ID | Nachrichten ID | Marktteilnehmer Name | Ereignisstatus | Ereignistyp | Ereignis Start | Ereignis Stop | Typ der Nichtverfügbarkeit | Veröffentlichungsdatum / -zeit | Maßeinheit | Nicht verfügbare Kapazität | Verfügbare Kapazität | Technische Kapazität | Bilanzierungszone 1 | Name der Anlage | |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
×
|
×
|
×
| |||||||||||||
20 | 0000000000000000000000020_001 | astora GmbH and Co. KG | Inactive | Injection unavailability | 2021-10-04 06:00:00 | 2021-10-15 18:00:00 | Planned | 2021-05-25 12:09:00 | KWh/h | 14365000.00000 | 0.00000 | 14365000.00000 | 37Z0000000052293 | Rehden natural gas storage facility | |
21 | 0000000000000000000000021_001 | astora GmbH and Co. KG | Inactive | Withdrawal unavailability | 2021-10-04 06:00:00 | 2021-10-15 18:00:00 | Planned | 2021-05-26 19:21:51 | KWh/h | 22100000.00000 | 0.00000 | 22100000.00000 | 37Z0000000052293 | Rehden natural gas storage facility | |
22 | 0000000000000000000000022_001 | astora GmbH and Co. KG | Dismissed | Injection unavailability | 2021-10-26 16:00:00 | 2021-11-17 22:00:00 | Planned | 2021-05-28 08:06:38 | KWh/h | 3099249.00000 | 1033083.00000 | 4132332.00000 | 37Y701133MH0000P | UGS Haidach - Astora - Injection | |
23 | 0000000000000000000000023_001 | astora GmbH and Co. KG | Inactive | Injection unavailability | 2021-10-19 16:00:00 | 2021-10-26 16:00:00 | Planned | 2021-05-28 08:11:06 | KWh/h | 2066166.00000 | 2066166.00000 | 4132332.00000 | 37Y701133MH0000P | UGS Haidach - Astora - Injection | |
24 | 0000000000000000000000022_002 | astora GmbH and Co. KG | Inactive | Injection unavailability | 2021-10-26 16:00:00 | 2021-11-17 22:00:00 | Planned | 2021-05-28 08:18:49 | KWh/h | 1033083.00000 | 3099249.00000 | 4132332.00000 | 37Y701133MH0000P | UGS Haidach - Astora - Injection | |
25 | 0000000000000000000000025_001 | astora GmbH and Co. KG | Dismissed | Offshore pipeline unavailability | 2021-10-04 07:00:00 | 2021-10-19 16:00:00 | Planned | 2021-05-29 06:17:08 | KWh/h | 4132332.00000 | 0.00000 | 4132332.00000 | 37Y701133MH0000P | UGS Haidach - Astora - Injection | |
26 | 0000000000000000000000025_002 | astora GmbH and Co. KG | Inactive | Injection unavailability | 2021-10-04 07:00:00 | 2021-10-19 16:00:00 | Planned | 2021-05-30 15:14:10 | KWh/h | 4132332.00000 | 0.00000 | 4132332.00000 | 37Y701133MH0000P | UGS Haidach - Astora - Injection | |
27 | 0000000000000000000000027_001 | astora GmbH and Co. KG | Dismissed | Withdrawal unavailability | 2021-10-04 07:00:00 | 2021-10-19 16:00:00 | Planned | 2021-05-30 15:20:09 | KWh/h | 4357733.00000 | 0.00000 | 4357733.00000 | 37Y701133MH0000P | UGS Haidach - Astora - Withdrawal | |
28 | 0000000000000000000000027_002 | astora GmbH and Co. KG | Dismissed | Withdrawal unavailability | 2021-10-04 07:00:00 | 2021-10-19 16:05:00 | Planned | 2021-06-01 06:06:56 | KWh/h | 4357733.00000 | 0.00000 | 4357733.00000 | 37Y701133MH0000P | UGS Haidach - Astora - Withdrawal | |
