Showing 61-74 of 74 items.
 IDMessage IDMarket Participant NameEvent StatusType of EventEvent StartEvent StopType of UnavailabilityPublication date/timeUnit of MeasurementUnavailable CapacityAvailable CapacityTechnical CapacityBalancing Zone 1Affected Asset Name
 
 
 
×
×
 
×
 
 
540000000000000000000000051_004MET Speicher GmbHInactiveInjection unavailability2022-05-13 00:00:002022-05-16 00:00:00Planned2022-05-13 12:45:08kWh/h529000.00000450000.00000979000.0000037Y005053MH0000RUGS Reckrod
550000000000000000000000055_001MET Speicher GmbHInactiveInjection unavailability2022-05-16 00:00:002022-05-17 00:00:00Planned2022-05-13 12:49:10kWh/h679000.00000300000.00000979000.0000037Y005053MH0000RUGS Reckrod
570000000000000000000000057_001MET Speicher GmbHDismissedInjection unavailability2022-05-17 00:00:002022-05-18 00:00:00Planned2022-05-16 10:15:11kWh/h754000.00000225000.00000979000.0000037Y005053MH0000RUGS Reckrod
610000000000000000000000057_002MET Speicher GmbHInactiveInjection unavailability2022-05-17 00:00:002022-05-18 06:00:00Planned2022-05-17 14:12:06kWh/h754000.00000225000.00000979000.0000037Y005053MH0000RUGS Reckrod
620000000000000000000000062_001MET Speicher GmbHInactiveInjection unavailability2022-05-18 06:00:002022-05-18 14:00:00Planned2022-05-17 14:14:20kWh/h979000.000000.00000979000.0000037Y005053MH0000RUGS Reckrod
630000000000000000000000063_001MET Speicher GmbHInactiveInjection unavailability2022-05-18 14:00:002022-05-19 06:00:00Planned2022-05-17 14:15:59kWh/h479000.00000500000.00000979000.0000037Y005053MH0000RUGS Reckrod
640000000000000000000000064_001MET Speicher GmbHDismissedInjection unavailability2022-05-19 06:00:002022-05-20 06:00:00Planned2022-05-18 13:23:03kWh/h491000.00000483000.00000974000.0000037Y005053MH0000RUGS Reckrod
670000000000000000000000064_002MET Speicher GmbHInactiveInjection unavailability2022-05-19 06:00:002022-05-21 06:00:00Planned2022-05-19 14:09:03kWh/h491000.00000483000.00000974000.0000037Y005053MH0000RUGS Reckrod
680000000000000000000000068_001MET Speicher GmbHInactiveInjection unavailability2022-05-23 06:00:002022-05-24 06:00:00Planned2022-05-20 07:18:54kWh/h639.00000333.00000972.0000037Y005053MH0000RUGS Reckrod
720000000000000000000000048_002MET Speicher GmbHDismissedStorage unavailability2022-10-18 06:00:002022-11-11 16:00:00Planned2022-10-13 06:22:49GWh1461.000000.000001461.0000037Y005053MH0000RUGS Reckrod
730000000000000000000000048_003MET Speicher GmbHInactiveStorage unavailability2022-10-18 06:00:002022-11-04 06:00:00Planned2022-11-03 18:13:45GWh1461.000000.000001461.0000037Y005053MH0000RUGS Reckrod
870000000000000000000000087_001MET Speicher GmbHInactiveWithdrawal unavailability2022-11-28 06:00:002022-11-30 06:00:00Planned2022-11-27 10:09:25GWh/d49.500000.0000049.5000037Y005053MH0000RUGS Reckrod
880000000000000000000000088_001MET Speicher GmbHInactiveWithdrawal unavailability2022-12-06 06:00:002022-12-08 16:00:00Planned2022-12-05 14:34:56GWh/d49.500000.0000049.5000037Y005053MH0000RUGS Reckrod
890000000000000000000000089_001MET Speicher GmbHInactiveInjection unavailability2023-02-28 18:00:002023-03-15 18:00:00Planned2023-02-28 10:40:36GWh/d24.744000.0000024.7440037Y005053MH0000RUGS Reckrod
Showing 101-120 of 145 items.
 IDMessage IDMarket Participant NameEvent StatusType of EventEvent StartEvent StopType of UnavailabilityPublication date/timeUnit of MeasurementUnavailable CapacityAvailable CapacityInstalled CapacityFuel TypeBidding ZoneAffected Asset Name
 
 
 
×
×
 
×
 
 
 
