 IDNachrichten IDMp NameEreignisstatusEreignistypEreignis Start (UTC)Ereignis Stop (UTC)Typ der NichtverfügbarkeitVeröffentlichungsdatum / -zeit (UTC)MaßeinheitNicht verfügbare KapazitätVerfügbare KapazitätTechnische KapazitätBilanzierungszoneName der Anlage
 
 
 
×
×
 
×
 
 
 
700000000000000000000000038_004MET Speicher GmbHInactiveStorage unavailability2022-10-09 06:00:002022-10-15 18:00:00Planned2022-09-23 09:11:28GWh1442.000000.000001442.0000037Y005053MH0000R, 21YNL----TTF---1UGS Etzel-ESE MET
690000000000000000000000038_003MET Speicher GmbHDismissedStorage unavailability2022-10-09 06:00:002022-10-17 18:00:00Planned2022-05-27 07:27:36GWh1485.000000.000001485.0000037Y005053MH0000R, 21YNL----TTF---1UGS Etzel-ESE MET
680000000000000000000000068_001MET Speicher GmbHInactiveInjection unavailability2022-05-23 06:00:002022-05-24 06:00:00Planned2022-05-20 07:18:54kWh/h639.00000333.00000972.0000037Y005053MH0000RUGS Reckrod
670000000000000000000000064_002MET Speicher GmbHInactiveInjection unavailability2022-05-19 06:00:002022-05-21 06:00:00Planned2022-05-19 14:09:03kWh/h491000.00000483000.00000974000.0000037Y005053MH0000RUGS Reckrod
660000000000000000000000060_002MET Speicher GmbHDismissedInjection unavailability2022-09-27 06:00:002022-10-18 14:00:00Planned2022-05-19 14:04:59kWh/h127737.00000127737.00000255474.0000021YNL----TTF---1UGS Etzel-ESE MET
650000000000000000000000059_002MET Speicher GmbHDismissedWithdrawal unavailability2022-09-27 06:00:002022-10-18 14:00:00Planned2022-05-19 14:04:13kWh/h209488.00000209489.00000418977.0000021YNL----TTF---1UGS Etzel-ESE MET
640000000000000000000000064_001MET Speicher GmbHDismissedInjection unavailability2022-05-19 06:00:002022-05-20 06:00:00Planned2022-05-18 13:23:03kWh/h491000.00000483000.00000974000.0000037Y005053MH0000RUGS Reckrod
630000000000000000000000063_001MET Speicher GmbHInactiveInjection unavailability2022-05-18 14:00:002022-05-19 06:00:00Planned2022-05-17 14:15:59kWh/h479000.00000500000.00000979000.0000037Y005053MH0000RUGS Reckrod
620000000000000000000000062_001MET Speicher GmbHInactiveInjection unavailability2022-05-18 06:00:002022-05-18 14:00:00Planned2022-05-17 14:14:20kWh/h979000.000000.00000979000.0000037Y005053MH0000RUGS Reckrod
610000000000000000000000057_002MET Speicher GmbHInactiveInjection unavailability2022-05-17 00:00:002022-05-18 06:00:00Planned2022-05-17 14:12:06kWh/h754000.00000225000.00000979000.0000037Y005053MH0000RUGS Reckrod
