 IDMessage IDMarket Participant NameEvent StatusType of EventEvent StartEvent StopType of UnavailabilityPublication date/timeUnit of MeasurementUnavailable CapacityAvailable CapacityTechnical CapacityBalancing Zone 1Affected Asset Name
 
 
 
×
×
 
×
 
 
630000000000000000000000063_001MET Speicher GmbHInactiveInjection unavailability2022-05-18 14:00:002022-05-19 06:00:00Planned2022-05-17 14:15:59kWh/h479000.00000500000.00000979000.0000037Y005053MH0000RUGS Reckrod
640000000000000000000000064_001MET Speicher GmbHDismissedInjection unavailability2022-05-19 06:00:002022-05-20 06:00:00Planned2022-05-18 13:23:03kWh/h491000.00000483000.00000974000.0000037Y005053MH0000RUGS Reckrod
670000000000000000000000064_002MET Speicher GmbHInactiveInjection unavailability2022-05-19 06:00:002022-05-21 06:00:00Planned2022-05-19 14:09:03kWh/h491000.00000483000.00000974000.0000037Y005053MH0000RUGS Reckrod
530000000000000000000000051_003MET Speicher GmbHDismissedInjection unavailability2022-05-13 00:00:002022-05-14 00:00:00Planned2022-05-12 13:09:45kWh/h529000.00000450000.00000979000.0000037Y005053MH0000RUGS Reckrod
540000000000000000000000051_004MET Speicher GmbHInactiveInjection unavailability2022-05-13 00:00:002022-05-16 00:00:00Planned2022-05-13 12:45:08kWh/h529000.00000450000.00000979000.0000037Y005053MH0000RUGS Reckrod
550000000000000000000000055_001MET Speicher GmbHInactiveInjection unavailability2022-05-16 00:00:002022-05-17 00:00:00Planned2022-05-13 12:49:10kWh/h679000.00000300000.00000979000.0000037Y005053MH0000RUGS Reckrod
570000000000000000000000057_001MET Speicher GmbHDismissedInjection unavailability2022-05-17 00:00:002022-05-18 00:00:00Planned2022-05-16 10:15:11kWh/h754000.00000225000.00000979000.0000037Y005053MH0000RUGS Reckrod
610000000000000000000000057_002MET Speicher GmbHInactiveInjection unavailability2022-05-17 00:00:002022-05-18 06:00:00Planned2022-05-17 14:12:06kWh/h754000.00000225000.00000979000.0000037Y005053MH0000RUGS Reckrod
590000000000000000000000059_001MET Speicher GmbHDismissedWithdrawal unavailability2022-09-27 06:00:002022-10-18 14:00:00Planned2022-05-16 15:30:18kWh/h209488.00000209489.00000418977.0000021YNL----TTF---1UGS Etzel-ESE MET
650000000000000000000000059_002MET Speicher GmbHDismissedWithdrawal unavailability2022-09-27 06:00:002022-10-18 14:00:00Planned2022-05-19 14:04:13kWh/h209488.00000209489.00000418977.0000021YNL----TTF---1UGS Etzel-ESE MET
420000000000000000000000042_001MET Speicher GmbHInactiveInjection unavailability2022-03-23 06:00:002022-03-24 18:00:00Planned2022-03-17 08:23:50kWh/h957000.00000170000.000001127000.0000037Y005053MH0000RUGS Reckrod
600000000000000000000000060_001MET Speicher GmbHDismissedInjection unavailability2022-09-27 06:00:002022-10-18 14:00:00Planned2022-05-16 15:32:43kWh/h127737.00000127737.00000255474.0000021YNL----TTF---1UGS Etzel-ESE MET
660000000000000000000000060_002MET Speicher GmbHDismissedInjection unavailability2022-09-27 06:00:002022-10-18 14:00:00Planned2022-05-19 14:04:59kWh/h127737.00000127737.00000255474.0000021YNL----TTF---1UGS Etzel-ESE MET
350000000000000000000000035_001MET Speicher GmbHDismissedStorage unavailability2022-03-17 18:00:002022-05-13 16:00:00Planned2022-01-03 16:53:00GWh11.756001473.244001485.0000037Y005053MH0000RUGS Etzel-ESE MET
490000000000000000000000035_002MET Speicher GmbHInactiveStorage unavailability2022-03-17 18:00:002022-05-20 16:00:00Planned2022-04-28 13:06:39GWh11.756001473.244001485.0000037Y005053MH0000RUGS Etzel-ESE MET
800000000000000000000000080_001MET Speicher GmbHDismissedStorage unavailability2023-04-04 16:00:002023-05-24 16:00:00Planned2022-11-11 15:56:34GWh15.000001427.000001442.0000037Y005053MH0000RUGS Etzel-ESE MET
860000000000000000000000080_002MET Speicher GmbHInactiveStorage unavailability2023-04-04 16:00:002023-05-09 16:00:00Planned2022-11-16 16:42:06GWh15.000001427.000001442.0000037Y005053MH0000RUGS Etzel-ESE MET
760000000000000000000000076_001MET Speicher GmbHDismissedStorage unavailability2023-02-10 08:00:002023-03-15 08:00:00Planned2022-11-11 15:55:29GWh17.000001425.000001442.0000037Y005053MH0000RUGS Etzel-ESE MET
820000000000000000000000076_002MET Speicher GmbHInactiveStorage unavailability2023-02-10 08:00:002023-03-17 08:00:00Planned2022-11-16 16:39:02GWh17.000001425.000001442.0000037Y005053MH0000RUGS Etzel-ESE MET
400000000000000000000000040_001MET Speicher GmbHInactiveWithdrawal unavailability2022-05-26 06:00:002022-07-22 18:00:00Planned2022-03-17 08:54:49GWh24.970001417.030001442.0000037Y005053MH0000RUGS Etzel-ESE MET
Showing 1-20 of 145 items.
 IDMessage IDMarket Participant NameEvent StatusType of EventEvent StartEvent StopType of UnavailabilityPublication date/timeUnit of MeasurementUnavailable CapacityAvailable CapacityInstalled CapacityFuel TypeBidding ZoneAffected Asset Name
 
