:52:04 | MW | 30.00000 | 109.00000 | 139.00000 | Fossil Gas | 10X1001A1001A094 | INESCO WKK | |
200 | 0000000000000000000000199_002 | Ineos oxide utilities NV | Dismissed | Production unavailability | 2023-12-23 10:00:00 | 2023-12-28 00:00:00 | Unplanned | 2023-12-26 09:06:02 | MW | 30.00000 | 109.00000 | 139.00000 | Fossil Gas | 10X1001A1001A094 | INESCO WKK | |
202 | 0000000000000000000000202_001 | Ineos oxide utilities NV | Dismissed | Production unavailability | 2024-01-05 08:40:00 | 2024-01-10 00:00:00 | Unplanned | 2024-01-05 07:36:25 | MW | 30.00000 | 109.00000 | 139.00000 | Fossil Gas | 10X1001A1001A094 | INESCO WKK | |
203 | 0000000000000000000000203_001 | Ineos oxide utilities NV | Dismissed | Production unavailability | 2024-01-10 00:00:00 | 2024-01-12 00:00:00 | Planned | 2024-01-05 07:43:09 | MW | 50.00000 | 89.00000 | 139.00000 | Fossil Gas | 10X1001A1001A094 | INESCO WKK | |
204 | 0000000000000000000000204_001 | Ineos oxide utilities NV | Dismissed | Production unavailability | 2024-01-08 01:10:00 | 2024-01-08 10:00:00 | Unplanned | 2024-01-08 03:36:14 | MW | 96.00000 | 43.00000 | 139.00000 | Fossil Gas | 10X1001A1001A094 | INESCO WKK | |
205 | 0000000000000000000000204_002 | Ineos oxide utilities NV | Dismissed | Production unavailability | 2024-01-08 01:10:00 | 2024-01-08 18:00:00 | Unplanned | 2024-01-08 08:14:01 | MW | 96.00000 | 43.00000 | 139.00000 | Fossil Gas | 10X1001A1001A094 | INESCO WKK | |
206 | 0000000000000000000000204_003 | Ineos oxide utilities NV | Dismissed | Production unavailability | 2024-01-08 01:10:00 | 2024-01-09 12:00:00 | Unplanned | 2024-01-08 16:21:17 | MW | 96.00000 | 43.00000 | 139.00000 | Fossil Gas | 10X1001A1001A094 | INESCO WKK | |
207 | 0000000000000000000000204_004 | Ineos oxide utilities NV | Dismissed | Production unavailability | 2024-01-08 01:10:00 | 2024-01-09 12:00:00 | Unplanned | 2024-01-08 16:43:37 | MW | 80.00000 | 58.00000 | 139.00000 | Fossil Gas | 10X1001A1001A094 | INESCO WKK | |
208 | 0000000000000000000000204_005 | Ineos oxide utilities NV | Dismissed | Production unavailability | 2024-01-08 01:10:00 | 2024-01-09 18:00:00 | Unplanned | 2024-01-09 08:23:35 | MW | 80.00000 | 58.00000 | 139.00000 | Fossil Gas | 10X1001A1001A094 | INESCO WKK | |
209 | 0000000000000000000000203_002 | Ineos oxide utilities NV | Dismissed | Production unavailability | 2024-01-17 00:00:00 | 2024-01-19 00:00:00 | Planned | 2024-01-09 10:04:18 | MW | 50.00000 | 89.00000 | 139.00000 | Fossil Gas | 10X1001A1001A094 | INESCO WKK | |
211 | 0000000000000000000000204_006 | Ineos oxide utilities NV | Dismissed | Production unavailability | 2024-01-08 01:10:00 | 2024-01-10 18:00:00 | Unplanned | 2024-01-09 16:43:13 | MW | 80.00000 | 58.00000 | 139.00000 | Fossil Gas | 10X1001A1001A094 | INESCO WKK |
ID | Message ID | Market Participant Name | Event Status | Event Start | Event Stop | Publication date/time | Remarks | |
---|---|---|---|---|---|---|---|---|
×
|
×
|
×
| ||||||
12 | 0000000000000000000000012_001 | Swissgrid AG | Dismissed | 2024-02-20 04:00:00 | 2024-02-21 19:00:00 | 2024-02-13 15:04:43 | Information: At the request of the Swiss supervisory authority ElCom, Swissgrid (Swiss TSO) will coordinate an energy reserve test with hydroelectric reserve, thermal reserve power plant and emergency power groups between 20/02/2024 04:00 and 21/02/2024 19:00. During this period, an excess of approx. 1’452.80 MWh will be fed into the grid, which may have an impact on prices. | |
14 | 0000000000000000000000012_002 | Swissgrid AG | Dismissed | 2024-02-20 04:00:00 | 2024-02-21 19:00:00 | 2024-02-14 17:40:34 | Information: At the request of the Swiss supervisory authority ElCom, Swissgrid (Swiss TSO) will coordinate an energy reserve test with hydroelectric reserve, thermal reserve power plant and emergency power groups between 20/02/2024 04:00 and 21/02/2024 19:00. During this period, an excess of approx. 1’452.80 MWh will be fed into the grid, which may have an impact on prices. | |
10 | 0000000000000000000000010_001 | Swissgrid AG | Inactive | 2020-12-21 00:00:00 | 2022-01-05 00:00:00 | 2021-12-23 09:12:31 | A temporary price Cap and Floor was introduced for Swiss offers in TERRE. From delivery period of 21.12.2020 00:00 onwards the offers prices in TERRE from Switzerland have been limited to +/- 999 EUR/MWh. The temporary price Cap and Floor will be removed as of 05.01.2022. For delivery periods from 05.01.2022 00:00 onwards, the relevant price Cap and Floor will be +/- 9’999 EUR/MWh. | |
11 | 0000000000000000000000011_001 | Swissgrid AG | Inactive | 2022-12-01 00:00:00 | 2023-05-15 23:55:00 | 2022-10-25 13:42:46 | Information about the Swiss hydropower reserve administrated by Swissgrid according to the Swiss Ordinance on the establishment of a hydropower reserve is available on our website. Today Swissgrid procured a total energy volume of 400 GWh for the coming winter period (01 December 2022 until 15 May 2023). See https://www.swissgrid.ch/en/home/newsroom/newsfeed/20221025-01.html | |
13 | 0000000000000000000000013_001 | Swissgrid AG | Inactive | 2024-02-20 04:00:00 | 2024-02-21 19:00:00 | 2024-02-14 17:27:59 | UPDATE (reduced amount of energy) Information: At the request of the Swiss supervisory authority ElCom, Swissgrid (Swiss TSO) will coordinate an energy reserve test with hydroelectric reserve, thermal reserve power plant and emergency power groups between 20/02/2024 04:00 and 21/02/2024 19:00. During this period, an excess of approx. 966.5 MWh will be fed into the grid, which may have an impact on prices. |