Showing 21-40 of 74 items.
 IDMessage IDMarket Participant NameEvent StatusType of EventEvent StartEvent StopType of UnavailabilityPublication date/timeUnit of MeasurementUnavailable CapacityAvailable CapacityTechnical CapacityBalancing Zone 1Affected Asset Name
 
 
 
×
×
 
×
 
 
690000000000000000000000038_003MET Speicher GmbHDismissedStorage unavailability2022-10-09 06:00:002022-10-17 18:00:00Planned2022-05-27 07:27:36GWh1485.000000.000001485.0000037Y005053MH0000RUGS Etzel-ESE MET
790000000000000000000000079_001MET Speicher GmbHDismissedWithdrawal unavailability2023-04-04 16:00:002023-05-24 16:00:00Planned2022-11-11 15:56:21kWh/h70000.000001845000.000001915000.0000037Y005053MH0000RUGS Etzel-ESE MET
850000000000000000000000079_002MET Speicher GmbHInactiveWithdrawal unavailability2023-04-04 16:00:002023-05-09 16:00:00Planned2022-11-16 16:41:38kWh/h70000.000001845000.000001915000.0000037Y005053MH0000RUGS Etzel-ESE MET
750000000000000000000000075_001MET Speicher GmbHDismissedWithdrawal unavailability2023-02-10 08:00:002023-03-15 08:00:00Planned2022-11-11 15:55:15kWh/h85500.000001829500.000001915000.0000037Y005053MH0000RUGS Etzel-ESE MET
810000000000000000000000075_002MET Speicher GmbHInactiveWithdrawal unavailability2023-02-10 08:00:002023-03-17 08:00:00Planned2022-11-16 16:37:23kWh/h85500.000001829500.000001915000.0000037Y005053MH0000RUGS Etzel-ESE MET
360000000000000000000000036_001MET Speicher GmbHDismissedWithdrawal unavailability2022-03-17 18:00:002022-05-13 16:00:00Planned2022-01-03 16:53:15kWh/h95750.000001819250.000001915000.0000037Y005053MH0000RUGS Etzel-ESE MET
500000000000000000000000036_002MET Speicher GmbHInactiveWithdrawal unavailability2022-03-17 18:00:002022-05-20 16:00:00Planned2022-04-28 13:07:34kWh/h95750.000001819250.000001915000.0000037Y005053MH0000RUGS Etzel-ESE MET
600000000000000000000000060_001MET Speicher GmbHDismissedInjection unavailability2022-09-27 06:00:002022-10-18 14:00:00Planned2022-05-16 15:32:43kWh/h127737.00000127737.00000255474.0000021YNL----TTF---1UGS Etzel-ESE MET
660000000000000000000000060_002MET Speicher GmbHDismissedInjection unavailability2022-09-27 06:00:002022-10-18 14:00:00Planned2022-05-19 14:04:59kWh/h127737.00000127737.00000255474.0000021YNL----TTF---1UGS Etzel-ESE MET
770000000000000000000000077_001MET Speicher GmbHDismissedWithdrawal unavailability2023-03-15 08:00:002023-04-04 16:00:00Planned2022-11-11 15:55:50kWh/h155500.000001759500.000001915000.0000037Y005053MH0000RUGS Etzel-ESE MET
830000000000000000000000077_002MET Speicher GmbHInactiveWithdrawal unavailability2023-03-17 08:00:002023-04-04 16:00:00Planned2022-11-16 16:40:32kWh/h155500.000001759500.000001915000.0000037Y005053MH0000RUGS Etzel-ESE MET
590000000000000000000000059_001MET Speicher GmbHDismissedWithdrawal unavailability2022-09-27 06:00:002022-10-18 14:00:00Planned2022-05-16 15:30:18kWh/h209488.00000209489.00000418977.0000021YNL----TTF---1UGS Etzel-ESE MET
650000000000000000000000059_002MET Speicher GmbHDismissedWithdrawal unavailability2022-09-27 06:00:002022-10-18 14:00:00Planned2022-05-19 14:04:13kWh/h209488.00000209489.00000418977.0000021YNL----TTF---1UGS Etzel-ESE MET
740000000000000000000000074_001MET Speicher GmbHInactiveTransmission system unavailability2023-09-20 08:00:002023-09-20 18:00:00Planned2022-11-11 14:59:13kWh/h418977.000000.00000418977.0000021YNL----TTF---1UGS Etzel-ESE MET
370000000000000000000000037_001MET Speicher GmbHInactiveOther unavailability2022-09-21 08:00:002022-09-21 18:00:00Planned2022-01-03 16:53:25kWh/h419000.000000.00000419000.0000021YNL----TTF---1UGS Etzel-ESE MET
630000000000000000000000063_001MET Speicher GmbHInactiveInjection unavailability2022-05-18 14:00:002022-05-19 06:00:00Planned2022-05-17 14:15:59kWh/h479000.00000500000.00000979000.0000037Y005053MH0000RUGS Reckrod
640000000000000000000000064_001MET Speicher GmbHDismissedInjection unavailability2022-05-19 06:00:002022-05-20 06:00:00Planned2022-05-18 13:23:03kWh/h491000.00000483000.00000974000.0000037Y005053MH0000RUGS Reckrod
670000000000000000000000064_002MET Speicher GmbHInactiveInjection unavailability2022-05-19 06:00:002022-05-21 06:00:00Planned2022-05-19 14:09:03kWh/h491000.00000483000.00000974000.0000037Y005053MH0000RUGS Reckrod
440000000000000000000000044_001MET Speicher GmbHInactiveInjection unavailability2022-07-18 06:00:002022-07-22 16:00:00Planned2022-04-25 15:19:50kWh/h515500.00000515500.000001031000.0000037Y005053MH0000RUGS Reckrod
460000000000000000000000046_001MET Speicher GmbHInactiveInjection unavailability2022-07-25 06:00:002022-07-29 16:00:00Planned2022-04-25 15:21:37kWh/h515500.00000515500.000001031000.0000037Y005053MH0000RUGS Reckrod
Showing 41-60 of 145 items.
 IDMessage IDMarket Participant NameEvent StatusType of EventEvent StartEvent StopType of UnavailabilityPublication date/timeUnit of MeasurementUnavailable CapacityAvailable CapacityInstalled CapacityFuel TypeBidding ZoneAffected Asset Name
 
