89 | 0000000000000000000000089_001 | MET Speicher GmbH | Inactive | Injection unavailability | 2023-02-28 18:00:00 | 2023-03-15 18:00:00 | Planned | 2023-02-28 10:40:36 | GWh/d | 24.74400 | 0.00000 | 24.74400 | 37Y005053MH0000R | UGS Reckrod | |
88 | 0000000000000000000000088_001 | MET Speicher GmbH | Inactive | Withdrawal unavailability | 2022-12-06 06:00:00 | 2022-12-08 16:00:00 | Planned | 2022-12-05 14:34:56 | GWh/d | 49.50000 | 0.00000 | 49.50000 | 37Y005053MH0000R | UGS Reckrod | |
87 | 0000000000000000000000087_001 | MET Speicher GmbH | Inactive | Withdrawal unavailability | 2022-11-28 06:00:00 | 2022-11-30 06:00:00 | Planned | 2022-11-27 10:09:25 | GWh/d | 49.50000 | 0.00000 | 49.50000 | 37Y005053MH0000R | UGS Reckrod | |
86 | 0000000000000000000000080_002 | MET Speicher GmbH | Inactive | Storage unavailability | 2023-04-04 16:00:00 | 2023-05-09 16:00:00 | Planned | 2022-11-16 16:42:06 | GWh | 15.00000 | 1427.00000 | 1442.00000 | 37Y005053MH0000R | UGS Etzel-ESE MET | |
85 | 0000000000000000000000079_002 | MET Speicher GmbH | Inactive | Withdrawal unavailability | 2023-04-04 16:00:00 | 2023-05-09 16:00:00 | Planned | 2022-11-16 16:41:38 | kWh/h | 70000.00000 | 1845000.00000 | 1915000.00000 | 37Y005053MH0000R | UGS Etzel-ESE MET | |
84 | 0000000000000000000000078_002 | MET Speicher GmbH | Inactive | Storage unavailability | 2023-03-17 08:00:00 | 2023-04-04 16:00:00 | Planned | 2022-11-16 16:40:51 | GWh | 32.00000 | 1410.00000 | 1442.00000 | 37Y005053MH0000R | UGS Etzel-ESE MET | |
83 | 0000000000000000000000077_002 | MET Speicher GmbH | Inactive | Withdrawal unavailability | 2023-03-17 08:00:00 | 2023-04-04 16:00:00 | Planned | 2022-11-16 16:40:32 | kWh/h | 155500.00000 | 1759500.00000 | 1915000.00000 | 37Y005053MH0000R | UGS Etzel-ESE MET | |
82 | 0000000000000000000000076_002 | MET Speicher GmbH | Inactive | Storage unavailability | 2023-02-10 08:00:00 | 2023-03-17 08:00:00 | Planned | 2022-11-16 16:39:02 | GWh | 17.00000 | 1425.00000 | 1442.00000 | 37Y005053MH0000R | UGS Etzel-ESE MET | |
81 | 0000000000000000000000075_002 | MET Speicher GmbH | Inactive | Withdrawal unavailability | 2023-02-10 08:00:00 | 2023-03-17 08:00:00 | Planned | 2022-11-16 16:37:23 | kWh/h | 85500.00000 | 1829500.00000 | 1915000.00000 | 37Y005053MH0000R | UGS Etzel-ESE MET | |
80 | 0000000000000000000000080_001 | MET Speicher GmbH | Dismissed | Storage unavailability | 2023-04-04 16:00:00 | 2023-05-24 16:00:00 | Planned | 2022-11-11 15:56:34 | GWh | 15.00000 | 1427.00000 | 1442.00000 | 37Y005053MH0000R | UGS Etzel-ESE MET | |
79 | 0000000000000000000000079_001 | MET Speicher GmbH | Dismissed | Withdrawal unavailability | 2023-04-04 16:00:00 | 2023-05-24 16:00:00 | Planned | 2022-11-11 15:56:21 | kWh/h | 70000.00000 | 1845000.00000 | 1915000.00000 | 37Y005053MH0000R | UGS Etzel-ESE MET | |
78 | 0000000000000000000000078_001 | MET Speicher GmbH | Dismissed | Storage unavailability | 2023-03-15 08:00:00 | 2023-04-04 16:00:00 | Planned | 2022-11-11 15:56:03 | GWh | 32.00000 | 1410.00000 | 1442.00000 | 37Y005053MH0000R | UGS Etzel-ESE MET | |
77 | 0000000000000000000000077_001 | MET Speicher GmbH | Dismissed | Withdrawal unavailability | 2023-03-15 08:00:00 | 2023-04-04 16:00:00 | Planned | 2022-11-11 15:55:50 | kWh/h | 155500.00000 | 1759500.00000 | 1915000.00000 | 37Y005053MH0000R | UGS Etzel-ESE MET | |
