ID | Nachrichten ID | Marktteilnehmer Name | Ereignisstatus | Ereignistyp | Ereignis Start | Ereignis Stop | Typ der Nichtverfügbarkeit | Veröffentlichungsdatum / -zeit | Maßeinheit | Nicht verfügbare Kapazität | Verfügbare Kapazität | Technische Kapazität | Bilanzierungszone 1 | Name der Anlage | |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
×
|
×
|
×
| |||||||||||||
56 | 0000000000000000000000038_002 | MET Speicher GmbH | Dismissed | Storage unavailability | 2022-10-07 06:00:00 | 2022-10-15 18:00:00 | Planned | 2022-05-16 07:16:06 | GWh | 1485.00000 | 0.00000 | 1485.00000 | 37Y005053MH0000R | UGS Etzel-ESE MET | |
62 | 0000000000000000000000062_001 | MET Speicher GmbH | Inactive | Injection unavailability | 2022-05-18 06:00:00 | 2022-05-18 14:00:00 | Planned | 2022-05-17 14:14:20 | kWh/h | 979000.00000 | 0.00000 | 979000.00000 | 37Y005053MH0000R | UGS Reckrod | |
69 | 0000000000000000000000038_003 | MET Speicher GmbH | Dismissed | Storage unavailability | 2022-10-09 06:00:00 | 2022-10-17 18:00:00 | Planned | 2022-05-27 07:27:36 | GWh | 1485.00000 | 0.00000 | 1485.00000 | 37Y005053MH0000R | UGS Etzel-ESE MET | |
70 | 0000000000000000000000038_004 | MET Speicher GmbH | Inactive | Storage unavailability | 2022-10-09 06:00:00 | 2022-10-15 18:00:00 | Planned | 2022-09-23 09:11:28 | GWh | 1442.00000 | 0.00000 | 1442.00000 | 37Y005053MH0000R | UGS Etzel-ESE MET | |
72 | 0000000000000000000000048_002 | MET Speicher GmbH | Dismissed | Storage unavailability | 2022-10-18 06:00:00 | 2022-11-11 16:00:00 | Planned | 2022-10-13 06:22:49 | GWh | 1461.00000 | 0.00000 | 1461.00000 | 37Y005053MH0000R | UGS Reckrod | |
73 | 0000000000000000000000048_003 | MET Speicher GmbH | Inactive | Storage unavailability | 2022-10-18 06:00:00 | 2022-11-04 06:00:00 | Planned | 2022-11-03 18:13:45 | GWh | 1461.00000 | 0.00000 | 1461.00000 | 37Y005053MH0000R | UGS Reckrod | |
74 | 0000000000000000000000074_001 | MET Speicher GmbH | Inactive | Transmission system unavailability | 2023-09-20 08:00:00 | 2023-09-20 18:00:00 | Planned | 2022-11-11 14:59:13 | kWh/h | 418977.00000 | 0.00000 | 418977.00000 | 21YNL----TTF---1 | UGS Etzel-ESE MET | |
87 | 0000000000000000000000087_001 | MET Speicher GmbH | Inactive | Withdrawal unavailability | 2022-11-28 06:00:00 | 2022-11-30 06:00:00 | Planned | 2022-11-27 10:09:25 | GWh/d | 49.50000 | 0.00000 | 49.50000 | 37Y005053MH0000R | UGS Reckrod | |
88 | 0000000000000000000000088_001 | MET Speicher GmbH | Inactive | Withdrawal unavailability | 2022-12-06 06:00:00 | 2022-12-08 16:00:00 | Planned | 2022-12-05 14:34:56 | GWh/d | 49.50000 | 0.00000 | 49.50000 | 37Y005053MH0000R | UGS Reckrod | |
89 | 0000000000000000000000089_001 | MET Speicher GmbH | Inactive | Injection unavailability | 2023-02-28 18:00:00 | 2023-03-15 18:00:00 | Planned | 2023-02-28 10:40:36 | GWh/d | 24.74400 | 0.00000 | 24.74400 | 37Y005053MH0000R | UGS Reckrod | |
68 | 0000000000000000000000068_001 | MET Speicher GmbH | Inactive | Injection unavailability | 2022-05-23 06:00:00 | 2022-05-24 06:00:00 | Planned | 2022-05-20 07:18:54 | kWh/h | 639.00000 | 333.00000 | 972.00000 | 37Y005053MH0000R | UGS Reckrod | |
39 | 0000000000000000000000039_001 | MET Speicher GmbH | Inactive | Injection unavailability | 2022-05-26 06:00:00 | 2022-07-22 18:00:00 | Planned | 2022-03-17 08:54:32 | GWh | 68.44000 | 1373.56000 | 1442.00000 | 37Y005053MH0000R | UGS Etzel-ESE MET | |
