 IDMessage IDMarket Participant NameEvent StatusType of EventEvent StartEvent StopType of UnavailabilityPublication date/timeUnit of MeasurementUnavailable CapacityAvailable CapacityTechnical CapacityBalancing Zone 1Affected Asset Name
 
 
 
×
×
 
×
 
 
330000000000000000000000033_001MET Speicher GmbHInactiveInjection unavailability2022-01-17 08:00:002022-03-25 16:00:00Planned2022-01-03 16:52:30kWh/h750750.000001524250.000002275000.0000037Y005053MH0000RUGS Etzel-ESE MET
340000000000000000000000034_001MET Speicher GmbHInactiveWithdrawal unavailability2022-01-17 08:00:002022-03-25 16:00:00Planned2022-01-03 16:52:47kWh/h631950.000001283050.000001915000.0000037Y005053MH0000RUGS Etzel-ESE MET
370000000000000000000000037_001MET Speicher GmbHInactiveOther unavailability2022-09-21 08:00:002022-09-21 18:00:00Planned2022-01-03 16:53:25kWh/h419000.000000.00000419000.0000021YNL----TTF---1UGS Etzel-ESE MET
390000000000000000000000039_001MET Speicher GmbHInactiveInjection unavailability2022-05-26 06:00:002022-07-22 18:00:00Planned2022-03-17 08:54:32GWh68.440001373.560001442.0000037Y005053MH0000RUGS Etzel-ESE MET
400000000000000000000000040_001MET Speicher GmbHInactiveWithdrawal unavailability2022-05-26 06:00:002022-07-22 18:00:00Planned2022-03-17 08:54:49GWh24.970001417.030001442.0000037Y005053MH0000RUGS Etzel-ESE MET
410000000000000000000000041_001MET Speicher GmbHInactiveWithdrawal unavailability2022-03-23 06:00:002022-03-24 18:00:00Planned2022-03-17 08:23:25kWh/h2063000.000000.000002063000.0000037Y005053MH0000RUGS Reckrod
420000000000000000000000042_001MET Speicher GmbHInactiveInjection unavailability2022-03-23 06:00:002022-03-24 18:00:00Planned2022-03-17 08:23:50kWh/h957000.00000170000.000001127000.0000037Y005053MH0000RUGS Reckrod
430000000000000000000000043_001MET Speicher GmbHInactiveInjection unavailability2022-07-11 06:00:002022-07-15 16:00:00Planned2022-04-25 15:18:56kWh/h1031000.000000.000001031000.0000037Y005053MH0000RUGS Reckrod
440000000000000000000000044_001MET Speicher GmbHInactiveInjection unavailability2022-07-18 06:00:002022-07-22 16:00:00Planned2022-04-25 15:19:50kWh/h515500.00000515500.000001031000.0000037Y005053MH0000RUGS Reckrod
450000000000000000000000045_001MET Speicher GmbHInactiveWithdrawal unavailability2022-07-18 06:00:002022-07-22 16:00:00Planned2022-04-25 15:20:44kWh/h1031500.000001031500.000002063000.0000037Y005053MH0000RUGS Reckrod
460000000000000000000000046_001MET Speicher GmbHInactiveInjection unavailability2022-07-25 06:00:002022-07-29 16:00:00Planned2022-04-25 15:21:37kWh/h515500.00000515500.000001031000.0000037Y005053MH0000RUGS Reckrod
470000000000000000000000047_001MET Speicher GmbHInactiveWithdrawal unavailability2022-07-25 06:00:002022-07-29 16:00:00Planned2022-04-25 15:22:28kWh/h1031500.000001031500.000002063000.0000037Y005053MH0000RUGS Reckrod
490000000000000000000000035_002MET Speicher GmbHInactiveStorage unavailability2022-03-17 18:00:002022-05-20 16:00:00Planned2022-04-28 13:06:39GWh11.756001473.244001485.0000037Y005053MH0000RUGS Etzel-ESE MET
500000000000000000000000036_002MET Speicher GmbHInactiveWithdrawal unavailability2022-03-17 18:00:002022-05-20 16:00:00Planned2022-04-28 13:07:34kWh/h95750.000001819250.000001915000.0000037Y005053MH0000RUGS Etzel-ESE MET
540000000000000000000000051_004MET Speicher GmbHInactiveInjection unavailability2022-05-13 00:00:002022-05-16 00:00:00Planned2022-05-13 12:45:08kWh/h529000.00000450000.00000979000.0000037Y005053MH0000RUGS Reckrod
550000000000000000000000055_001MET Speicher GmbHInactiveInjection unavailability2022-05-16 00:00:002022-05-17 00:00:00Planned2022-05-13 12:49:10kWh/h679000.00000300000.00000979000.0000037Y005053MH0000RUGS Reckrod
610000000000000000000000057_002MET Speicher GmbHInactiveInjection unavailability2022-05-17 00:00:002022-05-18 06:00:00Planned2022-05-17 14:12:06kWh/h754000.00000225000.00000979000.0000037Y005053MH0000RUGS Reckrod
620000000000000000000000062_001MET Speicher GmbHInactiveInjection unavailability2022-05-18 06:00:002022-05-18 14:00:00Planned2022-05-17 14:14:20kWh/h979000.000000.00000979000.0000037Y005053MH0000RUGS Reckrod
630000000000000000000000063_001MET Speicher GmbHInactiveInjection unavailability2022-05-18 14:00:002022-05-19 06:00:00Planned2022-05-17 14:15:59kWh/h479000.00000500000.00000979000.0000037Y005053MH0000RUGS Reckrod
670000000000000000000000064_002MET Speicher GmbHInactiveInjection unavailability2022-05-19 06:00:002022-05-21 06:00:00Planned2022-05-19 14:09:03kWh/h491000.00000483000.00000974000.0000037Y005053MH0000RUGS Reckrod
Showing 121-140 of 145 items.
 IDMessage IDMarket Participant NameEvent StatusType of EventEvent StartEvent StopType of UnavailabilityPublication date/timeUnit of MeasurementUnavailable CapacityAvailable CapacityInstalled CapacityFuel TypeBidding ZoneAffected Asset Name
 