76 | 0000000000000000000000076_001 | MET Speicher GmbH | Dismissed | Storage unavailability | 2023-02-10 08:00:00 | 2023-03-15 08:00:00 | Planned | 2022-11-11 15:55:29 | GWh | 17.00000 | 1425.00000 | 1442.00000 | 37Y005053MH0000R | UGS Etzel-ESE MET | |
75 | 0000000000000000000000075_001 | MET Speicher GmbH | Dismissed | Withdrawal unavailability | 2023-02-10 08:00:00 | 2023-03-15 08:00:00 | Planned | 2022-11-11 15:55:15 | kWh/h | 85500.00000 | 1829500.00000 | 1915000.00000 | 37Y005053MH0000R | UGS Etzel-ESE MET | |
74 | 0000000000000000000000074_001 | MET Speicher GmbH | Inactive | Transmission system unavailability | 2023-09-20 08:00:00 | 2023-09-20 18:00:00 | Planned | 2022-11-11 14:59:13 | kWh/h | 418977.00000 | 0.00000 | 418977.00000 | 21YNL----TTF---1 | UGS Etzel-ESE MET | |
73 | 0000000000000000000000048_003 | MET Speicher GmbH | Inactive | Storage unavailability | 2022-10-18 06:00:00 | 2022-11-04 06:00:00 | Planned | 2022-11-03 18:13:45 | GWh | 1461.00000 | 0.00000 | 1461.00000 | 37Y005053MH0000R | UGS Reckrod | |
72 | 0000000000000000000000048_002 | MET Speicher GmbH | Dismissed | Storage unavailability | 2022-10-18 06:00:00 | 2022-11-11 16:00:00 | Planned | 2022-10-13 06:22:49 | GWh | 1461.00000 | 0.00000 | 1461.00000 | 37Y005053MH0000R | UGS Reckrod | |
71 | 0000000000000000000000058_002 | MET Speicher GmbH | Inactive | Injection unavailability | 2022-10-10 08:00:00 | 2022-12-16 16:00:00 | Planned | 2022-09-23 09:17:44 | kWh/h | 752000.00000 | 1505000.00000 | 2257000.00000 | 37Y005053MH0000R | UGS Etzel-ESE MET | |
70 | 0000000000000000000000038_004 | MET Speicher GmbH | Inactive | Storage unavailability | 2022-10-09 06:00:00 | 2022-10-15 18:00:00 | Planned | 2022-09-23 09:11:28 | GWh | 1442.00000 | 0.00000 | 1442.00000 | 37Y005053MH0000R | UGS Etzel-ESE MET |
ID | Nachrichten ID | Marktteilnehmer Name | Ereignisstatus | Ereignistyp | Ereignis Start | Ereignis Stop | Typ der Nichtverfügbarkeit | Veröffentlichungsdatum / -zeit | Maßeinheit | Nicht verfügbare Kapazität | Verfügbare Kapazität | Installierte Kapazität | Kraftstofftyp | Gebotszone | Name der Anlage | |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
×
|
×
|
×
| ||||||||||||||
161 | 0000000000000000000000161_001 | Ineos oxide utilities NV | Dismissed | Production unavailability | 2023-08-31 15:00:00 | 2023-09-26 00:00:00 | Planned | 2023-08-23 14:13:30 | MW | 92.50000 | 46.50000 | 139.00000 | Fossil Gas | 10X1001A1001A094 | INESCO WKK | |
160 | 0000000000000000000000160_001 | Ineos oxide utilities NV | Inactive | Production unavailability | 2023-08-30 10:00:00 | 2023-08-31 15:00:00 | Planned | 2023-08-23 14:13:11 | MW | 98.00000 | 41.00000 | 139.00000 | Fossil Gas | 10X1001A1001A094 | INESCO WKK | |
158 | 0000000000000000000000158_001 | Energie Wasser Bern | Dismissed | Production unavailability | 2025-08-10 07:00:00 | 2025-09-18 17:00:00 | Planned | 2023-06-19 05:53:02 | MW | 43.50000 | 0.00000 | 43.50000 | Fossil Gas | 10YCH-SWISSGRIDZ | GUD Energiezentrale Forsthaus | |
157 | 0000000000000000000000157_001 | Energie Wasser Bern | Inactive | Production unavailability | 2024-09-08 07:00:00 | 2024-09-19 17:00:00 | Planned | 2023-06-19 05:50:06 | MW | 43.50000 | 0.00000 | 43.50000 | Fossil Gas | 10YCH-SWISSGRIDZ | GUD Energiezentrale Forsthaus | |
156 | 0000000000000000000000154_003 | Ineos oxide utilities NV | Inactive | Production unavailability | 2023-06-12 21:15:00 | 2023-06-16 14:25:00 | Unplanned | 2023-06-16 12:21:44 | MW | 10.00000 | 129.00000 | 139.00000 | Fossil Gas | 10X1001A1001A094 | INESCO WKK | |