 
 
×
×
 
×
 
 
 
920000000000000000000000092_001Stadtwerke Rostock AGInactiveProduction unavailability2022-04-18 00:00:002022-05-27 23:55:00Planned2022-04-19 12:24:57MW36.0000072.00000108.00000Fossil Gas11XSWROSTOCK---YRostock Marienehe Produktionsanlage
930000000000000000000000093_001Stadtwerke Rostock AGInactiveProduction unavailability2022-05-28 00:00:002022-06-20 23:55:00Planned2022-05-20 05:42:18MW36.0000072.00000108.00000Fossil Gas11XSWROSTOCK---YRostock Marienehe Produktionsanlage
1010000000000000000000000101_001Stadtwerke Rostock AGInactiveProduction unavailability2022-10-04 14:00:002022-10-14 23:55:00Unplanned2022-10-04 12:33:40MW36.0000072.00000108.00000Fossil Gas11XSWROSTOCK---YRostock Marienehe Produktionsanlage
1110000000000000000000000111_001Stadtwerke Rostock AGInactiveProduction unavailability2023-03-16 06:30:002023-03-17 23:55:00Planned2023-03-15 08:39:20MW36.0000072.00000108.00000Fossil Gas11XSWROSTOCK---YRostock Marienehe Produktionsanlage
1420000000000000000000000142_001Stadtwerke Rostock AGInactiveProduction unavailability2023-04-11 00:00:002023-06-21 23:55:00Planned2023-06-01 12:28:30MW36.0000072.00000108.00000Fossil Gas11XSWROSTOCK---YRostock Marienehe Produktionsanlage
1440000000000000000000000144_001Stadtwerke Rostock AGInactiveProduction unavailability2023-06-23 00:00:002023-08-04 23:55:00Planned2023-06-05 07:29:53MW36.0000072.00000108.00000Fossil Gas11XSWROSTOCK---YRostock Marienehe Produktionsanlage
1450000000000000000000000145_001Stadtwerke Rostock AGInactiveProduction unavailability2023-08-11 00:00:002023-09-01 23:55:00Planned2023-06-05 07:41:02MW36.0000072.00000108.00000Fossil Gas11XSWROSTOCK---YRostock Marienehe Produktionsanlage
1460000000000000000000000146_001Stadtwerke Rostock AGInactiveProduction unavailability2023-09-15 00:00:002023-09-20 23:55:00Planned2023-06-05 07:43:10MW36.0000072.00000108.00000Fossil Gas11XSWROSTOCK---YRostock Marienehe Produktionsanlage
770000000000000000000000077_001Energieversorgung Schwerin GmbH und Co. Erzeugung KGInactiveProduction unavailability2021-05-01 00:00:002023-04-01 00:00:00Planned2021-07-08 09:16:19MW40.000000.0000040.00000Fossil Gas10YDE-VE-------2HKW Süd
760000000000000000000000076_001Energie Wasser BernInactiveProduction unavailability2021-09-01 00:00:002021-10-01 00:00:00Planned2021-07-08 08:14:13MW43.500000.0000043.50000Fossil Gas10YCH-SWISSGRIDZGUD Energiezentrale Forsthaus
900000000000000000000000090_001Energie Wasser BernInactiveProduction unavailability2022-09-05 07:00:002022-09-23 17:00:00Planned2022-02-08 08:38:49MW43.500000.0000043.50000Fossil Gas10YCH-SWISSGRIDZGUD Energiezentrale Forsthaus
1570000000000000000000000157_001Energie Wasser BernActiveProduction unavailability2024-09-08 07:00:002024-09-19 17:00:00Planned2023-06-19 05:50:06MW43.500000.0000043.50000Fossil Gas10YCH-SWISSGRIDZGUD Energiezentrale Forsthaus
1580000000000000000000000158_001Energie Wasser BernActiveProduction unavailability2025-08-10 07:00:002025-09-18 17:00:00Planned2023-06-19 05:53:02MW43.500000.0000043.50000Fossil Gas10YCH-SWISSGRIDZGUD Energiezentrale Forsthaus
1030000000000000000000000103_001Ineos oxide utilities NVInactiveProduction unavailability2023-09-04 00:00:002023-09-23 00:00:00Planned2023-01-30 09:59:15MW46.0000043.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
1040000000000000000000000104_001Ineos oxide utilities NVInactiveProduction unavailability2023-10-02 00:00:002023-10-28 00:00:00Planned2023-01-30 10:00:55MW46.0000043.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
1960000000000000000000000196_001Ineos oxide utilities NVDismissedProduction unavailability2023-12-09 00:00:002024-01-01 00:00:00Planned2023-12-09 09:47:45MW46.0000093.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
1980000000000000000000000196_002Ineos oxide utilities NVInactiveProduction unavailability2023-12-09 00:00:002023-12-22 15:00:00Planned2023-12-22 18:17:40MW46.0000093.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
1020000000000000000000000102_001Ineos oxide utilities NVInactiveProduction unavailability2023-08-28 00:00:002023-11-07 00:00:00Planned2023-01-30 09:43:50MW50.0000089.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
2030000000000000000000000203_001Ineos oxide utilities NVDismissedProduction unavailability2024-01-10 00:00:002024-01-12 00:00:00Planned2024-01-05 07:43:09MW50.0000089.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
2090000000000000000000000203_002Ineos oxide utilities NVDismissedProduction unavailability2024-01-17 00:00:002024-01-19 00:00:00Planned2024-01-09 10:04:18MW50.0000089.00000139.00000Fossil Gas10X1001A1001A094INESCO WKK
Showing 1-5 of 5 items.
 IDMessage IDMarket Participant NameEvent StatusEvent StartEvent StopPublication date/timeRemarks
 
