 IDMessage IDMarket Participant NameEvent StatusType of EventEvent StartEvent StopType of UnavailabilityPublication date/timeUnit of MeasurementUnavailable CapacityAvailable CapacityTechnical CapacityBalancing Zone 1Affected Asset Name
 
 
 
×
×
 
×
 
 
650000000000000000000000059_002MET Speicher GmbHDismissedWithdrawal unavailability2022-09-27 06:00:002022-10-18 14:00:00Planned2022-05-19 14:04:13kWh/h209488.00000209489.00000418977.0000021YNL----TTF---1UGS Etzel-ESE MET
660000000000000000000000060_002MET Speicher GmbHDismissedInjection unavailability2022-09-27 06:00:002022-10-18 14:00:00Planned2022-05-19 14:04:59kWh/h127737.00000127737.00000255474.0000021YNL----TTF---1UGS Etzel-ESE MET
690000000000000000000000038_003MET Speicher GmbHDismissedStorage unavailability2022-10-09 06:00:002022-10-17 18:00:00Planned2022-05-27 07:27:36GWh1485.000000.000001485.0000037Y005053MH0000RUGS Etzel-ESE MET
720000000000000000000000048_002MET Speicher GmbHDismissedStorage unavailability2022-10-18 06:00:002022-11-11 16:00:00Planned2022-10-13 06:22:49GWh1461.000000.000001461.0000037Y005053MH0000RUGS Reckrod
750000000000000000000000075_001MET Speicher GmbHDismissedWithdrawal unavailability2023-02-10 08:00:002023-03-15 08:00:00Planned2022-11-11 15:55:15kWh/h85500.000001829500.000001915000.0000037Y005053MH0000RUGS Etzel-ESE MET
760000000000000000000000076_001MET Speicher GmbHDismissedStorage unavailability2023-02-10 08:00:002023-03-15 08:00:00Planned2022-11-11 15:55:29GWh17.000001425.000001442.0000037Y005053MH0000RUGS Etzel-ESE MET
770000000000000000000000077_001MET Speicher GmbHDismissedWithdrawal unavailability2023-03-15 08:00:002023-04-04 16:00:00Planned2022-11-11 15:55:50kWh/h155500.000001759500.000001915000.0000037Y005053MH0000RUGS Etzel-ESE MET
780000000000000000000000078_001MET Speicher GmbHDismissedStorage unavailability2023-03-15 08:00:002023-04-04 16:00:00Planned2022-11-11 15:56:03GWh32.000001410.000001442.0000037Y005053MH0000RUGS Etzel-ESE MET
790000000000000000000000079_001MET Speicher GmbHDismissedWithdrawal unavailability2023-04-04 16:00:002023-05-24 16:00:00Planned2022-11-11 15:56:21kWh/h70000.000001845000.000001915000.0000037Y005053MH0000RUGS Etzel-ESE MET
800000000000000000000000080_001MET Speicher GmbHDismissedStorage unavailability2023-04-04 16:00:002023-05-24 16:00:00Planned2022-11-11 15:56:34GWh15.000001427.000001442.0000037Y005053MH0000RUGS Etzel-ESE MET
170000000000000000000000016_002astora GmbH and Co. KGInactiveInjection unavailability2020-11-02 08:00:002020-12-11 18:00:00Planned2020-06-10 09:41:22KWh/h14365000.000000.0000014365000.0000037Z0000000052293Rehden natural gas storage facility
200000000000000000000000020_001astora GmbH and Co. KGInactiveInjection unavailability2021-10-04 06:00:002021-10-15 18:00:00Planned2021-05-25 12:09:00KWh/h14365000.000000.0000014365000.0000037Z0000000052293Rehden natural gas storage facility
210000000000000000000000021_001astora GmbH and Co. KGInactiveWithdrawal unavailability2021-10-04 06:00:002021-10-15 18:00:00Planned2021-05-26 19:21:51KWh/h22100000.000000.0000022100000.0000037Z0000000052293Rehden natural gas storage facility
230000000000000000000000023_001astora GmbH and Co. KGInactiveInjection unavailability2021-10-19 16:00:002021-10-26 16:00:00Planned2021-05-28 08:11:06KWh/h2066166.000002066166.000004132332.0000037Y701133MH0000PUGS Haidach - Astora - Injection
240000000000000000000000022_002astora GmbH and Co. KGInactiveInjection unavailability2021-10-26 16:00:002021-11-17 22:00:00Planned2021-05-28 08:18:49KWh/h1033083.000003099249.000004132332.0000037Y701133MH0000PUGS Haidach - Astora - Injection
260000000000000000000000025_002astora GmbH and Co. KGInactiveInjection unavailability2021-10-04 07:00:002021-10-19 16:00:00Planned2021-05-30 15:14:10KWh/h4132332.000000.000004132332.0000037Y701133MH0000PUGS Haidach - Astora - Injection
290000000000000000000000027_003astora GmbH and Co. KGInactiveWithdrawal unavailability2021-10-04 07:00:002021-10-19 16:00:00Planned2021-06-04 12:43:09kWh/h4357733.000000.000004357733.0000037Y701133MH0000PUGS Haidach - Astora - Withdrawal
300000000000000000000000030_001astora GmbH and Co. KGInactiveInjection unavailability2021-06-07 07:00:002021-06-09 16:00:00Planned2021-06-04 12:48:20kWh/h4132332.000000.000004132332.0000037Y701133MH0000PUGS Haidach - Astora - Injection
310000000000000000000000031_001astora GmbH and Co. KGInactiveWithdrawal unavailability2021-06-07 07:00:002021-06-09 16:00:00Planned2021-06-07 22:59:18kWh/h4357733.000000.000004357733.0000037Y701133MH0000PUGS Haidach - Astora - Withdrawal
320000000000000000000000032_001MET Speicher GmbHInactiveInjection unavailability2022-01-03 08:00:002022-01-16 16:00:00Planned2022-01-03 16:51:54kWh/h750750.000001524250.000002275000.0000037Y005053MH0000RUGS Etzel-ESE MET
Showing 121-140 of 145 items.
 IDMessage IDMarket Participant NameEvent StatusType of EventEvent StartEvent StopType of UnavailabilityPublication date/timeUnit of MeasurementUnavailable CapacityAvailable CapacityInstalled CapacityFuel TypeBidding ZoneAffected Asset Name
 