78 | 0000000000000000000000078_001 | MET Speicher GmbH | Dismissed | Storage unavailability | 2023-03-15 08:00:00 | 2023-04-04 16:00:00 | Planned | 2022-11-11 15:56:03 | GWh | 32.00000 | 1410.00000 | 1442.00000 | 37Y005053MH0000R | UGS Etzel-ESE MET | |
84 | 0000000000000000000000078_002 | MET Speicher GmbH | Inactive | Storage unavailability | 2023-03-17 08:00:00 | 2023-04-04 16:00:00 | Planned | 2022-11-16 16:40:51 | GWh | 32.00000 | 1410.00000 | 1442.00000 | 37Y005053MH0000R | UGS Etzel-ESE MET | |
40 | 0000000000000000000000040_001 | MET Speicher GmbH | Inactive | Withdrawal unavailability | 2022-05-26 06:00:00 | 2022-07-22 18:00:00 | Planned | 2022-03-17 08:54:49 | GWh | 24.97000 | 1417.03000 | 1442.00000 | 37Y005053MH0000R | UGS Etzel-ESE MET | |
76 | 0000000000000000000000076_001 | MET Speicher GmbH | Dismissed | Storage unavailability | 2023-02-10 08:00:00 | 2023-03-15 08:00:00 | Planned | 2022-11-11 15:55:29 | GWh | 17.00000 | 1425.00000 | 1442.00000 | 37Y005053MH0000R | UGS Etzel-ESE MET | |
82 | 0000000000000000000000076_002 | MET Speicher GmbH | Inactive | Storage unavailability | 2023-02-10 08:00:00 | 2023-03-17 08:00:00 | Planned | 2022-11-16 16:39:02 | GWh | 17.00000 | 1425.00000 | 1442.00000 | 37Y005053MH0000R | UGS Etzel-ESE MET | |
80 | 0000000000000000000000080_001 | MET Speicher GmbH | Dismissed | Storage unavailability | 2023-04-04 16:00:00 | 2023-05-24 16:00:00 | Planned | 2022-11-11 15:56:34 | GWh | 15.00000 | 1427.00000 | 1442.00000 | 37Y005053MH0000R | UGS Etzel-ESE MET | |
86 | 0000000000000000000000080_002 | MET Speicher GmbH | Inactive | Storage unavailability | 2023-04-04 16:00:00 | 2023-05-09 16:00:00 | Planned | 2022-11-16 16:42:06 | GWh | 15.00000 | 1427.00000 | 1442.00000 | 37Y005053MH0000R | UGS Etzel-ESE MET | |
35 | 0000000000000000000000035_001 | MET Speicher GmbH | Dismissed | Storage unavailability | 2022-03-17 18:00:00 | 2022-05-13 16:00:00 | Planned | 2022-01-03 16:53:00 | GWh | 11.75600 | 1473.24400 | 1485.00000 | 37Y005053MH0000R | UGS Etzel-ESE MET |
ID | Nachrichten ID | Marktteilnehmer Name | Ereignisstatus | Ereignistyp | Ereignis Start | Ereignis Stop | Typ der Nichtverfügbarkeit | Veröffentlichungsdatum / -zeit | Maßeinheit | Nicht verfügbare Kapazität | Verfügbare Kapazität | Installierte Kapazität | Kraftstofftyp | Gebotszone | Name der Anlage | |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
×
|
×
|
×
| ||||||||||||||
198 | 0000000000000000000000196_002 | Ineos oxide utilities NV | Inactive | Production unavailability | 2023-12-09 00:00:00 | 2023-12-22 15:00:00 | Planned | 2023-12-22 18:17:40 | MW | 46.00000 | 93.00000 | 139.00000 | Fossil Gas | 10X1001A1001A094 | INESCO WKK | |
108 | 0000000000000000000000108_001 | Ineos oxide utilities NV | Dismissed | Production unavailability | 2023-03-09 20:00:00 | 2023-03-10 12:00:00 | Unplanned | 2023-03-09 19:08:04 | MW | 33.00000 | 106.00000 | 139.00000 | Fossil Gas | 10X1001A1001A094 | INESCO WKK | |
109 | 0000000000000000000000108_002 | Ineos oxide utilities NV | Dismissed | Production unavailability | 2023-03-09 20:00:00 | 2023-03-10 12:00:00 | Unplanned | 2023-03-10 09:58:07 | MW | 33.00000 | 106.00000 | 139.00000 | Fossil Gas | 10X1001A1001A094 | INESCO WKK | |
110 | 0000000000000000000000108_003 | Ineos oxide utilities NV | Dismissed | Production unavailability | 2023-03-09 20:00:00 | 2023-03-10 12:00:00 | Unplanned | 2023-03-10 10:00:18 | MW | 33.00000 | 106.00000 | 139.00000 | Fossil Gas | 10X1001A1001A094 | INESCO WKK | |