1930000000000000000000000193_001Ineos oxide utilities NVInactiveProduction unavailability2023-12-07 15:00:002023-12-09 00:00:00Planned2023-12-07 10:02:15MW92.5000046.50000139.00000Fossil Gas10X1001A1001A094INESCO WKK
1940000000000000000000000164_005Ineos oxide utilities NVDismissedProduction unavailability2023-11-15 00:00:002024-01-01 00:00:00Planned2023-12-07 12:45:25MW98.0000041.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
1950000000000000000000000164_006Ineos oxide utilities NVInactiveProduction unavailability2023-11-15 00:00:002023-12-09 00:00:00Planned2023-12-09 09:47:31MW98.0000041.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
1960000000000000000000000196_001Ineos oxide utilities NVDismissedProduction unavailability2023-12-09 00:00:002024-01-01 00:00:00Planned2023-12-09 09:47:45MW46.0000093.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
1970000000000000000000000197_001Ineos oxide utilities NVInactiveProduction unavailability2023-12-14 08:00:002023-12-15 00:00:00Unplanned2023-12-14 07:53:19MW95.0000044.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
1980000000000000000000000196_002Ineos oxide utilities NVInactiveProduction unavailability2023-12-09 00:00:002023-12-22 15:00:00Planned2023-12-22 18:17:40MW46.0000093.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
1990000000000000000000000199_001Ineos oxide utilities NVDismissedProduction unavailability2023-12-23 10:00:002023-12-27 00:00:00Unplanned2023-12-23 08:52:04MW30.00000109.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
2000000000000000000000000199_002Ineos oxide utilities NVDismissedProduction unavailability2023-12-23 10:00:002023-12-28 00:00:00Unplanned2023-12-26 09:06:02MW30.00000109.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
2010000000000000000000000199_003Ineos oxide utilities NVInactiveProduction unavailability2023-12-23 10:00:002024-01-03 00:00:00Unplanned2023-12-26 11:25:37MW30.00000109.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
2020000000000000000000000202_001Ineos oxide utilities NVDismissedProduction unavailability2024-01-05 08:40:002024-01-10 00:00:00Unplanned2024-01-05 07:36:25MW30.00000109.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
2030000000000000000000000203_001Ineos oxide utilities NVDismissedProduction unavailability2024-01-10 00:00:002024-01-12 00:00:00Planned2024-01-05 07:43:09MW50.0000089.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
2040000000000000000000000204_001Ineos oxide utilities NVDismissedProduction unavailability2024-01-08 01:10:002024-01-08 10:00:00Unplanned2024-01-08 03:36:14MW96.0000043.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
2050000000000000000000000204_002Ineos oxide utilities NVDismissedProduction unavailability2024-01-08 01:10:002024-01-08 18:00:00Unplanned2024-01-08 08:14:01MW96.0000043.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
2060000000000000000000000204_003Ineos oxide utilities NVDismissedProduction unavailability2024-01-08 01:10:002024-01-09 12:00:00Unplanned2024-01-08 16:21:17MW96.0000043.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
2070000000000000000000000204_004Ineos oxide utilities NVDismissedProduction unavailability2024-01-08 01:10:002024-01-09 12:00:00Unplanned2024-01-08 16:43:37MW80.0000058.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
2080000000000000000000000204_005Ineos oxide utilities NVDismissedProduction unavailability2024-01-08 01:10:002024-01-09 18:00:00Unplanned2024-01-09 08:23:35MW80.0000058.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
2090000000000000000000000203_002Ineos oxide utilities NVDismissedProduction unavailability2024-01-17 00:00:002024-01-19 00:00:00Planned2024-01-09 10:04:18MW50.0000089.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
2100000000000000000000000202_002Ineos oxide utilities NVInactiveProduction unavailability2024-01-05 08:40:002024-01-17 00:00:00Unplanned2024-01-09 10:05:15MW30.00000109.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
2110000000000000000000000204_006Ineos oxide utilities NVDismissedProduction unavailability2024-01-08 01:10:002024-01-10 18:00:00Unplanned2024-01-09 16:43:13MW80.0000058.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
2120000000000000000000000204_007Ineos oxide utilities NVDismissedProduction unavailability2024-01-08 01:10:002024-01-10 15:30:00Unplanned2024-01-10 14:25:34MW80.0000058.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
Showing 1-5 of 5 items.
 IDMessage IDMarket Participant NameEvent StatusEvent StartEvent StopPublication date/timeRemarks
 
 
×
×
×
140000000000000000000000012_002Swissgrid AGDismissed2024-02-20 04:00:002024-02-21 19:00:002024-02-14 17:40:34Information: At the request of the Swiss supervisory authority ElCom, Swissgrid (Swiss TSO) will coordinate an energy reserve test with hydroelectric reserve, thermal reserve power plant and emergency power groups between 20/02/2024 04:00 and 21/02/2024 19:00. During this period, an excess of approx. 1’452.80 MWh will be fed into the grid, which may have an impact on prices.
130000000000000000000000013_001Swissgrid AGInactive2024-02-20 04:00:002024-02-21 19:00:002024-02-14 17:27:59UPDATE (reduced amount of energy)
Information: At the request of the Swiss supervisory authority ElCom, Swissgrid (Swiss TSO) will coordinate an energy reserve test with hydroelectric reserve, thermal reserve power plant and emergency power groups between 20/02/2024 04:00 and 21/02/2024 19:00. During this period, an excess of approx. 966.5 MWh will be fed into the grid, which may have an impact on prices.
120000000000000000000000012_001Swissgrid AGDismissed2024-02-20 04:00:002024-02-21 19:00:002024-02-13 15:04:43Information: At the request of the Swiss supervisory authority ElCom, Swissgrid (Swiss TSO) will coordinate an energy reserve test with hydroelectric reserve, thermal reserve power plant and emergency power groups between 20/02/2024 04:00 and 21/02/2024 19:00. During this period, an excess of approx. 1’452.80 MWh will be fed into the grid, which may have an impact on prices.
110000000000000000000000011_001Swissgrid AGInactive2022-12-01 00:00:002023-05-15 23:55:002022-10-25 13:42:46Information about the Swiss hydropower reserve administrated by Swissgrid according to the Swiss Ordinance on the establishment of a hydropower reserve is available on our website. Today Swissgrid procured a total energy volume of 400 GWh for the coming winter period (01 December 2022 until 15 May 2023). See https://www.swissgrid.ch/en/home/newsroom/newsfeed/20221025-01.html
100000000000000000000000010_001Swissgrid AGInactive2020-12-21 00:00:002022-01-05 00:00:002021-12-23 09:12:31A temporary price Cap and Floor was introduced for Swiss offers in TERRE. From delivery period of 21.12.2020 00:00 onwards the offers prices in TERRE from Switzerland have been limited to +/- 999 EUR/MWh.

The temporary price Cap and Floor will be removed as of 05.01.2022. For delivery periods from 05.01.2022 00:00 onwards, the relevant price Cap and Floor will be +/- 9’999 EUR/MWh.