Showing 61-74 of 74 items.
 IDMessage IDMarket Participant NameEvent StatusType of EventEvent StartEvent StopType of UnavailabilityPublication date/timeUnit of MeasurementUnavailable CapacityAvailable CapacityTechnical CapacityBalancing Zone 1Affected Asset Name
 
 
 
×
×
 
×
 
 
230000000000000000000000023_001astora GmbH and Co. KGInactiveInjection unavailability2021-10-19 16:00:002021-10-26 16:00:00Planned2021-05-28 08:11:06KWh/h2066166.000002066166.000004132332.0000037Y701133MH0000PUGS Haidach - Astora - Injection
250000000000000000000000025_001astora GmbH and Co. KGDismissedOffshore pipeline unavailability2021-10-04 07:00:002021-10-19 16:00:00Planned2021-05-29 06:17:08KWh/h4132332.000000.000004132332.0000037Y701133MH0000PUGS Haidach - Astora - Injection
260000000000000000000000025_002astora GmbH and Co. KGInactiveInjection unavailability2021-10-04 07:00:002021-10-19 16:00:00Planned2021-05-30 15:14:10KWh/h4132332.000000.000004132332.0000037Y701133MH0000PUGS Haidach - Astora - Injection
270000000000000000000000027_001astora GmbH and Co. KGDismissedWithdrawal unavailability2021-10-04 07:00:002021-10-19 16:00:00Planned2021-05-30 15:20:09KWh/h4357733.000000.000004357733.0000037Y701133MH0000PUGS Haidach - Astora - Withdrawal
280000000000000000000000027_002astora GmbH and Co. KGDismissedWithdrawal unavailability2021-10-04 07:00:002021-10-19 16:05:00Planned2021-06-01 06:06:56KWh/h4357733.000000.000004357733.0000037Y701133MH0000PUGS Haidach - Astora - Withdrawal
290000000000000000000000027_003astora GmbH and Co. KGInactiveWithdrawal unavailability2021-10-04 07:00:002021-10-19 16:00:00Planned2021-06-04 12:43:09kWh/h4357733.000000.000004357733.0000037Y701133MH0000PUGS Haidach - Astora - Withdrawal
200000000000000000000000020_001astora GmbH and Co. KGInactiveInjection unavailability2021-10-04 06:00:002021-10-15 18:00:00Planned2021-05-25 12:09:00KWh/h14365000.000000.0000014365000.0000037Z0000000052293Rehden natural gas storage facility
210000000000000000000000021_001astora GmbH and Co. KGInactiveWithdrawal unavailability2021-10-04 06:00:002021-10-15 18:00:00Planned2021-05-26 19:21:51KWh/h22100000.000000.0000022100000.0000037Z0000000052293Rehden natural gas storage facility
300000000000000000000000030_001astora GmbH and Co. KGInactiveInjection unavailability2021-06-07 07:00:002021-06-09 16:00:00Planned2021-06-04 12:48:20kWh/h4132332.000000.000004132332.0000037Y701133MH0000PUGS Haidach - Astora - Injection
310000000000000000000000031_001astora GmbH and Co. KGInactiveWithdrawal unavailability2021-06-07 07:00:002021-06-09 16:00:00Planned2021-06-07 22:59:18kWh/h4357733.000000.000004357733.0000037Y701133MH0000PUGS Haidach - Astora - Withdrawal
170000000000000000000000016_002astora GmbH and Co. KGInactiveInjection unavailability2020-11-02 08:00:002020-12-11 18:00:00Planned2020-06-10 09:41:22KWh/h14365000.000000.0000014365000.0000037Z0000000052293Rehden natural gas storage facility
160000000000000000000000016_001astora GmbH and Co. KGDismissedInjection unavailability2020-10-05 06:00:002020-10-17 18:00:00Planned2020-06-10 09:31:00KWh/h14365000.000000.0000014365000.0000037Z0000000052293Rehden natural gas storage facility
180000000000000000000000018_001astora GmbH and Co. KGDismissedWithdrawal unavailability2020-10-05 06:00:002020-10-17 18:00:00Planned2020-06-10 09:51:11KWh/h22100000.000000.0000022100000.0000037Z0000000052293Rehden natural gas storage facility
190000000000000000000000018_002astora GmbH and Co. KGDismissedWithdrawal unavailability2020-10-05 06:00:002020-10-17 18:00:00Planned2020-06-10 09:57:00KWh/h22100000.000000.0000022100000.0000037Z0000000052293Rehden natural gas storage facility
Showing 61-80 of 147 items.
 IDMessage IDMarket Participant NameEvent StatusType of EventEvent StartEvent StopType of UnavailabilityPublication date/timeUnit of MeasurementUnavailable CapacityAvailable CapacityInstalled CapacityFuel TypeBidding ZoneAffected Asset Name
 