 
 
×
×
 
×
 
 
 
1420000000000000000000000142_001Stadtwerke Rostock AGInactiveProduction unavailability2023-04-11 00:00:002023-06-21 23:55:00Planned2023-06-01 12:28:30MW36.0000072.00000108.00000Fossil Gas11XSWROSTOCK---YRostock Marienehe Produktionsanlage
1440000000000000000000000144_001Stadtwerke Rostock AGInactiveProduction unavailability2023-06-23 00:00:002023-08-04 23:55:00Planned2023-06-05 07:29:53MW36.0000072.00000108.00000Fossil Gas11XSWROSTOCK---YRostock Marienehe Produktionsanlage
1450000000000000000000000145_001Stadtwerke Rostock AGInactiveProduction unavailability2023-08-11 00:00:002023-09-01 23:55:00Planned2023-06-05 07:41:02MW36.0000072.00000108.00000Fossil Gas11XSWROSTOCK---YRostock Marienehe Produktionsanlage
1460000000000000000000000146_001Stadtwerke Rostock AGInactiveProduction unavailability2023-09-15 00:00:002023-09-20 23:55:00Planned2023-06-05 07:43:10MW36.0000072.00000108.00000Fossil Gas11XSWROSTOCK---YRostock Marienehe Produktionsanlage
1530000000000000000000000139_010Ineos oxide utilities NVInactiveProduction unavailability2023-05-21 00:00:002023-06-12 17:00:00Planned2023-06-12 14:05:52MW87.0000052.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
1560000000000000000000000154_003Ineos oxide utilities NVInactiveProduction unavailability2023-06-12 21:15:002023-06-16 14:25:00Unplanned2023-06-16 12:21:44MW10.00000129.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
1600000000000000000000000160_001Ineos oxide utilities NVInactiveProduction unavailability2023-08-30 10:00:002023-08-31 15:00:00Planned2023-08-23 14:13:11MW98.0000041.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
1720000000000000000000000161_004Ineos oxide utilities NVInactiveProduction unavailability2023-08-31 15:00:002023-10-06 00:00:00Planned2023-10-02 08:06:14MW92.5000046.50000139.00000Fossil Gas10X1001A1001A094INESCO WKK
1750000000000000000000000162_006Ineos oxide utilities NVInactiveProduction unavailability2023-10-06 00:00:002023-10-09 10:00:00Planned2023-10-06 17:13:38MW98.0000041.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
1780000000000000000000000163_006Ineos oxide utilities NVInactiveProduction unavailability2023-10-09 10:00:002023-11-15 00:00:00Planned2023-10-27 16:12:17MW92.5000046.50000139.00000Fossil Gas10X1001A1001A094INESCO WKK
1880000000000000000000000180_006Ineos oxide utilities NVInactiveProduction unavailability2023-11-11 16:00:002023-11-22 18:00:00Unplanned2023-11-20 09:03:56MW117.0000022.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
1890000000000000000000000186_002Ineos oxide utilities NVInactiveProduction unavailability2023-11-22 18:00:002023-11-23 14:00:00Planned2023-11-20 09:04:52MW101.0000038.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
1900000000000000000000000187_002Ineos oxide utilities NVInactiveProduction unavailability2023-11-23 14:00:002023-11-29 00:00:00Planned2023-11-20 09:07:16MW93.0000046.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
1910000000000000000000000191_001Ineos oxide utilities NVInactiveProduction unavailability2023-11-23 10:00:002023-11-25 00:00:00Planned2023-11-22 08:53:37MW139.000000.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
1920000000000000000000000192_001Ineos oxide utilities NVInactiveProduction unavailability2023-12-04 16:00:002023-12-05 17:00:00Unplanned2023-12-04 15:37:15MW92.5000046.50000139.00000Fossil Gas10X1001A1001A094INESCO WKK
1930000000000000000000000193_001Ineos oxide utilities NVInactiveProduction unavailability2023-12-07 15:00:002023-12-09 00:00:00Planned2023-12-07 10:02:15MW92.5000046.50000139.00000Fossil Gas10X1001A1001A094INESCO WKK
1950000000000000000000000164_006Ineos oxide utilities NVInactiveProduction unavailability2023-11-15 00:00:002023-12-09 00:00:00Planned2023-12-09 09:47:31MW98.0000041.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
1970000000000000000000000197_001Ineos oxide utilities NVInactiveProduction unavailability2023-12-14 08:00:002023-12-15 00:00:00Unplanned2023-12-14 07:53:19MW95.0000044.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
1980000000000000000000000196_002Ineos oxide utilities NVInactiveProduction unavailability2023-12-09 00:00:002023-12-22 15:00:00Planned2023-12-22 18:17:40MW46.0000093.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
2010000000000000000000000199_003Ineos oxide utilities NVInactiveProduction unavailability2023-12-23 10:00:002024-01-03 00:00:00Unplanned2023-12-26 11:25:37MW30.00000109.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
Showing 1-5 of 5 items.
 IDMessage IDMarket Participant NameEvent StatusEvent StartEvent StopPublication date/timeRemarks
 