 
 
×
×
 
×
 
 
 
1050000000000000000000000105_001Ineos oxide utilities NVInactiveProduction unavailability2023-02-05 12:15:002023-02-07 00:00:00Unplanned2023-02-05 11:21:51MW0.00000139.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
1340000000000000000000000134_001Ineos oxide utilities NVDismissedProduction unavailability2023-05-04 20:10:002023-05-05 13:00:00Unplanned2023-05-04 18:28:46MW4.50000134.50000139.00000Fossil Gas10X1001A1001A094INESCO WKK
1350000000000000000000000134_002Ineos oxide utilities NVDismissedProduction unavailability2023-05-04 20:10:002023-05-15 00:00:00Unplanned2023-05-05 08:01:17MW4.50000134.50000139.00000Fossil Gas10X1001A1001A094INESCO WKK
1360000000000000000000000134_003Ineos oxide utilities NVInactiveProduction unavailability2023-05-04 20:10:002023-05-20 00:00:00Unplanned2023-05-12 08:58:37MW4.50000134.50000139.00000Fossil Gas10X1001A1001A094INESCO WKK
1060000000000000000000000106_001Ineos oxide utilities NVDismissedProduction unavailability2023-02-12 22:35:002023-02-13 23:55:00Unplanned2023-02-12 21:26:46MW9.00000130.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
1070000000000000000000000106_002Ineos oxide utilities NVDismissedProduction unavailability2023-02-12 22:35:002023-02-13 23:55:00Unplanned2023-02-13 08:26:34MW9.00000130.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
1540000000000000000000000154_001Ineos oxide utilities NVDismissedProduction unavailability2023-06-12 21:15:002023-06-13 23:05:00Unplanned2023-06-12 19:10:48MW10.00000129.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
1550000000000000000000000154_002Ineos oxide utilities NVDismissedProduction unavailability2023-06-12 21:15:002023-07-01 00:00:00Unplanned2023-06-13 09:08:18MW10.00000129.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
1560000000000000000000000154_003Ineos oxide utilities NVInactiveProduction unavailability2023-06-12 21:15:002023-06-16 14:25:00Unplanned2023-06-16 12:21:44MW10.00000129.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
2170000000000000000000000217_001Ineos oxide utilities NVDismissedProduction unavailability2024-01-25 18:00:002024-01-27 00:00:00Unplanned2024-01-25 18:06:05MW10.00000129.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
2180000000000000000000000217_002Ineos oxide utilities NVDismissedProduction unavailability2024-01-25 18:00:002024-01-27 00:00:00Unplanned2024-01-25 18:07:12MW10.00000129.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
2190000000000000000000000217_003Ineos oxide utilities NVDismissedProduction unavailability2024-01-25 18:00:002024-01-11 00:40:00Unplanned2024-01-26 10:41:02MW10.00000129.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
2200000000000000000000000217_004Ineos oxide utilities NVDismissedProduction unavailability2024-01-25 18:00:002024-01-11 00:40:00Unplanned2024-01-27 07:34:16MW10.00000129.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
2210000000000000000000000217_005Ineos oxide utilities NVDismissedProduction unavailability2024-01-25 18:00:002024-01-26 11:40:00Unplanned2024-01-27 07:35:09MW10.00000129.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
2220000000000000000000000222_001Ineos oxide utilities NVDismissedProduction unavailability2024-02-08 20:15:002024-02-10 00:00:00Unplanned2024-02-08 19:18:16MW25.00000114.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
2230000000000000000000000222_002Ineos oxide utilities NVInactiveProduction unavailability2024-02-08 20:15:002024-02-09 14:30:00Unplanned2024-02-09 13:32:23MW25.00000114.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
1370000000000000000000000137_001Ineos oxide utilities NVDismissedProduction unavailability2023-05-13 21:00:002023-05-15 00:00:00Unplanned2023-05-13 19:19:52MW30.00000109.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
1380000000000000000000000137_002Ineos oxide utilities NVInactiveProduction unavailability2023-05-13 21:00:002023-05-17 00:00:00Unplanned2023-05-14 16:02:25MW30.00000109.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
1990000000000000000000000199_001Ineos oxide utilities NVDismissedProduction unavailability2023-12-23 10:00:002023-12-27 00:00:00Unplanned2023-12-23 08:52:04MW30.00000109.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
2000000000000000000000000199_002Ineos oxide utilities NVDismissedProduction unavailability2023-12-23 10:00:002023-12-28 00:00:00Unplanned2023-12-26 09:06:02MW30.00000109.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
Showing 1-5 of 5 items.
 IDMessage IDMarket Participant NameEvent StatusEvent StartEvent StopPublication date/timeRemarks
 