29 | 0000000000000000000000027_003 | astora GmbH and Co. KG | Inactive | Withdrawal unavailability | 2021-10-04 07:00:00 | 2021-10-19 16:00:00 | Planned | 2021-06-04 12:43:09 | kWh/h | 4357733.00000 | 0.00000 | 4357733.00000 | 37Y701133MH0000P | UGS Haidach - Astora - Withdrawal | |
30 | 0000000000000000000000030_001 | astora GmbH and Co. KG | Inactive | Injection unavailability | 2021-06-07 07:00:00 | 2021-06-09 16:00:00 | Planned | 2021-06-04 12:48:20 | kWh/h | 4132332.00000 | 0.00000 | 4132332.00000 | 37Y701133MH0000P | UGS Haidach - Astora - Injection | |
31 | 0000000000000000000000031_001 | astora GmbH and Co. KG | Inactive | Withdrawal unavailability | 2021-06-07 07:00:00 | 2021-06-09 16:00:00 | Planned | 2021-06-07 22:59:18 | kWh/h | 4357733.00000 | 0.00000 | 4357733.00000 | 37Y701133MH0000P | UGS Haidach - Astora - Withdrawal | |
35 | 0000000000000000000000035_001 | MET Speicher GmbH | Dismissed | Storage unavailability | 2022-03-17 18:00:00 | 2022-05-13 16:00:00 | Planned | 2022-01-03 16:53:00 | GWh | 11.75600 | 1473.24400 | 1485.00000 | 37Y005053MH0000R | UGS Etzel-ESE MET | |
36 | 0000000000000000000000036_001 | MET Speicher GmbH | Dismissed | Withdrawal unavailability | 2022-03-17 18:00:00 | 2022-05-13 16:00:00 | Planned | 2022-01-03 16:53:15 | kWh/h | 95750.00000 | 1819250.00000 | 1915000.00000 | 37Y005053MH0000R | UGS Etzel-ESE MET | |
39 | 0000000000000000000000039_001 | MET Speicher GmbH | Inactive | Injection unavailability | 2022-05-26 06:00:00 | 2022-07-22 18:00:00 | Planned | 2022-03-17 08:54:32 | GWh | 68.44000 | 1373.56000 | 1442.00000 | 37Y005053MH0000R | UGS Etzel-ESE MET | |
40 | 0000000000000000000000040_001 | MET Speicher GmbH | Inactive | Withdrawal unavailability | 2022-05-26 06:00:00 | 2022-07-22 18:00:00 | Planned | 2022-03-17 08:54:49 | GWh | 24.97000 | 1417.03000 | 1442.00000 | 37Y005053MH0000R | UGS Etzel-ESE MET | |
41 | 0000000000000000000000041_001 | MET Speicher GmbH | Inactive | Withdrawal unavailability | 2022-03-23 06:00:00 | 2022-03-24 18:00:00 | Planned | 2022-03-17 08:23:25 | kWh/h | 2063000.00000 | 0.00000 | 2063000.00000 | 37Y005053MH0000R | UGS Reckrod | |
42 | 0000000000000000000000042_001 | MET Speicher GmbH | Inactive | Injection unavailability | 2022-03-23 06:00:00 | 2022-03-24 18:00:00 | Planned | 2022-03-17 08:23:50 | kWh/h | 957000.00000 | 170000.00000 | 1127000.00000 | 37Y005053MH0000R | UGS Reckrod | |
49 | 0000000000000000000000035_002 | MET Speicher GmbH | Inactive | Storage unavailability | 2022-03-17 18:00:00 | 2022-05-20 16:00:00 | Planned | 2022-04-28 13:06:39 | GWh | 11.75600 | 1473.24400 | 1485.00000 | 37Y005053MH0000R | UGS Etzel-ESE MET | |
50 | 0000000000000000000000036_002 | MET Speicher GmbH | Inactive | Withdrawal unavailability | 2022-03-17 18:00:00 | 2022-05-20 16:00:00 | Planned | 2022-04-28 13:07:34 | kWh/h | 95750.00000 | 1819250.00000 | 1915000.00000 | 37Y005053MH0000R | UGS Etzel-ESE MET |