600000000000000000000000060_001MET Speicher GmbHDismissedInjection unavailability2022-09-27 06:00:002022-10-18 14:00:00Planned2022-05-16 15:32:43kWh/h127737.00000127737.00000255474.0000021YNL----TTF---1UGS Etzel-ESE MET
590000000000000000000000059_001MET Speicher GmbHDismissedWithdrawal unavailability2022-09-27 06:00:002022-10-18 14:00:00Planned2022-05-16 15:30:18kWh/h209488.00000209489.00000418977.0000021YNL----TTF---1UGS Etzel-ESE MET
580000000000000000000000058_001MET Speicher GmbHDismissedInjection unavailability2022-10-10 08:00:002022-12-16 16:00:00Planned2022-05-16 15:08:19kWh/h640000.000001275000.000001915000.0000037Y005053MH0000R, 21YNL----TTF---1UGS Etzel-ESE MET
570000000000000000000000057_001MET Speicher GmbHDismissedInjection unavailability2022-05-17 00:00:002022-05-18 00:00:00Planned2022-05-16 10:15:11kWh/h754000.00000225000.00000979000.0000037Y005053MH0000RUGS Reckrod
560000000000000000000000038_002MET Speicher GmbHDismissedStorage unavailability2022-10-07 06:00:002022-10-15 18:00:00Planned2022-05-16 07:16:06GWh1485.000000.000001485.0000037Y005053MH0000R, 21YNL----TTF---1UGS Etzel-ESE MET
550000000000000000000000055_001MET Speicher GmbHInactiveInjection unavailability2022-05-16 00:00:002022-05-17 00:00:00Planned2022-05-13 12:49:10kWh/h679000.00000300000.00000979000.0000037Y005053MH0000RUGS Reckrod
540000000000000000000000051_004MET Speicher GmbHInactiveInjection unavailability2022-05-13 00:00:002022-05-16 00:00:00Planned2022-05-13 12:45:08kWh/h529000.00000450000.00000979000.0000037Y005053MH0000RUGS Reckrod
530000000000000000000000051_003MET Speicher GmbHDismissedInjection unavailability2022-05-13 00:00:002022-05-14 00:00:00Planned2022-05-12 13:09:45kWh/h529000.00000450000.00000979000.0000037Y005053MH0000RUGS Reckrod
520000000000000000000000051_002MET Speicher GmbHDismissedInjection unavailability2022-05-13 08:00:002022-05-13 16:00:00Planned2022-05-12 13:07:50kWh/h979000.000000.00000979000.0000037Y005053MH0000RUGS Reckrod
510000000000000000000000051_001MET Speicher GmbHDismissedInjection unavailability2022-05-13 08:00:002022-05-13 16:00:00Planned2022-05-12 13:04:05kWh/h979000.000000.00000979000.0000037Y005053MH0000RUGS Reckrod
Zeige 321-340 von 343 Einträgen.
 IDNachrichten IDMp NameEreignisstatusEreignistypEreignis Start (UTC)Ereignis Stop (UTC)Typ der NichtverfügbarkeitVeröffentlichungsdatum / -zeit (UTC)MaßeinheitInstallierte KapazitätKraftstofftypGebotszoneName der Anlage
 
