65 | 0000000000000000000000059_002 | MET Speicher GmbH | Dismissed | Withdrawal unavailability | 2022-09-27 06:00:00 | 2022-10-18 14:00:00 | Planned | 2022-05-19 14:04:13 | kWh/h | 209488.00000 | 209489.00000 | 418977.00000 | 21YNL----TTF---1 | UGS Etzel-ESE MET | |
66 | 0000000000000000000000060_002 | MET Speicher GmbH | Dismissed | Injection unavailability | 2022-09-27 06:00:00 | 2022-10-18 14:00:00 | Planned | 2022-05-19 14:04:59 | kWh/h | 127737.00000 | 127737.00000 | 255474.00000 | 21YNL----TTF---1 | UGS Etzel-ESE MET | |
69 | 0000000000000000000000038_003 | MET Speicher GmbH | Dismissed | Storage unavailability | 2022-10-09 06:00:00 | 2022-10-17 18:00:00 | Planned | 2022-05-27 07:27:36 | GWh | 1485.00000 | 0.00000 | 1485.00000 | 37Y005053MH0000R | UGS Etzel-ESE MET | |
72 | 0000000000000000000000048_002 | MET Speicher GmbH | Dismissed | Storage unavailability | 2022-10-18 06:00:00 | 2022-11-11 16:00:00 | Planned | 2022-10-13 06:22:49 | GWh | 1461.00000 | 0.00000 | 1461.00000 | 37Y005053MH0000R | UGS Reckrod | |
75 | 0000000000000000000000075_001 | MET Speicher GmbH | Dismissed | Withdrawal unavailability | 2023-02-10 08:00:00 | 2023-03-15 08:00:00 | Planned | 2022-11-11 15:55:15 | kWh/h | 85500.00000 | 1829500.00000 | 1915000.00000 | 37Y005053MH0000R | UGS Etzel-ESE MET | |
76 | 0000000000000000000000076_001 | MET Speicher GmbH | Dismissed | Storage unavailability | 2023-02-10 08:00:00 | 2023-03-15 08:00:00 | Planned | 2022-11-11 15:55:29 | GWh | 17.00000 | 1425.00000 | 1442.00000 | 37Y005053MH0000R | UGS Etzel-ESE MET | |
77 | 0000000000000000000000077_001 | MET Speicher GmbH | Dismissed | Withdrawal unavailability | 2023-03-15 08:00:00 | 2023-04-04 16:00:00 | Planned | 2022-11-11 15:55:50 | kWh/h | 155500.00000 | 1759500.00000 | 1915000.00000 | 37Y005053MH0000R | UGS Etzel-ESE MET | |
78 | 0000000000000000000000078_001 | MET Speicher GmbH | Dismissed | Storage unavailability | 2023-03-15 08:00:00 | 2023-04-04 16:00:00 | Planned | 2022-11-11 15:56:03 | GWh | 32.00000 | 1410.00000 | 1442.00000 | 37Y005053MH0000R | UGS Etzel-ESE MET | |
79 | 0000000000000000000000079_001 | MET Speicher GmbH | Dismissed | Withdrawal unavailability | 2023-04-04 16:00:00 | 2023-05-24 16:00:00 | Planned | 2022-11-11 15:56:21 | kWh/h | 70000.00000 | 1845000.00000 | 1915000.00000 | 37Y005053MH0000R | UGS Etzel-ESE MET | |
80 | 0000000000000000000000080_001 | MET Speicher GmbH | Dismissed | Storage unavailability | 2023-04-04 16:00:00 | 2023-05-24 16:00:00 | Planned | 2022-11-11 15:56:34 | GWh | 15.00000 | 1427.00000 | 1442.00000 | 37Y005053MH0000R | UGS Etzel-ESE MET | |
17 | 0000000000000000000000016_002 | astora GmbH and Co. KG | Inactive | Injection unavailability | 2020-11-02 08:00:00 | 2020-12-11 18:00:00 | Planned | 2020-06-10 09:41:22 | KWh/h | 14365000.00000 | 0.00000 | 14365000.00000 | 37Z0000000052293 | Rehden natural gas storage facility | |
20 | 0000000000000000000000020_001 | astora GmbH and Co. KG | Inactive | Injection unavailability | 2021-10-04 06:00:00 | 2021-10-15 18:00:00 | Planned | 2021-05-25 12:09:00 | KWh/h | 14365000.00000 | 0.00000 | 14365000.00000 | 37Z0000000052293 | Rehden natural gas storage facility | |
21 | 0000000000000000000000021_001 | astora GmbH and Co. KG | Inactive | Withdrawal unavailability | 2021-10-04 06:00:00 | 2021-10-15 18:00:00 | Planned | 2021-05-26 19:21:51 | KWh/h | 22100000.00000 | 0.00000 | 22100000.00000 | 37Z0000000052293 | Rehden natural gas storage facility | |