 
 
×
×
 
×
 
 
 
1420000000000000000000000142_001Stadtwerke Rostock AGInactiveProduction unavailability2023-04-11 00:00:002023-06-21 23:55:00Planned2023-06-01 12:28:30MW36.0000072.00000108.00000Fossil Gas11XSWROSTOCK---YRostock Marienehe Produktionsanlage
1440000000000000000000000144_001Stadtwerke Rostock AGInactiveProduction unavailability2023-06-23 00:00:002023-08-04 23:55:00Planned2023-06-05 07:29:53MW36.0000072.00000108.00000Fossil Gas11XSWROSTOCK---YRostock Marienehe Produktionsanlage
1450000000000000000000000145_001Stadtwerke Rostock AGInactiveProduction unavailability2023-08-11 00:00:002023-09-01 23:55:00Planned2023-06-05 07:41:02MW36.0000072.00000108.00000Fossil Gas11XSWROSTOCK---YRostock Marienehe Produktionsanlage
1460000000000000000000000146_001Stadtwerke Rostock AGInactiveProduction unavailability2023-09-15 00:00:002023-09-20 23:55:00Planned2023-06-05 07:43:10MW36.0000072.00000108.00000Fossil Gas11XSWROSTOCK---YRostock Marienehe Produktionsanlage
1530000000000000000000000139_010Ineos oxide utilities NVInactiveProduction unavailability2023-05-21 00:00:002023-06-12 17:00:00Planned2023-06-12 14:05:52MW87.0000052.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
1560000000000000000000000154_003Ineos oxide utilities NVInactiveProduction unavailability2023-06-12 21:15:002023-06-16 14:25:00Unplanned2023-06-16 12:21:44MW10.00000129.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
1600000000000000000000000160_001Ineos oxide utilities NVInactiveProduction unavailability2023-08-30 10:00:002023-08-31 15:00:00Planned2023-08-23 14:13:11MW98.0000041.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
1720000000000000000000000161_004Ineos oxide utilities NVInactiveProduction unavailability2023-08-31 15:00:002023-10-06 00:00:00Planned2023-10-02 08:06:14MW92.5000046.50000139.00000Fossil Gas10X1001A1001A094INESCO WKK
1750000000000000000000000162_006Ineos oxide utilities NVInactiveProduction unavailability2023-10-06 00:00:002023-10-09 10:00:00Planned2023-10-06 17:13:38MW98.0000041.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
1780000000000000000000000163_006Ineos oxide utilities NVInactiveProduction unavailability2023-10-09 10:00:002023-11-15 00:00:00Planned2023-10-27 16:12:17MW92.5000046.50000139.00000Fossil Gas10X1001A1001A094INESCO WKK
1880000000000000000000000180_006Ineos oxide utilities NVInactiveProduction unavailability2023-11-11 16:00:002023-11-22 18:00:00Unplanned2023-11-20 09:03:56MW117.0000022.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
1890000000000000000000000186_002Ineos oxide utilities NVInactiveProduction unavailability2023-11-22 18:00:002023-11-23 14:00:00Planned2023-11-20 09:04:52MW101.0000038.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
1900000000000000000000000187_002Ineos oxide utilities NVInactiveProduction unavailability2023-11-23 14:00:002023-11-29 00:00:00Planned2023-11-20 09:07:16MW93.0000046.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
1910000000000000000000000191_001Ineos oxide utilities NVInactiveProduction unavailability2023-11-23 10:00:002023-11-25 00:00:00Planned2023-11-22 08:53:37MW139.000000.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
1920000000000000000000000192_001Ineos oxide utilities NVInactiveProduction unavailability2023-12-04 16:00:002023-12-05 17:00:00Unplanned2023-12-04 15:37:15MW92.5000046.50000139.00000Fossil Gas10X1001A1001A094INESCO WKK
1930000000000000000000000193_001Ineos oxide utilities NVInactiveProduction unavailability2023-12-07 15:00:002023-12-09 00:00:00Planned2023-12-07 10:02:15MW92.5000046.50000139.00000Fossil Gas10X1001A1001A094INESCO WKK
1950000000000000000000000164_006Ineos oxide utilities NVInactiveProduction unavailability2023-11-15 00:00:002023-12-09 00:00:00Planned2023-12-09 09:47:31MW98.0000041.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
1970000000000000000000000197_001Ineos oxide utilities NVInactiveProduction unavailability2023-12-14 08:00:002023-12-15 00:00:00Unplanned2023-12-14 07:53:19MW95.0000044.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
1980000000000000000000000196_002Ineos oxide utilities NVInactiveProduction unavailability2023-12-09 00:00:002023-12-22 15:00:00Planned2023-12-22 18:17:40MW46.0000093.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
2010000000000000000000000199_003Ineos oxide utilities NVInactiveProduction unavailability2023-12-23 10:00:002024-01-03 00:00:00Unplanned2023-12-26 11:25:37MW30.00000109.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
Showing 1-5 of 5 items.
 IDMessage IDMarket Participant NameEvent StatusEvent StartEvent StopPublication date/timeRemarks
 