 
 
×
×
 
×
 
 
 
 
1020000000000000000000000102_001Ineos oxide utilities NVInactiveProduction unavailability2023-08-28 00:00:002023-11-07 00:00:00Planned2023-01-30 09:43:50MW139.00000Fossil Gas10X1001A1001A094INESCO WKK
1010000000000000000000000101_001Stadtwerke Rostock AGInactiveProduction unavailability2022-10-04 14:00:002022-10-14 23:55:00Unplanned2022-10-04 12:33:40MW108.00000Fossil Gas11XSWROSTOCK---YRostock Marienehe Produktionsanlage
1000000000000000000000000100_001Electrica Energie Verde 1 SRLInactiveProduction unavailability2022-11-10 10:00:002022-11-10 14:00:00Planned2022-09-20 09:05:04MW7.50000Solar10XRO-TEL------2CEF Stanesti
990000000000000000000000099_001Electrica Energie Verde 1 SRLInactiveProduction unavailability2022-11-09 10:00:002022-11-09 16:00:00Planned2022-09-20 09:00:13MW7.50000Solar10YRO-TEL------PCEF Stanesti
980000000000000000000000098_001Electrica Energie Verde 1 SRLInactiveProduction unavailability2022-11-08 10:00:002022-11-08 16:00:00Planned2022-09-20 08:57:20MW7.50000Solar10YRO-TEL------PCEF Stanesti
970000000000000000000000097_001Electrica Energie Verde 1 SRLInactiveProduction unavailability2022-11-07 10:00:002022-11-07 16:00:00Planned2022-09-20 08:51:32MW7.50000Solar10YRO-TEL------PCEF Stanesti
950000000000000000000000095_001Stadtwerke Rostock AGInactiveProduction unavailability2022-06-10 00:00:002022-06-20 23:55:00Planned2022-06-09 05:36:11MW108.00000Fossil Gas11XSWROSTOCK---YRostock Marienehe Produktionsanlage
930000000000000000000000093_001Stadtwerke Rostock AGInactiveProduction unavailability2022-05-28 00:00:002022-06-20 23:55:00Planned2022-05-20 05:42:18MW108.00000Fossil Gas11XSWROSTOCK---YRostock Marienehe Produktionsanlage
920000000000000000000000092_001Stadtwerke Rostock AGInactiveProduction unavailability2022-04-18 00:00:002022-05-27 23:55:00Planned2022-04-19 12:24:57MW108.00000Fossil Gas11XSWROSTOCK---YRostock Marienehe Produktionsanlage
910000000000000000000000091_001Stadtwerke Rostock AGInactiveProduction unavailability2022-04-18 00:00:002022-05-27 23:55:00Planned2022-04-19 12:16:35MW36.00000Fossil Gas11XSWROSTOCK---YRostock Marienehe Produktionsanlage
900000000000000000000000090_001Energie Wasser BernInactiveProduction unavailability2022-09-05 07:00:002022-09-23 17:00:00Planned2022-02-08 08:38:49MW43.50000Fossil Gas10YCH-SWISSGRIDZGUD Energiezentrale Forsthaus
890000000000000000000000089_001Electrica Energie Verde 1 SRLInactiveProduction unavailability2022-02-01 08:00:002022-02-01 16:00:00Planned2022-01-27 11:55:01MW7.50000Solar10YRO-TEL------PCEF Stanesti
880000000000000000000000088_001Electrica Energie Verde 1 SRLInactiveProduction unavailability2021-12-16 10:00:002021-12-16 14:00:00Planned2021-12-03 11:42:26MW7.50000Solar10YRO-TEL------PCEF Stanesti
870000000000000000000000087_001Electrica Energie Verde 1 SRLInactiveProduction unavailability2021-12-15 10:00:002021-12-15 16:00:00Planned2021-12-03 11:39:52MW7.50000Solar10YRO-TEL------PCEF Stanesti
860000000000000000000000086_001Electrica Energie Verde 1 SRLInactiveProduction unavailability2021-12-14 10:00:002021-12-16 16:00:00Planned2021-12-03 11:37:12MW7.50000Solar10YRO-TEL------PCEF Stanesti
850000000000000000000000085_001Electrica Energie Verde 1 SRLInactiveProduction unavailability2021-12-13 10:00:002021-12-13 16:00:00Planned2021-12-03 11:32:56MW7.50000Solar10YRO-TEL------PCEF Stanesti
840000000000000000000000079_002Electrica Energie Verde 1 SRLDismissedProduction unavailability2022-04-28 08:00:002022-04-28 09:00:00Planned2021-07-26 06:15:51MW7.50000Solar10YRO-TEL------PCEF Stanesti
830000000000000000000000078_002Electrica Energie Verde 1 SRLDismissedProduction unavailability2022-04-27 08:00:002022-04-27 09:00:00Planned2021-07-23 11:07:35MW7.50000Solar10YRO-TEL------PCEF Stanesti
800000000000000000000000080_001Stadtwerke Rostock AGInactiveProduction unavailability2021-06-09 00:00:002021-08-01 00:00:00Planned2021-07-15 10:08:48MW108.00000Fossil Gas11XSWROSTOCK---YRostock Marienehe Produktionsanlage
790000000000000000000000079_001Electrica Energie Verde 1 SRLDismissedProduction unavailability2022-04-28 08:00:002022-04-28 09:00:00Planned2021-07-13 09:42:02MW7.50000Solar10YRO-TEL------PCEF Stanesti
Zeige 1-10 von 10 Einträgen.
 IDNachrichten IDMp NameEreignisstatusEreignis Start (UTC)Ereignis Stop (UTC)Veröffentlichungsdatum / -zeit (UTC)Bemerkungen
 