ID | Nachrichten ID | Marktteilnehmer Name | Ereignisstatus | Ereignistyp | Ereignis Start | Ereignis Stop | Typ der Nichtverfügbarkeit | Veröffentlichungsdatum / -zeit | Maßeinheit | Nicht verfügbare Kapazität | Verfügbare Kapazität | Installierte Kapazität | Kraftstofftyp | Gebotszone | Name der Anlage | |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
×
|
×
|
×
| ||||||||||||||
76 | 0000000000000000000000076_001 | Energie Wasser Bern | Inactive | Production unavailability | 2021-09-01 00:00:00 | 2021-10-01 00:00:00 | Planned | 2021-07-08 08:14:13 | MW | 43.50000 | 0.00000 | 43.50000 | Fossil Gas | 10YCH-SWISSGRIDZ | GUD Energiezentrale Forsthaus | |
77 | 0000000000000000000000077_001 | Energieversorgung Schwerin GmbH und Co. Erzeugung KG | Inactive | Production unavailability | 2021-05-01 00:00:00 | 2023-04-01 00:00:00 | Planned | 2021-07-08 09:16:19 | MW | 40.00000 | 0.00000 | 40.00000 | Fossil Gas | 10YDE-VE-------2 | HKW Süd | |
80 | 0000000000000000000000080_001 | Stadtwerke Rostock AG | Inactive | Production unavailability | 2021-06-09 00:00:00 | 2021-08-01 00:00:00 | Planned | 2021-07-15 10:08:48 | MW | 108.00000 | 0.00000 | 108.00000 | Fossil Gas | 11XSWROSTOCK---Y | Rostock Marienehe Produktionsanlage | |
89 | 0000000000000000000000089_001 | Electrica Energie Verde 1 SRL | Inactive | Production unavailability | 2022-02-01 08:00:00 | 2022-02-01 16:00:00 | Planned | 2022-01-27 11:55:01 | MW | 6.80000 | 0.00000 | 7.50000 | Solar | 10YRO-TEL------P | CEF Stanesti | |
90 | 0000000000000000000000090_001 | Energie Wasser Bern | Inactive | Production unavailability | 2022-09-05 07:00:00 | 2022-09-23 17:00:00 | Planned | 2022-02-08 08:38:49 | MW | 43.50000 | 0.00000 | 43.50000 | Fossil Gas | 10YCH-SWISSGRIDZ | GUD Energiezentrale Forsthaus | |
91 | 0000000000000000000000091_001 | Stadtwerke Rostock AG | Inactive | Production unavailability | 2022-04-18 00:00:00 | 2022-05-27 23:55:00 | Planned | 2022-04-19 12:16:35 | MW | 36.00000 | 72.00000 | 36.00000 | Fossil Gas | 11XSWROSTOCK---Y | Rostock Marienehe Produktionsanlage | |
92 | 0000000000000000000000092_001 | Stadtwerke Rostock AG | Inactive | Production unavailability | 2022-04-18 00:00:00 | 2022-05-27 23:55:00 | Planned | 2022-04-19 12:24:57 | MW | 36.00000 | 72.00000 | 108.00000 | Fossil Gas | 11XSWROSTOCK---Y | Rostock Marienehe Produktionsanlage | |
93 | 0000000000000000000000093_001 | Stadtwerke Rostock AG | Inactive | Production unavailability | 2022-05-28 00:00:00 | 2022-06-20 23:55:00 | Planned | 2022-05-20 05:42:18 | MW | 36.00000 | 72.00000 | 108.00000 | Fossil Gas | 11XSWROSTOCK---Y | Rostock Marienehe Produktionsanlage | |
95 | 0000000000000000000000095_001 | Stadtwerke Rostock AG | Inactive | Production unavailability | 2022-06-10 00:00:00 | 2022-06-20 23:55:00 | Planned | 2022-06-09 05:36:11 | MW | 108.00000 | 0.00000 | 108.00000 | Fossil Gas | 11XSWROSTOCK---Y | Rostock Marienehe Produktionsanlage | |