137 | 0000000000000000000000137_001 | Ineos oxide utilities NV | Dismissed | Production unavailability | 2023-05-13 21:00:00 | 2023-05-15 00:00:00 | Unplanned | 2023-05-13 19:19:52 | MW | 30.00000 | 109.00000 | 139.00000 | Fossil Gas | 10X1001A1001A094 | INESCO WKK | |
138 | 0000000000000000000000137_002 | Ineos oxide utilities NV | Inactive | Production unavailability | 2023-05-13 21:00:00 | 2023-05-17 00:00:00 | Unplanned | 2023-05-14 16:02:25 | MW | 30.00000 | 109.00000 | 139.00000 | Fossil Gas | 10X1001A1001A094 | INESCO WKK | |
199 | 0000000000000000000000199_001 | Ineos oxide utilities NV | Dismissed | Production unavailability | 2023-12-23 10:00:00 | 2023-12-27 00:00:00 | Unplanned | 2023-12-23 08:52:04 | MW | 30.00000 | 109.00000 | 139.00000 | Fossil Gas | 10X1001A1001A094 | INESCO WKK | |
200 | 0000000000000000000000199_002 | Ineos oxide utilities NV | Dismissed | Production unavailability | 2023-12-23 10:00:00 | 2023-12-28 00:00:00 | Unplanned | 2023-12-26 09:06:02 | MW | 30.00000 | 109.00000 | 139.00000 | Fossil Gas | 10X1001A1001A094 | INESCO WKK | |
201 | 0000000000000000000000199_003 | Ineos oxide utilities NV | Inactive | Production unavailability | 2023-12-23 10:00:00 | 2024-01-03 00:00:00 | Unplanned | 2023-12-26 11:25:37 | MW | 30.00000 | 109.00000 | 139.00000 | Fossil Gas | 10X1001A1001A094 | INESCO WKK | |
202 | 0000000000000000000000202_001 | Ineos oxide utilities NV | Dismissed | Production unavailability | 2024-01-05 08:40:00 | 2024-01-10 00:00:00 | Unplanned | 2024-01-05 07:36:25 | MW | 30.00000 | 109.00000 | 139.00000 | Fossil Gas | 10X1001A1001A094 | INESCO WKK | |
210 | 0000000000000000000000202_002 | Ineos oxide utilities NV | Inactive | Production unavailability | 2024-01-05 08:40:00 | 2024-01-17 00:00:00 | Unplanned | 2024-01-09 10:05:15 | MW | 30.00000 | 109.00000 | 139.00000 | Fossil Gas | 10X1001A1001A094 | INESCO WKK | |
222 | 0000000000000000000000222_001 | Ineos oxide utilities NV | Dismissed | Production unavailability | 2024-02-08 20:15:00 | 2024-02-10 00:00:00 | Unplanned | 2024-02-08 19:18:16 | MW | 25.00000 | 114.00000 | 139.00000 | Fossil Gas | 10X1001A1001A094 | INESCO WKK | |
223 | 0000000000000000000000222_002 | Ineos oxide utilities NV | Inactive | Production unavailability | 2024-02-08 20:15:00 | 2024-02-09 14:30:00 | Unplanned | 2024-02-09 13:32:23 | MW | 25.00000 | 114.00000 | 139.00000 | Fossil Gas | 10X1001A1001A094 | INESCO WKK | |
154 | 0000000000000000000000154_001 | Ineos oxide utilities NV | Dismissed | Production unavailability | 2023-06-12 21:15:00 | 2023-06-13 23:05:00 | Unplanned | 2023-06-12 19:10:48 | MW | 10.00000 | 129.00000 | 139.00000 | Fossil Gas | 10X1001A1001A094 | INESCO WKK | |
155 | 0000000000000000000000154_002 | Ineos oxide utilities NV | Dismissed | Production unavailability | 2023-06-12 21:15:00 | 2023-07-01 00:00:00 | Unplanned | 2023-06-13 09:08:18 | MW | 10.00000 | 129.00000 | 139.00000 | Fossil Gas | 10X1001A1001A094 | INESCO WKK | |
156 | 0000000000000000000000154_003 | Ineos oxide utilities NV | Inactive | Production unavailability | 2023-06-12 21:15:00 | 2023-06-16 14:25:00 | Unplanned | 2023-06-16 12:21:44 | MW | 10.00000 | 129.00000 | 139.00000 | Fossil Gas | 10X1001A1001A094 | INESCO WKK | |
217 | 0000000000000000000000217_001 | Ineos oxide utilities NV | Dismissed | Production unavailability | 2024-01-25 18:00:00 | 2024-01-27 00:00:00 | Unplanned | 2024-01-25 18:06:05 | MW | 10.00000 | 129.00000 | 139.00000 | Fossil Gas | 10X1001A1001A094 | INESCO WKK | |