23 | 0000000000000000000000023_001 | astora GmbH and Co. KG | Inactive | Injection unavailability | 2021-10-19 16:00:00 | 2021-10-26 16:00:00 | Planned | 2021-05-28 08:11:06 | KWh/h | 2066166.00000 | 2066166.00000 | 4132332.00000 | 37Y701133MH0000P | UGS Haidach - Astora - Injection | |
24 | 0000000000000000000000022_002 | astora GmbH and Co. KG | Inactive | Injection unavailability | 2021-10-26 16:00:00 | 2021-11-17 22:00:00 | Planned | 2021-05-28 08:18:49 | KWh/h | 1033083.00000 | 3099249.00000 | 4132332.00000 | 37Y701133MH0000P | UGS Haidach - Astora - Injection | |
26 | 0000000000000000000000025_002 | astora GmbH and Co. KG | Inactive | Injection unavailability | 2021-10-04 07:00:00 | 2021-10-19 16:00:00 | Planned | 2021-05-30 15:14:10 | KWh/h | 4132332.00000 | 0.00000 | 4132332.00000 | 37Y701133MH0000P | UGS Haidach - Astora - Injection | |
29 | 0000000000000000000000027_003 | astora GmbH and Co. KG | Inactive | Withdrawal unavailability | 2021-10-04 07:00:00 | 2021-10-19 16:00:00 | Planned | 2021-06-04 12:43:09 | kWh/h | 4357733.00000 | 0.00000 | 4357733.00000 | 37Y701133MH0000P | UGS Haidach - Astora - Withdrawal | |
30 | 0000000000000000000000030_001 | astora GmbH and Co. KG | Inactive | Injection unavailability | 2021-06-07 07:00:00 | 2021-06-09 16:00:00 | Planned | 2021-06-04 12:48:20 | kWh/h | 4132332.00000 | 0.00000 | 4132332.00000 | 37Y701133MH0000P | UGS Haidach - Astora - Injection | |
31 | 0000000000000000000000031_001 | astora GmbH and Co. KG | Inactive | Withdrawal unavailability | 2021-06-07 07:00:00 | 2021-06-09 16:00:00 | Planned | 2021-06-07 22:59:18 | kWh/h | 4357733.00000 | 0.00000 | 4357733.00000 | 37Y701133MH0000P | UGS Haidach - Astora - Withdrawal | |
32 | 0000000000000000000000032_001 | MET Speicher GmbH | Inactive | Injection unavailability | 2022-01-03 08:00:00 | 2022-01-16 16:00:00 | Planned | 2022-01-03 16:51:54 | kWh/h | 750750.00000 | 1524250.00000 | 2275000.00000 | 37Y005053MH0000R | UGS Etzel-ESE MET |
ID | Message ID | Market Participant Name | Event Status | Type of Event | Event Start | Event Stop | Type of Unavailability | Publication date/time | Unit of Measurement | Unavailable Capacity | Available Capacity | Installed Capacity | Fuel Type | Bidding Zone | Affected Asset Name | |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
×
|
×
|
×
| ||||||||||||||
92 | 0000000000000000000000092_001 | Stadtwerke Rostock AG | Inactive | Production unavailability | 2022-04-18 00:00:00 | 2022-05-27 23:55:00 | Planned | 2022-04-19 12:24:57 | MW | 36.00000 | 72.00000 | 108.00000 | Fossil Gas | 11XSWROSTOCK---Y | Rostock Marienehe Produktionsanlage | |
93 | 0000000000000000000000093_001 | Stadtwerke Rostock AG | Inactive | Production unavailability | 2022-05-28 00:00:00 | 2022-06-20 23:55:00 | Planned | 2022-05-20 05:42:18 | MW | 36.00000 | 72.00000 | 108.00000 | Fossil Gas | 11XSWROSTOCK---Y | Rostock Marienehe Produktionsanlage | |
95 | 0000000000000000000000095_001 | Stadtwerke Rostock AG | Inactive | Production unavailability | 2022-06-10 00:00:00 | 2022-06-20 23:55:00 | Planned | 2022-06-09 05:36:11 | MW | 108.00000 | 0.00000 | 108.00000 | Fossil Gas | 11XSWROSTOCK---Y | Rostock Marienehe Produktionsanlage | |
97 | 0000000000000000000000097_001 | Electrica Energie Verde 1 SRL | Inactive | Production unavailability | 2022-11-07 10:00:00 | 2022-11-07 16:00:00 | Planned | 2022-09-20 08:51:32 | MW | 2.38000 | 4.42000 | 7.50000 | Solar | 10YRO-TEL------P | CEF Stanesti | |