 
×
×
×
210000000000000000000000019_002Swissgrid AGInactive2026-06-24 09:00:002026-06-24 14:00:002026-06-24 14:30:02Please be informed that on Wednesday, 24 June 2026, from 09:00 CEST to 14:00 CEST, Swissgrid experienced an internal issue that disrupted data delivery processes to the Transparency Platform. As a result, all data items scheduled for submission during this period were affected.
Swissgrid is currently working to restore normal data delivery and to backfill the affected data.
We apologize for any inconvenience this may have caused and appreciate your understanding.
190000000000000000000000019_001Swissgrid AGActive2026-06-24 09:00:002026-06-24 14:00:002026-06-24 14:23:23Please be informed that on Wednesday, 24 June 2026, from 09:00 CEST to 14:00 CEST, Swissgrid experienced an internal issue that disrupted data delivery processes to the Transparency Platform. As a result, all data items scheduled for submission during this period were affected.
Swissgrid is currently working to restore normal data delivery and to backfill the affected data.
We apologize for any inconvenience this may have caused and appreciate your understanding.
180000000000000000000000018_001MET International AGActive2025-07-17 00:00:00(nicht gesetzt)2025-07-29 15:55:33MET International AG's regasification capacity is available due to termination of the TUA by MET International AG pursuant to its terms.
160000000000000000000000016_001Swissgrid AGInactive2026-02-01 00:00:002026-05-15 23:55:002025-06-20 12:30:16Information about the Swiss hydropower reserve administrated by Swissgrid on behalf of the Swiss national regulator ElCom according to the Swiss Ordinance on the establishment of a hydropower reserve is available on the website of ElCom. Today ElCom fixed a total energy volume of 250 GWh for the coming winter period (01 February 2026 until 15 May 2026). See https://www.elcom.admin.ch/elcom/de/home/dokumentation/weisungen.html
150000000000000000000000015_001Swissgrid AGInactive2025-02-18 08:00:002025-02-18 10:00:002025-02-14 13:53:46Information: At the request of the Swiss supervisory authority ElCom, Swissgrid (Swiss TSO) will coordinate an energy reserve test with a thermal reserve power plant between 18/02/2025 08:00 and 18/02/2025 10:00. During this period, an excess of approx. 500 MWh will be fed into the grid, which may have an impact on prices.
140000000000000000000000012_002Swissgrid AGDismissed2024-02-20 04:00:002024-02-21 19:00:002024-02-14 17:40:34Information: At the request of the Swiss supervisory authority ElCom, Swissgrid (Swiss TSO) will coordinate an energy reserve test with hydroelectric reserve, thermal reserve power plant and emergency power groups between 20/02/2024 04:00 and 21/02/2024 19:00. During this period, an excess of approx. 1’452.80 MWh will be fed into the grid, which may have an impact on prices.
130000000000000000000000013_001Swissgrid AGInactive2024-02-20 04:00:002024-02-21 19:00:002024-02-14 17:27:59UPDATE (reduced amount of energy)
Information: At the request of the Swiss supervisory authority ElCom, Swissgrid (Swiss TSO) will coordinate an energy reserve test with hydroelectric reserve, thermal reserve power plant and emergency power groups between 20/02/2024 04:00 and 21/02/2024 19:00. During this period, an excess of approx. 966.5 MWh will be fed into the grid, which may have an impact on prices.
120000000000000000000000012_001Swissgrid AGDismissed2024-02-20 04:00:002024-02-21 19:00:002024-02-13 15:04:43Information: At the request of the Swiss supervisory authority ElCom, Swissgrid (Swiss TSO) will coordinate an energy reserve test with hydroelectric reserve, thermal reserve power plant and emergency power groups between 20/02/2024 04:00 and 21/02/2024 19:00. During this period, an excess of approx. 1’452.80 MWh will be fed into the grid, which may have an impact on prices.
110000000000000000000000011_001Swissgrid AGInactive2022-12-01 00:00:002023-05-15 23:55:002022-10-25 13:42:46Information about the Swiss hydropower reserve administrated by Swissgrid according to the Swiss Ordinance on the establishment of a hydropower reserve is available on our website. Today Swissgrid procured a total energy volume of 400 GWh for the coming winter period (01 December 2022 until 15 May 2023). See https://www.swissgrid.ch/en/home/newsroom/newsfeed/20221025-01.html
100000000000000000000000010_001Swissgrid AGInactive2020-12-21 00:00:002022-01-05 00:00:002021-12-23 09:12:31A temporary price Cap and Floor was introduced for Swiss offers in TERRE. From delivery period of 21.12.2020 00:00 onwards the offers prices in TERRE from Switzerland have been limited to +/- 999 EUR/MWh.

The temporary price Cap and Floor will be removed as of 05.01.2022. For delivery periods from 05.01.2022 00:00 onwards, the relevant price Cap and Floor will be +/- 9’999 EUR/MWh.