218 | 0000000000000000000000217_002 | Ineos oxide utilities NV | Dismissed | Production unavailability | 2024-01-25 18:00:00 | 2024-01-27 00:00:00 | Unplanned | 2024-01-25 18:07:12 | MW | 10.00000 | 129.00000 | 139.00000 | Fossil Gas | 10X1001A1001A094 | INESCO WKK | |
219 | 0000000000000000000000217_003 | Ineos oxide utilities NV | Dismissed | Production unavailability | 2024-01-25 18:00:00 | 2024-01-11 00:40:00 | Unplanned | 2024-01-26 10:41:02 | MW | 10.00000 | 129.00000 | 139.00000 | Fossil Gas | 10X1001A1001A094 | INESCO WKK | |
220 | 0000000000000000000000217_004 | Ineos oxide utilities NV | Dismissed | Production unavailability | 2024-01-25 18:00:00 | 2024-01-11 00:40:00 | Unplanned | 2024-01-27 07:34:16 | MW | 10.00000 | 129.00000 | 139.00000 | Fossil Gas | 10X1001A1001A094 | INESCO WKK |
ID | Nachrichten ID | Marktteilnehmer Name | Ereignisstatus | Ereignis Start | Ereignis Stop | Veröffentlichungsdatum / -zeit | Bemerkungen | |
---|---|---|---|---|---|---|---|---|
×
|
×
|
×
| ||||||
14 | 0000000000000000000000012_002 | Swissgrid AG | Dismissed | 2024-02-20 04:00:00 | 2024-02-21 19:00:00 | 2024-02-14 17:40:34 | Information: At the request of the Swiss supervisory authority ElCom, Swissgrid (Swiss TSO) will coordinate an energy reserve test with hydroelectric reserve, thermal reserve power plant and emergency power groups between 20/02/2024 04:00 and 21/02/2024 19:00. During this period, an excess of approx. 1’452.80 MWh will be fed into the grid, which may have an impact on prices. | |
13 | 0000000000000000000000013_001 | Swissgrid AG | Inactive | 2024-02-20 04:00:00 | 2024-02-21 19:00:00 | 2024-02-14 17:27:59 | UPDATE (reduced amount of energy) Information: At the request of the Swiss supervisory authority ElCom, Swissgrid (Swiss TSO) will coordinate an energy reserve test with hydroelectric reserve, thermal reserve power plant and emergency power groups between 20/02/2024 04:00 and 21/02/2024 19:00. During this period, an excess of approx. 966.5 MWh will be fed into the grid, which may have an impact on prices. | |
12 | 0000000000000000000000012_001 | Swissgrid AG | Dismissed | 2024-02-20 04:00:00 | 2024-02-21 19:00:00 | 2024-02-13 15:04:43 | Information: At the request of the Swiss supervisory authority ElCom, Swissgrid (Swiss TSO) will coordinate an energy reserve test with hydroelectric reserve, thermal reserve power plant and emergency power groups between 20/02/2024 04:00 and 21/02/2024 19:00. During this period, an excess of approx. 1’452.80 MWh will be fed into the grid, which may have an impact on prices. | |
11 | 0000000000000000000000011_001 | Swissgrid AG | Inactive | 2022-12-01 00:00:00 | 2023-05-15 23:55:00 | 2022-10-25 13:42:46 | Information about the Swiss hydropower reserve administrated by Swissgrid according to the Swiss Ordinance on the establishment of a hydropower reserve is available on our website. Today Swissgrid procured a total energy volume of 400 GWh for the coming winter period (01 December 2022 until 15 May 2023). See https://www.swissgrid.ch/en/home/newsroom/newsfeed/20221025-01.html | |
10 | 0000000000000000000000010_001 | Swissgrid AG | Inactive | 2020-12-21 00:00:00 | 2022-01-05 00:00:00 | 2021-12-23 09:12:31 | A temporary price Cap and Floor was introduced for Swiss offers in TERRE. From delivery period of 21.12.2020 00:00 onwards the offers prices in TERRE from Switzerland have been limited to +/- 999 EUR/MWh. The temporary price Cap and Floor will be removed as of 05.01.2022. For delivery periods from 05.01.2022 00:00 onwards, the relevant price Cap and Floor will be +/- 9’999 EUR/MWh. |