 
 
×
×
 
×
 
 
 
1710000000000000000000000162_004Ineos oxide utilities NVDismissedProduction unavailability2023-10-04 00:00:002023-10-05 15:00:00Planned2023-09-29 12:18:43MW98.0000041.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
1670000000000000000000000162_002Ineos oxide utilities NVDismissedProduction unavailability2023-10-03 00:00:002023-10-05 00:00:00Planned2023-09-21 08:13:00MW98.0000041.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
1690000000000000000000000162_003Ineos oxide utilities NVDismissedProduction unavailability2023-10-03 00:00:002023-10-05 15:00:00Planned2023-09-21 08:15:19MW98.0000041.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
1040000000000000000000000104_001Ineos oxide utilities NVInactiveProduction unavailability2023-10-02 00:00:002023-10-28 00:00:00Planned2023-01-30 10:00:55MW46.0000043.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
1630000000000000000000000163_001Ineos oxide utilities NVDismissedProduction unavailability2023-09-28 15:00:002023-10-24 00:00:00Planned2023-08-23 14:14:07MW92.5000046.50000139.00000Fossil Gas10X1001A1001A094INESCO WKK
1620000000000000000000000162_001Ineos oxide utilities NVDismissedProduction unavailability2023-09-26 00:00:002023-09-28 15:00:00Planned2023-08-23 14:13:47MW98.0000041.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
1460000000000000000000000146_001Stadtwerke Rostock AGInactiveProduction unavailability2023-09-15 00:00:002023-09-20 23:55:00Planned2023-06-05 07:43:10MW36.0000072.00000108.00000Fossil Gas11XSWROSTOCK---YRostock Marienehe Produktionsanlage
1030000000000000000000000103_001Ineos oxide utilities NVInactiveProduction unavailability2023-09-04 00:00:002023-09-23 00:00:00Planned2023-01-30 09:59:15MW46.0000043.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
1610000000000000000000000161_001Ineos oxide utilities NVDismissedProduction unavailability2023-08-31 15:00:002023-09-26 00:00:00Planned2023-08-23 14:13:30MW92.5000046.50000139.00000Fossil Gas10X1001A1001A094INESCO WKK
1680000000000000000000000161_002Ineos oxide utilities NVDismissedProduction unavailability2023-08-31 15:00:002023-10-03 00:00:00Planned2023-09-21 08:13:31MW92.5000046.50000139.00000Fossil Gas10X1001A1001A094INESCO WKK
1700000000000000000000000161_003Ineos oxide utilities NVDismissedProduction unavailability2023-08-31 15:00:002023-10-04 00:00:00Planned2023-09-29 12:18:20MW92.5000046.50000139.00000Fossil Gas10X1001A1001A094INESCO WKK
1720000000000000000000000161_004Ineos oxide utilities NVInactiveProduction unavailability2023-08-31 15:00:002023-10-06 00:00:00Planned2023-10-02 08:06:14MW92.5000046.50000139.00000Fossil Gas10X1001A1001A094INESCO WKK
1600000000000000000000000160_001Ineos oxide utilities NVInactiveProduction unavailability2023-08-30 10:00:002023-08-31 15:00:00Planned2023-08-23 14:13:11MW98.0000041.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
1020000000000000000000000102_001Ineos oxide utilities NVInactiveProduction unavailability2023-08-28 00:00:002023-11-07 00:00:00Planned2023-01-30 09:43:50MW50.0000089.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
1450000000000000000000000145_001Stadtwerke Rostock AGInactiveProduction unavailability2023-08-11 00:00:002023-09-01 23:55:00Planned2023-06-05 07:41:02MW36.0000072.00000108.00000Fossil Gas11XSWROSTOCK---YRostock Marienehe Produktionsanlage
1440000000000000000000000144_001Stadtwerke Rostock AGInactiveProduction unavailability2023-06-23 00:00:002023-08-04 23:55:00Planned2023-06-05 07:29:53MW36.0000072.00000108.00000Fossil Gas11XSWROSTOCK---YRostock Marienehe Produktionsanlage
1540000000000000000000000154_001Ineos oxide utilities NVDismissedProduction unavailability2023-06-12 21:15:002023-06-13 23:05:00Unplanned2023-06-12 19:10:48MW10.00000129.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
1550000000000000000000000154_002Ineos oxide utilities NVDismissedProduction unavailability2023-06-12 21:15:002023-07-01 00:00:00Unplanned2023-06-13 09:08:18MW10.00000129.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
1560000000000000000000000154_003Ineos oxide utilities NVInactiveProduction unavailability2023-06-12 21:15:002023-06-16 14:25:00Unplanned2023-06-16 12:21:44MW10.00000129.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
1410000000000000000000000141_001Stadtwerke Rostock AGInactiveProduction unavailability2023-06-02 00:00:002023-06-11 23:55:00Planned2023-05-25 08:07:11MW108.000000.00000108.00000Fossil Gas11XSWROSTOCK---YRostock Marienehe Produktionsanlage
Showing 1-5 of 5 items.
 IDMessage IDMarket Participant NameEvent StatusEvent StartEvent StopPublication date/timeRemarks
 