101 | 0000000000000000000000101_001 | Stadtwerke Rostock AG | Inactive | Production unavailability | 2022-10-04 14:00:00 | 2022-10-14 23:55:00 | Unplanned | 2022-10-04 12:33:40 | MW | 36.00000 | 72.00000 | 108.00000 | Fossil Gas | 11XSWROSTOCK---Y | Rostock Marienehe Produktionsanlage | |
102 | 0000000000000000000000102_001 | Ineos oxide utilities NV | Inactive | Production unavailability | 2023-08-28 00:00:00 | 2023-11-07 00:00:00 | Planned | 2023-01-30 09:43:50 | MW | 50.00000 | 89.00000 | 139.00000 | Fossil Gas | 10X1001A1001A094 | INESCO WKK | |
103 | 0000000000000000000000103_001 | Ineos oxide utilities NV | Inactive | Production unavailability | 2023-09-04 00:00:00 | 2023-09-23 00:00:00 | Planned | 2023-01-30 09:59:15 | MW | 46.00000 | 43.00000 | 139.00000 | Fossil Gas | 10X1001A1001A094 | INESCO WKK | |
104 | 0000000000000000000000104_001 | Ineos oxide utilities NV | Inactive | Production unavailability | 2023-10-02 00:00:00 | 2023-10-28 00:00:00 | Planned | 2023-01-30 10:00:55 | MW | 46.00000 | 43.00000 | 139.00000 | Fossil Gas | 10X1001A1001A094 | INESCO WKK | |
105 | 0000000000000000000000105_001 | Ineos oxide utilities NV | Inactive | Production unavailability | 2023-02-05 12:15:00 | 2023-02-07 00:00:00 | Unplanned | 2023-02-05 11:21:51 | MW | 0.00000 | 139.00000 | 139.00000 | Fossil Gas | 10X1001A1001A094 | INESCO WKK | |
106 | 0000000000000000000000106_001 | Ineos oxide utilities NV | Dismissed | Production unavailability | 2023-02-12 22:35:00 | 2023-02-13 23:55:00 | Unplanned | 2023-02-12 21:26:46 | MW | 9.00000 | 130.00000 | 139.00000 | Fossil Gas | 10X1001A1001A094 | INESCO WKK | |
107 | 0000000000000000000000106_002 | Ineos oxide utilities NV | Dismissed | Production unavailability | 2023-02-12 22:35:00 | 2023-02-13 23:55:00 | Unplanned | 2023-02-13 08:26:34 | MW | 9.00000 | 130.00000 | 139.00000 | Fossil Gas | 10X1001A1001A094 | INESCO WKK | |
108 | 0000000000000000000000108_001 | Ineos oxide utilities NV | Dismissed | Production unavailability | 2023-03-09 20:00:00 | 2023-03-10 12:00:00 | Unplanned | 2023-03-09 19:08:04 | MW | 33.00000 | 106.00000 | 139.00000 | Fossil Gas | 10X1001A1001A094 | INESCO WKK | |
109 | 0000000000000000000000108_002 | Ineos oxide utilities NV | Dismissed | Production unavailability | 2023-03-09 20:00:00 | 2023-03-10 12:00:00 | Unplanned | 2023-03-10 09:58:07 | MW | 33.00000 | 106.00000 | 139.00000 | Fossil Gas | 10X1001A1001A094 | INESCO WKK | |
110 | 0000000000000000000000108_003 | Ineos oxide utilities NV | Dismissed | Production unavailability | 2023-03-09 20:00:00 | 2023-03-10 12:00:00 | Unplanned | 2023-03-10 10:00:18 | MW | 33.00000 | 106.00000 | 139.00000 | Fossil Gas | 10X1001A1001A094 | INESCO WKK | |
111 | 0000000000000000000000111_001 | Stadtwerke Rostock AG | Inactive | Production unavailability | 2023-03-16 06:30:00 | 2023-03-17 23:55:00 | Planned | 2023-03-15 08:39:20 | MW | 36.00000 | 72.00000 | 108.00000 | Fossil Gas | 11XSWROSTOCK---Y | Rostock Marienehe Produktionsanlage |