 
×
×
×
140000000000000000000000012_002Swissgrid AGDismissed2024-02-20 04:00:002024-02-21 19:00:002024-02-14 17:40:34Information: At the request of the Swiss supervisory authority ElCom, Swissgrid (Swiss TSO) will coordinate an energy reserve test with hydroelectric reserve, thermal reserve power plant and emergency power groups between 20/02/2024 04:00 and 21/02/2024 19:00. During this period, an excess of approx. 1’452.80 MWh will be fed into the grid, which may have an impact on prices.
130000000000000000000000013_001Swissgrid AGInactive2024-02-20 04:00:002024-02-21 19:00:002024-02-14 17:27:59UPDATE (reduced amount of energy)
Information: At the request of the Swiss supervisory authority ElCom, Swissgrid (Swiss TSO) will coordinate an energy reserve test with hydroelectric reserve, thermal reserve power plant and emergency power groups between 20/02/2024 04:00 and 21/02/2024 19:00. During this period, an excess of approx. 966.5 MWh will be fed into the grid, which may have an impact on prices.
120000000000000000000000012_001Swissgrid AGDismissed2024-02-20 04:00:002024-02-21 19:00:002024-02-13 15:04:43Information: At the request of the Swiss supervisory authority ElCom, Swissgrid (Swiss TSO) will coordinate an energy reserve test with hydroelectric reserve, thermal reserve power plant and emergency power groups between 20/02/2024 04:00 and 21/02/2024 19:00. During this period, an excess of approx. 1’452.80 MWh will be fed into the grid, which may have an impact on prices.
110000000000000000000000011_001Swissgrid AGInactive2022-12-01 00:00:002023-05-15 23:55:002022-10-25 13:42:46Information about the Swiss hydropower reserve administrated by Swissgrid according to the Swiss Ordinance on the establishment of a hydropower reserve is available on our website. Today Swissgrid procured a total energy volume of 400 GWh for the coming winter period (01 December 2022 until 15 May 2023). See https://www.swissgrid.ch/en/home/newsroom/newsfeed/20221025-01.html
100000000000000000000000010_001Swissgrid AGInactive2020-12-21 00:00:002022-01-05 00:00:002021-12-23 09:12:31A temporary price Cap and Floor was introduced for Swiss offers in TERRE. From delivery period of 21.12.2020 00:00 onwards the offers prices in TERRE from Switzerland have been limited to +/- 999 EUR/MWh.

The temporary price Cap and Floor will be removed as of 05.01.2022. For delivery periods from 05.01.2022 00:00 onwards, the relevant price Cap and Floor will be +/- 9’999 EUR/MWh.