155 | 0000000000000000000000154_002 | Ineos oxide utilities NV | Dismissed | Production unavailability | 2023-06-12 21:15:00 | 2023-07-01 00:00:00 | Unplanned | 2023-06-13 09:08:18 | MW | 10.00000 | 129.00000 | 139.00000 | Fossil Gas | 10X1001A1001A094 | INESCO WKK | |
154 | 0000000000000000000000154_001 | Ineos oxide utilities NV | Dismissed | Production unavailability | 2023-06-12 21:15:00 | 2023-06-13 23:05:00 | Unplanned | 2023-06-12 19:10:48 | MW | 10.00000 | 129.00000 | 139.00000 | Fossil Gas | 10X1001A1001A094 | INESCO WKK | |
153 | 0000000000000000000000139_010 | Ineos oxide utilities NV | Inactive | Production unavailability | 2023-05-21 00:00:00 | 2023-06-12 17:00:00 | Planned | 2023-06-12 14:05:52 | MW | 87.00000 | 52.00000 | 139.00000 | Fossil Gas | 10X1001A1001A094 | INESCO WKK | |
152 | 0000000000000000000000139_009 | Ineos oxide utilities NV | Dismissed | Production unavailability | 2023-05-21 00:00:00 | 2023-06-14 00:00:00 | Planned | 2023-06-12 07:46:03 | MW | 87.00000 | 52.00000 | 139.00000 | Fossil Gas | 10X1001A1001A094 | INESCO WKK | |
151 | 0000000000000000000000139_008 | Ineos oxide utilities NV | Dismissed | Production unavailability | 2023-05-21 00:00:00 | 2023-06-13 00:00:00 | Planned | 2023-06-09 14:41:54 | MW | 87.00000 | 52.00000 | 139.00000 | Fossil Gas | 10X1001A1001A094 | INESCO WKK | |
150 | 0000000000000000000000139_007 | Ineos oxide utilities NV | Dismissed | Production unavailability | 2023-05-21 00:00:00 | 2023-06-10 00:00:00 | Planned | 2023-06-09 14:39:49 | MW | 87.00000 | 52.00000 | 139.00000 | Fossil Gas | 10X1001A1001A094 | INESCO WKK | |
149 | 0000000000000000000000139_006 | Ineos oxide utilities NV | Dismissed | Production unavailability | 2023-05-21 00:00:00 | 2023-06-10 00:00:00 | Planned | 2023-06-09 14:38:26 | MW | 87.00000 | 52.00000 | 139.00000 | Fossil Gas | 10X1001A1001A094 | INESCO WKK | |
148 | 0000000000000000000000139_005 | Ineos oxide utilities NV | Dismissed | Production unavailability | 2023-05-21 00:00:00 | 2023-06-10 00:00:00 | Planned | 2023-06-08 14:54:08 | MW | 87.00000 | 52.00000 | 139.00000 | Fossil Gas | 10X1001A1001A094 | INESCO WKK | |
147 | 0000000000000000000000139_004 | Ineos oxide utilities NV | Dismissed | Production unavailability | 2023-05-21 00:00:00 | 2023-06-09 00:00:00 | Planned | 2023-06-06 07:36:24 | MW | 87.00000 | 52.00000 | 139.00000 | Fossil Gas | 10X1001A1001A094 | INESCO WKK | |
146 | 0000000000000000000000146_001 | Stadtwerke Rostock AG | Inactive | Production unavailability | 2023-09-15 00:00:00 | 2023-09-20 23:55:00 | Planned | 2023-06-05 07:43:10 | MW | 36.00000 | 72.00000 | 108.00000 | Fossil Gas | 11XSWROSTOCK---Y | Rostock Marienehe Produktionsanlage | |
145 | 0000000000000000000000145_001 | Stadtwerke Rostock AG | Inactive | Production unavailability | 2023-08-11 00:00:00 | 2023-09-01 23:55:00 | Planned | 2023-06-05 07:41:02 | MW | 36.00000 | 72.00000 | 108.00000 | Fossil Gas | 11XSWROSTOCK---Y | Rostock Marienehe Produktionsanlage | |
144 | 0000000000000000000000144_001 | Stadtwerke Rostock AG | Inactive | Production unavailability | 2023-06-23 00:00:00 | 2023-08-04 23:55:00 | Planned | 2023-06-05 07:29:53 | MW | 36.00000 | 72.00000 | 108.00000 | Fossil Gas | 11XSWROSTOCK---Y | Rostock Marienehe Produktionsanlage | |
143 | 0000000000000000000000139_003 | Ineos oxide utilities NV | Dismissed | Production unavailability | 2023-05-21 00:00:00 | 2023-06-08 00:00:00 | Planned | 2023-06-02 07:30:23 | MW | 87.00000 | 52.00000 | 139.00000 | Fossil Gas | 10X1001A1001A094 | INESCO WKK | |