ID | Nachrichten ID | Marktteilnehmer Name | Ereignisstatus | Ereignis Start | Ereignis Stop | Veröffentlichungsdatum / -zeit | Bemerkungen | |
---|---|---|---|---|---|---|---|---|
×
|
×
|
×
| ||||||
10 | 0000000000000000000000010_001 | Swissgrid AG | Inactive | 2020-12-21 00:00:00 | 2022-01-05 00:00:00 | 2021-12-23 09:12:31 | A temporary price Cap and Floor was introduced for Swiss offers in TERRE. From delivery period of 21.12.2020 00:00 onwards the offers prices in TERRE from Switzerland have been limited to +/- 999 EUR/MWh. The temporary price Cap and Floor will be removed as of 05.01.2022. For delivery periods from 05.01.2022 00:00 onwards, the relevant price Cap and Floor will be +/- 9’999 EUR/MWh. | |
11 | 0000000000000000000000011_001 | Swissgrid AG | Inactive | 2022-12-01 00:00:00 | 2023-05-15 23:55:00 | 2022-10-25 13:42:46 | Information about the Swiss hydropower reserve administrated by Swissgrid according to the Swiss Ordinance on the establishment of a hydropower reserve is available on our website. Today Swissgrid procured a total energy volume of 400 GWh for the coming winter period (01 December 2022 until 15 May 2023). See https://www.swissgrid.ch/en/home/newsroom/newsfeed/20221025-01.html | |
12 | 0000000000000000000000012_001 | Swissgrid AG | Dismissed | 2024-02-20 04:00:00 | 2024-02-21 19:00:00 | 2024-02-13 15:04:43 | Information: At the request of the Swiss supervisory authority ElCom, Swissgrid (Swiss TSO) will coordinate an energy reserve test with hydroelectric reserve, thermal reserve power plant and emergency power groups between 20/02/2024 04:00 and 21/02/2024 19:00. During this period, an excess of approx. 1’452.80 MWh will be fed into the grid, which may have an impact on prices. | |
14 | 0000000000000000000000012_002 | Swissgrid AG | Dismissed | 2024-02-20 04:00:00 | 2024-02-21 19:00:00 | 2024-02-14 17:40:34 | Information: At the request of the Swiss supervisory authority ElCom, Swissgrid (Swiss TSO) will coordinate an energy reserve test with hydroelectric reserve, thermal reserve power plant and emergency power groups between 20/02/2024 04:00 and 21/02/2024 19:00. During this period, an excess of approx. 1’452.80 MWh will be fed into the grid, which may have an impact on prices. | |
13 | 0000000000000000000000013_001 | Swissgrid AG | Inactive | 2024-02-20 04:00:00 | 2024-02-21 19:00:00 | 2024-02-14 17:27:59 | UPDATE (reduced amount of energy) Information: At the request of the Swiss supervisory authority ElCom, Swissgrid (Swiss TSO) will coordinate an energy reserve test with hydroelectric reserve, thermal reserve power plant and emergency power groups between 20/02/2024 04:00 and 21/02/2024 19:00. During this period, an excess of approx. 966.5 MWh will be fed into the grid, which may have an impact on prices. |