 
×
×
×
120000000000000000000000012_001Swissgrid AGDismissed2024-02-20 04:00:002024-02-21 19:00:002024-02-13 15:04:43Information: At the request of the Swiss supervisory authority ElCom, Swissgrid (Swiss TSO) will coordinate an energy reserve test with hydroelectric reserve, thermal reserve power plant and emergency power groups between 20/02/2024 04:00 and 21/02/2024 19:00. During this period, an excess of approx. 1’452.80 MWh will be fed into the grid, which may have an impact on prices.
130000000000000000000000013_001Swissgrid AGInactive2024-02-20 04:00:002024-02-21 19:00:002024-02-14 17:27:59UPDATE (reduced amount of energy)
Information: At the request of the Swiss supervisory authority ElCom, Swissgrid (Swiss TSO) will coordinate an energy reserve test with hydroelectric reserve, thermal reserve power plant and emergency power groups between 20/02/2024 04:00 and 21/02/2024 19:00. During this period, an excess of approx. 966.5 MWh will be fed into the grid, which may have an impact on prices.
140000000000000000000000012_002Swissgrid AGDismissed2024-02-20 04:00:002024-02-21 19:00:002024-02-14 17:40:34Information: At the request of the Swiss supervisory authority ElCom, Swissgrid (Swiss TSO) will coordinate an energy reserve test with hydroelectric reserve, thermal reserve power plant and emergency power groups between 20/02/2024 04:00 and 21/02/2024 19:00. During this period, an excess of approx. 1’452.80 MWh will be fed into the grid, which may have an impact on prices.
110000000000000000000000011_001Swissgrid AGInactive2022-12-01 00:00:002023-05-15 23:55:002022-10-25 13:42:46Information about the Swiss hydropower reserve administrated by Swissgrid according to the Swiss Ordinance on the establishment of a hydropower reserve is available on our website. Today Swissgrid procured a total energy volume of 400 GWh for the coming winter period (01 December 2022 until 15 May 2023). See https://www.swissgrid.ch/en/home/newsroom/newsfeed/20221025-01.html
100000000000000000000000010_001Swissgrid AGInactive2020-12-21 00:00:002022-01-05 00:00:002021-12-23 09:12:31A temporary price Cap and Floor was introduced for Swiss offers in TERRE. From delivery period of 21.12.2020 00:00 onwards the offers prices in TERRE from Switzerland have been limited to +/- 999 EUR/MWh.

The temporary price Cap and Floor will be removed as of 05.01.2022. For delivery periods from 05.01.2022 00:00 onwards, the relevant price Cap and Floor will be +/- 9’999 EUR/MWh.