 
×
×
×
120000000000000000000000012_001Swissgrid AGDismissed2024-02-20 04:00:002024-02-21 19:00:002024-02-13 15:04:43Information: At the request of the Swiss supervisory authority ElCom, Swissgrid (Swiss TSO) will coordinate an energy reserve test with hydroelectric reserve, thermal reserve power plant and emergency power groups between 20/02/2024 04:00 and 21/02/2024 19:00. During this period, an excess of approx. 1’452.80 MWh will be fed into the grid, which may have an impact on prices.
140000000000000000000000012_002Swissgrid AGDismissed2024-02-20 04:00:002024-02-21 19:00:002024-02-14 17:40:34Information: At the request of the Swiss supervisory authority ElCom, Swissgrid (Swiss TSO) will coordinate an energy reserve test with hydroelectric reserve, thermal reserve power plant and emergency power groups between 20/02/2024 04:00 and 21/02/2024 19:00. During this period, an excess of approx. 1’452.80 MWh will be fed into the grid, which may have an impact on prices.
100000000000000000000000010_001Swissgrid AGInactive2020-12-21 00:00:002022-01-05 00:00:002021-12-23 09:12:31A temporary price Cap and Floor was introduced for Swiss offers in TERRE. From delivery period of 21.12.2020 00:00 onwards the offers prices in TERRE from Switzerland have been limited to +/- 999 EUR/MWh.

The temporary price Cap and Floor will be removed as of 05.01.2022. For delivery periods from 05.01.2022 00:00 onwards, the relevant price Cap and Floor will be +/- 9’999 EUR/MWh.
110000000000000000000000011_001Swissgrid AGInactive2022-12-01 00:00:002023-05-15 23:55:002022-10-25 13:42:46Information about the Swiss hydropower reserve administrated by Swissgrid according to the Swiss Ordinance on the establishment of a hydropower reserve is available on our website. Today Swissgrid procured a total energy volume of 400 GWh for the coming winter period (01 December 2022 until 15 May 2023). See https://www.swissgrid.ch/en/home/newsroom/newsfeed/20221025-01.html
130000000000000000000000013_001Swissgrid AGInactive2024-02-20 04:00:002024-02-21 19:00:002024-02-14 17:27:59UPDATE (reduced amount of energy)
Information: At the request of the Swiss supervisory authority ElCom, Swissgrid (Swiss TSO) will coordinate an energy reserve test with hydroelectric reserve, thermal reserve power plant and emergency power groups between 20/02/2024 04:00 and 21/02/2024 19:00. During this period, an excess of approx. 966.5 MWh will be fed into the grid, which may have an impact on prices.