 
×
×
×
120000000000000000000000012_001Swissgrid AGDismissed2024-02-20 04:00:002024-02-21 19:00:002024-02-13 15:04:43Information: At the request of the Swiss supervisory authority ElCom, Swissgrid (Swiss TSO) will coordinate an energy reserve test with hydroelectric reserve, thermal reserve power plant and emergency power groups between 20/02/2024 04:00 and 21/02/2024 19:00. During this period, an excess of approx. 1’452.80 MWh will be fed into the grid, which may have an impact on prices.
140000000000000000000000012_002Swissgrid AGDismissed2024-02-20 04:00:002024-02-21 19:00:002024-02-14 17:40:34Information: At the request of the Swiss supervisory authority ElCom, Swissgrid (Swiss TSO) will coordinate an energy reserve test with hydroelectric reserve, thermal reserve power plant and emergency power groups between 20/02/2024 04:00 and 21/02/2024 19:00. During this period, an excess of approx. 1’452.80 MWh will be fed into the grid, which may have an impact on prices.
100000000000000000000000010_001Swissgrid AGInactive2020-12-21 00:00:002022-01-05 00:00:002021-12-23 09:12:31A temporary price Cap and Floor was introduced for Swiss offers in TERRE. From delivery period of 21.12.2020 00:00 onwards the offers prices in TERRE from Switzerland have been limited to +/- 999 EUR/MWh.

The temporary price Cap and Floor will be removed as of 05.01.2022. For delivery periods from 05.01.2022 00:00 onwards, the relevant price Cap and Floor will be +/- 9’999 EUR/MWh.
110000000000000000000000011_001Swissgrid AGInactive2022-12-01 00:00:002023-05-15 23:55:002022-10-25 13:42:46Information about the Swiss hydropower reserve administrated by Swissgrid according to the Swiss Ordinance on the establishment of a hydropower reserve is available on our website. Today Swissgrid procured a total energy volume of 400 GWh for the coming winter period (01 December 2022 until 15 May 2023). See https://www.swissgrid.ch/en/home/newsroom/newsfeed/20221025-01.html
130000000000000000000000013_001Swissgrid AGInactive2024-02-20 04:00:002024-02-21 19:00:002024-02-14 17:27:59UPDATE (reduced amount of energy)
Information: At the request of the Swiss supervisory authority ElCom, Swissgrid (Swiss TSO) will coordinate an energy reserve test with hydroelectric reserve, thermal reserve power plant and emergency power groups between 20/02/2024 04:00 and 21/02/2024 19:00. During this period, an excess of approx. 966.5 MWh will be fed into the grid, which may have an impact on prices.