142 | 0000000000000000000000142_001 | Stadtwerke Rostock AG | Inactive | Production unavailability | 2023-04-11 00:00:00 | 2023-06-21 23:55:00 | Planned | 2023-06-01 12:28:30 | MW | 36.00000 | 72.00000 | 108.00000 | Fossil Gas | 11XSWROSTOCK---Y | Rostock Marienehe Produktionsanlage | |
141 | 0000000000000000000000141_001 | Stadtwerke Rostock AG | Inactive | Production unavailability | 2023-06-02 00:00:00 | 2023-06-11 23:55:00 | Planned | 2023-05-25 08:07:11 | MW | 108.00000 | 0.00000 | 108.00000 | Fossil Gas | 11XSWROSTOCK---Y | Rostock Marienehe Produktionsanlage |
ID | Nachrichten ID | Marktteilnehmer Name | Ereignisstatus | Ereignis Start | Ereignis Stop | Veröffentlichungsdatum / -zeit | Bemerkungen | |
---|---|---|---|---|---|---|---|---|
×
|
×
|
×
| ||||||
14 | 0000000000000000000000012_002 | Swissgrid AG | Dismissed | 2024-02-20 04:00:00 | 2024-02-21 19:00:00 | 2024-02-14 17:40:34 | Information: At the request of the Swiss supervisory authority ElCom, Swissgrid (Swiss TSO) will coordinate an energy reserve test with hydroelectric reserve, thermal reserve power plant and emergency power groups between 20/02/2024 04:00 and 21/02/2024 19:00. During this period, an excess of approx. 1’452.80 MWh will be fed into the grid, which may have an impact on prices. | |
13 | 0000000000000000000000013_001 | Swissgrid AG | Inactive | 2024-02-20 04:00:00 | 2024-02-21 19:00:00 | 2024-02-14 17:27:59 | UPDATE (reduced amount of energy) Information: At the request of the Swiss supervisory authority ElCom, Swissgrid (Swiss TSO) will coordinate an energy reserve test with hydroelectric reserve, thermal reserve power plant and emergency power groups between 20/02/2024 04:00 and 21/02/2024 19:00. During this period, an excess of approx. 966.5 MWh will be fed into the grid, which may have an impact on prices. | |
12 | 0000000000000000000000012_001 | Swissgrid AG | Dismissed | 2024-02-20 04:00:00 | 2024-02-21 19:00:00 | 2024-02-13 15:04:43 | Information: At the request of the Swiss supervisory authority ElCom, Swissgrid (Swiss TSO) will coordinate an energy reserve test with hydroelectric reserve, thermal reserve power plant and emergency power groups between 20/02/2024 04:00 and 21/02/2024 19:00. During this period, an excess of approx. 1’452.80 MWh will be fed into the grid, which may have an impact on prices. | |
11 | 0000000000000000000000011_001 | Swissgrid AG | Inactive | 2022-12-01 00:00:00 | 2023-05-15 23:55:00 | 2022-10-25 13:42:46 | Information about the Swiss hydropower reserve administrated by Swissgrid according to the Swiss Ordinance on the establishment of a hydropower reserve is available on our website. Today Swissgrid procured a total energy volume of 400 GWh for the coming winter period (01 December 2022 until 15 May 2023). See https://www.swissgrid.ch/en/home/newsroom/newsfeed/20221025-01.html | |
10 | 0000000000000000000000010_001 | Swissgrid AG | Inactive | 2020-12-21 00:00:00 | 2022-01-05 00:00:00 | 2021-12-23 09:12:31 | A temporary price Cap and Floor was introduced for Swiss offers in TERRE. From delivery period of 21.12.2020 00:00 onwards the offers prices in TERRE from Switzerland have been limited to +/- 999 EUR/MWh. The temporary price Cap and Floor will be removed as of 05.01.2022. For delivery periods from 05.01.2022 00:00 onwards, the relevant price Cap and Floor will be +/- 9’999 EUR/MWh. |