 
×
×
×
140000000000000000000000012_002Swissgrid AGDismissed2024-02-20 04:00:002024-02-21 19:00:002024-02-14 17:40:34Information: At the request of the Swiss supervisory authority ElCom, Swissgrid (Swiss TSO) will coordinate an energy reserve test with hydroelectric reserve, thermal reserve power plant and emergency power groups between 20/02/2024 04:00 and 21/02/2024 19:00. During this period, an excess of approx. 1’452.80 MWh will be fed into the grid, which may have an impact on prices.
130000000000000000000000013_001Swissgrid AGInactive2024-02-20 04:00:002024-02-21 19:00:002024-02-14 17:27:59UPDATE (reduced amount of energy)
Information: At the request of the Swiss supervisory authority ElCom, Swissgrid (Swiss TSO) will coordinate an energy reserve test with hydroelectric reserve, thermal reserve power plant and emergency power groups between 20/02/2024 04:00 and 21/02/2024 19:00. During this period, an excess of approx. 966.5 MWh will be fed into the grid, which may have an impact on prices.
120000000000000000000000012_001Swissgrid AGDismissed2024-02-20 04:00:002024-02-21 19:00:002024-02-13 15:04:43Information: At the request of the Swiss supervisory authority ElCom, Swissgrid (Swiss TSO) will coordinate an energy reserve test with hydroelectric reserve, thermal reserve power plant and emergency power groups between 20/02/2024 04:00 and 21/02/2024 19:00. During this period, an excess of approx. 1’452.80 MWh will be fed into the grid, which may have an impact on prices.
110000000000000000000000011_001Swissgrid AGInactive2022-12-01 00:00:002023-05-15 23:55:002022-10-25 13:42:46Information about the Swiss hydropower reserve administrated by Swissgrid according to the Swiss Ordinance on the establishment of a hydropower reserve is available on our website. Today Swissgrid procured a total energy volume of 400 GWh for the coming winter period (01 December 2022 until 15 May 2023). See https://www.swissgrid.ch/en/home/newsroom/newsfeed/20221025-01.html
100000000000000000000000010_001Swissgrid AGInactive2020-12-21 00:00:002022-01-05 00:00:002021-12-23 09:12:31A temporary price Cap and Floor was introduced for Swiss offers in TERRE. From delivery period of 21.12.2020 00:00 onwards the offers prices in TERRE from Switzerland have been limited to +/- 999 EUR/MWh.

The temporary price Cap and Floor will be removed as of 05.01.2022. For delivery periods from 05.01.2022 00:00 onwards, the relevant price Cap and Floor will be +/- 9’999 EUR/MWh.