98 | 0000000000000000000000098_001 | Electrica Energie Verde 1 SRL | Inactive | Production unavailability | 2022-11-08 10:00:00 | 2022-11-08 16:00:00 | Planned | 2022-09-20 08:57:20 | MW | 2.38000 | 4.42000 | 7.50000 | Solar | 10YRO-TEL------P | CEF Stanesti | |
99 | 0000000000000000000000099_001 | Electrica Energie Verde 1 SRL | Inactive | Production unavailability | 2022-11-09 10:00:00 | 2022-11-09 16:00:00 | Planned | 2022-09-20 09:00:13 | MW | 2.38000 | 4.42000 | 7.50000 | Solar | 10YRO-TEL------P | CEF Stanesti | |
100 | 0000000000000000000000100_001 | Electrica Energie Verde 1 SRL | Inactive | Production unavailability | 2022-11-10 10:00:00 | 2022-11-10 14:00:00 | Planned | 2022-09-20 09:05:04 | MW | 6.80000 | 0.00000 | 7.50000 | Solar | 10XRO-TEL------2 | CEF Stanesti | |
101 | 0000000000000000000000101_001 | Stadtwerke Rostock AG | Inactive | Production unavailability | 2022-10-04 14:00:00 | 2022-10-14 23:55:00 | Unplanned | 2022-10-04 12:33:40 | MW | 36.00000 | 72.00000 | 108.00000 | Fossil Gas | 11XSWROSTOCK---Y | Rostock Marienehe Produktionsanlage | |
102 | 0000000000000000000000102_001 | Ineos oxide utilities NV | Inactive | Production unavailability | 2023-08-28 00:00:00 | 2023-11-07 00:00:00 | Planned | 2023-01-30 09:43:50 | MW | 50.00000 | 89.00000 | 139.00000 | Fossil Gas | 10X1001A1001A094 | INESCO WKK | |
103 | 0000000000000000000000103_001 | Ineos oxide utilities NV | Inactive | Production unavailability | 2023-09-04 00:00:00 | 2023-09-23 00:00:00 | Planned | 2023-01-30 09:59:15 | MW | 46.00000 | 43.00000 | 139.00000 | Fossil Gas | 10X1001A1001A094 | INESCO WKK | |
104 | 0000000000000000000000104_001 | Ineos oxide utilities NV | Inactive | Production unavailability | 2023-10-02 00:00:00 | 2023-10-28 00:00:00 | Planned | 2023-01-30 10:00:55 | MW | 46.00000 | 43.00000 | 139.00000 | Fossil Gas | 10X1001A1001A094 | INESCO WKK | |
105 | 0000000000000000000000105_001 | Ineos oxide utilities NV | Inactive | Production unavailability | 2023-02-05 12:15:00 | 2023-02-07 00:00:00 | Unplanned | 2023-02-05 11:21:51 | MW | 0.00000 | 139.00000 | 139.00000 | Fossil Gas | 10X1001A1001A094 | INESCO WKK | |
111 | 0000000000000000000000111_001 | Stadtwerke Rostock AG | Inactive | Production unavailability | 2023-03-16 06:30:00 | 2023-03-17 23:55:00 | Planned | 2023-03-15 08:39:20 | MW | 36.00000 | 72.00000 | 108.00000 | Fossil Gas | 11XSWROSTOCK---Y | Rostock Marienehe Produktionsanlage | |
114 | 0000000000000000000000114_001 | Ineos oxide utilities NV | Inactive | Production unavailability | 2023-03-20 15:00:00 | 2023-03-24 00:00:00 | Planned | 2023-03-20 14:09:30 | MW | 88.00000 | 51.00000 | 139.00000 | Fossil Gas | 10X1001A1001A094 | INESCO WKK | |
116 | 0000000000000000000000116_001 | Ineos oxide utilities NV | Inactive | Production unavailability | 2023-03-23 01:40:00 | 2023-03-23 05:00:00 | Unplanned | 2023-03-23 01:30:24 | MW | 96.00000 | 43.00000 | 139.00000 | Fossil Gas | 10X1001A1001A094 | INESCO WKK | |
117 | 0000000000000000000000117_001 | Ineos oxide utilities NV | Inactive | Production unavailability | 2023-03-23 02:45:00 | 2023-03-23 05:00:00 | Planned | 2023-03-23 02:29:13 | MW | 139.00000 | 0.00000 | 139.00000 | Fossil Gas | 10X1001A1001A094 | INESCO WKK | |
125 | 0000000000000000000000124_002 | Ineos oxide utilities NV | Inactive | Production unavailability | 2023-04-16 00:30:00 | 2023-04-16 06:00:00 | Unplanned | 2023-04-15 22:48:51 | MW | 96.00000 | 43.00000 | 139.00000 | Fossil Gas | 10X1001A1001A094 | INESCO WKK | |
136 | 0000000000000000000000134_003 | Ineos oxide utilities NV | Inactive | Production unavailability | 2023-05-04 20:10:00 | 2023-05-20 00:00:00 | Unplanned | 2023-05-12 08:58:37 | MW | 4.50000 | 134.50000 | 139.00000 | Fossil Gas | 10X1001A1001A094 | INESCO WKK | |
138 | 0000000000000000000000137_002 | Ineos oxide utilities NV | Inactive | Production unavailability | 2023-05-13 21:00:00 | 2023-05-17 00:00:00 | Unplanned | 2023-05-14 16:02:25 | MW | 30.00000 | 109.00000 | 139.00000 | Fossil Gas | 10X1001A1001A094 | INESCO WKK | |
141 | 0000000000000000000000141_001 | Stadtwerke Rostock AG | Inactive | Production unavailability | 2023-06-02 00:00:00 | 2023-06-11 23:55:00 | Planned | 2023-05-25 08:07:11 | MW | 108.00000 | 0.00000 | 108.00000 | Fossil Gas | 11XSWROSTOCK---Y | Rostock Marienehe Produktionsanlage |
ID | Message ID | Market Participant Name | Event Status | Event Start | Event Stop | Publication date/time | Remarks | |
---|---|---|---|---|---|---|---|---|
×
|
×
|
×
| ||||||
12 | 0000000000000000000000012_001 | Swissgrid AG | Dismissed | 2024-02-20 04:00:00 | 2024-02-21 19:00:00 | 2024-02-13 15:04:43 | Information: At the request of the Swiss supervisory authority ElCom, Swissgrid (Swiss TSO) will coordinate an energy reserve test with hydroelectric reserve, thermal reserve power plant and emergency power groups between 20/02/2024 04:00 and 21/02/2024 19:00. During this period, an excess of approx. 1’452.80 MWh will be fed into the grid, which may have an impact on prices. | |
14 | 0000000000000000000000012_002 | Swissgrid AG | Dismissed | 2024-02-20 04:00:00 | 2024-02-21 19:00:00 | 2024-02-14 17:40:34 | Information: At the request of the Swiss supervisory authority ElCom, Swissgrid (Swiss TSO) will coordinate an energy reserve test with hydroelectric reserve, thermal reserve power plant and emergency power groups between 20/02/2024 04:00 and 21/02/2024 19:00. During this period, an excess of approx. 1’452.80 MWh will be fed into the grid, which may have an impact on prices. | |
10 | 0000000000000000000000010_001 | Swissgrid AG | Inactive | 2020-12-21 00:00:00 | 2022-01-05 00:00:00 | 2021-12-23 09:12:31 | A temporary price Cap and Floor was introduced for Swiss offers in TERRE. From delivery period of 21.12.2020 00:00 onwards the offers prices in TERRE from Switzerland have been limited to +/- 999 EUR/MWh. The temporary price Cap and Floor will be removed as of 05.01.2022. For delivery periods from 05.01.2022 00:00 onwards, the relevant price Cap and Floor will be +/- 9’999 EUR/MWh. | |
11 | 0000000000000000000000011_001 | Swissgrid AG | Inactive | 2022-12-01 00:00:00 | 2023-05-15 23:55:00 | 2022-10-25 13:42:46 | Information about the Swiss hydropower reserve administrated by Swissgrid according to the Swiss Ordinance on the establishment of a hydropower reserve is available on our website. Today Swissgrid procured a total energy volume of 400 GWh for the coming winter period (01 December 2022 until 15 May 2023). See https://www.swissgrid.ch/en/home/newsroom/newsfeed/20221025-01.html | |
13 | 0000000000000000000000013_001 | Swissgrid AG | Inactive | 2024-02-20 04:00:00 | 2024-02-21 19:00:00 | 2024-02-14 17:27:59 | UPDATE (reduced amount of energy) Information: At the request of the Swiss supervisory authority ElCom, Swissgrid (Swiss TSO) will coordinate an energy reserve test with hydroelectric reserve, thermal reserve power plant and emergency power groups between 20/02/2024 04:00 and 21/02/2024 19:00. During this period, an excess of approx. 966.5 MWh will be fed into the grid, which may have an impact on prices. |